Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow

UPRERARegistered

Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow is a RERA-registered residential project by U.P. Awas Evam Vikas Parishad in Lucknow (RERA ID UPRERAPRJ290595). Registered with a completion deadline of 31 Dec 2025.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ290595
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryU.P. Awas Evam Vikas Parishad
Proposed start1 Apr 2021
Project duration57 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompetent authority
Applicant address104 Mahatma Gandhi Marg, Lucknow
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    258/SE(HQ)/280

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered15 Jul 2020
Original completion31 Dec 2025
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹8,160
Sanctioning authorityU.P. Awas Evam Vikas Parishad

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors96 · 2 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK9623
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · 1 BHK44823
2 · 1 BHK44823
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Sanjeev Kashyap
License 2007-079
Architect Planing Unit-4, Neelgiri Complex Indira Nagar Lucknow
Engineer
MR. YOGESH KUMAR
CD-14, U.P.A.V.P. , SECTOR-9, VRINDAVAN YOJNA ,LUCKNOW
Contractor
NA
NA
Sr.Development work declared to RERA
1Demarcation of Plots
Boundary wall with Brick work.
2Boundary Wall
Brick work in boundary will be done at the time of start of work.
3Road Work
B.C./ C.C. /Interlocking block
4Footpaths
Interlocking blocks
5Water Supply Including Drinking Water Facilities
Internal water supply system will be developed
6Sewer System
Sewer System with under ground hump pipe will be developed
7Drain
Open drain in Brick work.
8Parks
Park will be developed as per approved Layout Plan
9Tree Planting
Tree Planting will be done in park
10Design For Electric Supply Including Street Lighting
Round MS Electric Pole and LED Light as Street Light will be provided inside the campus
11Community Buildings
Not applicable
12Treatment and Disposal System of Sewage and Sullage water
In S.T.P.
13Solid Waste Management And Disposal System
door to door garbage collection throw R.W.A./ Local body
14Water Conservation System
Not applicable
15Energy Management System Including Use of Renewable Energy
Not applicable
16Fire Protection And Fire Safety System
Will be provided as per norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not applicable
18Emergency Evacuation Services
Not applicable
19Other Miscellaneous Work
Not applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 31 Dec 2025.

Sanctioned by U.P. Awas Evam Vikas Parishad · 816 sqm of land · an approved plan of 2 blocks and 96 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
258/SE(HQ)/28022 Jan 202031 Dec 202531 Dec 202531 Dec 2025
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
822(part), 786(part),787,788(part),784(part),761,760,759(part),762,763,735(part),743(part),742,744(part),753(part),754,785(part)15917Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New11 Jun 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New11 Jun 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New11 Jun 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New11 Jun 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New11 Jun 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New11 Jun 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New22 Jun 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New11 Jun 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New7 Jul 2020 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New7 Jul 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New7 Jul 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New7 Jul 2020 ↗

Quarterly progress reports

19 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

19 quarterly progress reports are on file with UPRERA, covering 2021-Q1 to 2025-Q3.

QuarterConstructionCertificates
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q30%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameU.P. Awas Evam Vikas Parishad
RolePromoter · current
RERA IDUPRERAPRM4243
PANAAAJU0103A
CIN / TANLKNU05017F
Registered address104 Mahatma Gandhi Marg, Lucknow
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
UPAVP PMAY AVADH VIHAR YOJNA LUCKNOWBankAxis Bank Ltd.BranchAxis Bank Ltd. Aliganj BranchA/C no.IFSCUTIB0001692
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

14 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)761 (Under Registration - 10 ) → 762 (Under Registration - 11 )
changed in Estanzo’s record
19 Oct 2026
Promoter’s complaints tally (all their projects)760 (Under Registration - 9 ) → 761 (Under Registration - 10 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)759 (Under Registration - 8 ) → 760 (Under Registration - 9 )
changed in Estanzo’s record
15 Oct 2026
Promoter’s complaints tally (all their projects)758 (Under Registration - 7 ) → 759 (Under Registration - 8 )
changed in Estanzo’s record
13 Oct 2026
Promoter’s complaints tally (all their projects)757 (Under Registration - 6 ) → 758 (Under Registration - 7 )
changed in Estanzo’s record
9 Oct 2026
Promoter’s complaints tally (all their projects)755 (Under Registration - 4 ) → 757 (Under Registration - 6 )
changed in Estanzo’s record
7 Oct 2026
Promoter’s complaints tally (all their projects)753 (Under Registration - 2 ) → 755 (Under Registration - 4 )
changed in Estanzo’s record
5 Oct 2026
Promoter’s complaints tally (all their projects)753 (Under Registration - 6 ) → 753 (Under Registration - 2 )
changed in Estanzo’s record
1 Oct 2026
Promoter’s complaints tally (all their projects)752 (Under Registration - 5 ) → 753 (Under Registration - 6 )
changed in Estanzo’s record
29 Sept 2026
Promoter’s complaints tally (all their projects)751 (Under Registration - 4 ) → 752 (Under Registration - 5 )
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)750 (Under Registration - 3 ) → 751 (Under Registration - 4 )
changed in Estanzo’s record
17 Sept 2026
Promoter’s complaints tally (all their projects)748 (Under Registration - 1 ) → 750 (Under Registration - 3 )
changed in Estanzo’s record
3 Sept 2026
Promoter’s complaints tally (all their projects)747 (Under Registration - 0 ) → 748 (Under Registration - 1 )
changed in Estanzo’s record
1 Sept 2026
Promoter’s complaints tally (all their projects)746 (Under Registration - 2 ) → 747 (Under Registration - 0 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 19 Oct 2026 · 14 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow

Is Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow RERA registered?

Yes. Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow is registered with UPRERA under registration number UPRERAPRJ290595, registered on 15 Jul 2020. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow?

The completion date filed with UPRERA is 31 Dec 2025. No completion certificate is on record yet.

Who is the builder of Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow?

U.P. Awas Evam Vikas Parishad is the promoter entity that filed Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow with UPRERA (promoter RERA ID UPRERAPRM4243). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow located?

Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow is registered in Lucknow, as filed with UPRERA.

What configurations are available in Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow?

The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow?

The approved unit plan describes 2 blocks and 96 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Pradhan Mantri Awas Yojna, Avadh Vihar Yojna, Pocket-2, Lucknow?

About 476 units per acre: 96 planned units across 0.20 acres (816 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗