Timeline Bar
Registered15 Jan 2020
Revised10 Dec 2021
Promised11 Dec 2021
Today29 Jul 2026
Timeline
Promised completion11 Dec 2021
Revised completion10 Dec 2021
Actual completion—
Possession delay56 mo delay
Registration & Cost Details
Registration fee (in ₹)₹51,000
Project cost (in ₹ Lakhs)₹2,669 Lakhs
Project duration30 months
Project categoryResidential
Locality—
Original start date—
Proposed start date10 Dec 2019
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeIndividual
Mobile9839908091
EmailGHCC3000@YAHOO.COM
Coordinator9335155112
Address300 COLONELGANJ, ALLAHABAD
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 02/PA/TS/Zone-1,2/PMAY/2018-19 | 17 Oct 2019 | 16 Oct 2021 | 10 Dec 2021 | 11 Dec 2021 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 482 | 59.74 | Khasra |
| 483 | 8606.77 | Khasra |
Frequently Asked Questions
What is the RERA registration number of Pushp Niketan?
The RERA registration number of Pushp Niketan is UPRERAPRJ493779, as recorded on the UP-RERA portal.
What is the RERA status of Pushp Niketan?
As reported by UP-RERA, the status of Pushp Niketan is "Registered".
Where is Pushp Niketan located?
As reported to UP-RERA, Pushp Niketan is located at Allahabad, Prayagraj, Uttar Pradesh.
When will Pushp Niketan be completed?
The latest completion date reported to UP-RERA for Pushp Niketan is 10 Dec 2021.
Is Pushp Niketan delayed?
Measured against the latest completion date reported to UP-RERA, Pushp Niketan is 56 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026