Solitaire Pride

UPRERARegistered

Solitaire Pride is a RERA-registered residential project by The Innovators Digital Ads Pvt. Ltd in Prayagraj (RERA ID UPRERAPRJ222610). Registered with a completion deadline of 10 Jun 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
18%Q3'25
21%Q4'25
23%Q1'26
27.8%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ222610
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAllahabad Development Authority
Proposed start10 Jan 2023
Project duration42 months
AddressAllahabad **, Prayagraj
TehsilAllahabad **
Applicant typeCompany
Applicant address93, Katghar road, Allahabad U.P.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    73/Pra. Aa. (Tec. Cel.) Zone-2/Prasta/L.O.P./2018-2019

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered3 Feb 2023
Original completion10 Jun 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹10,500
Sanctioning authorityAllahabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 1 · 13 (from plan)
ConfigurationUnitsCarpet area
3 BHK—85-117
1 BHK—33
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Group Housing 1 Tower E and F · 3 BHK, 1 BHK, OTHER13—33-117
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Deepak Mehta and Associates
License COA-87-10840
Deepak Mehta and Associates, 1st, 2nd Floor, Plot No. 16A, Abhishek Plaza, Mayur Vihar, New Delhi
Engineer
Tajuddin Ashraf
1st Floor, H-53 opposite Vijaya Bank, Sector -63 Noida
Contractor
Self
33/1A/SF-2 Srikhand Market, Tashkand Marg, Civil Lines, Prayagraj
Sr.Development work declared to RERA
1Demarcation of Plots
YES - Demarcated on Site of Project
2Boundary Wall
YES - RCC Retaining wall , AAC BLOCK
3Road Work
YES - 6 Mtr Wide VDF Road around the tower
4Footpaths
YES - Soiling/ Paver block footpath work
5Water Supply Including Drinking Water Facilities
YES - under ground tank and pump house domestic water tank 50 KL
6Sewer System
YES - Sewer System having capacity 100 KLD Plant
7Drain
YES - Laying of DWC 300 mm dia pipe with circular chamber and rainwater harvesting
8Parks
YES - Park Covered with grass with kids play Asset
9Tree Planting
YES - Tree plantation is done around primes adjoining of boundary wall
10Design For Electric Supply Including Street Lighting
Electric supply shown in services coordination plan through 11KV, 3way RMU (Compact type) and 11KV /415KV corporation, solar Pannel provided on the top of the building.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
YES - Primary ,Secondary and Turtle treatment ,Sullage water use in landscape
13Solid Waste Management And Disposal System
YES - use in manure and water recycle of STP system
14Water Conservation System
YES - Water Conservation system through rainwater harvesting
15Energy Management System Including Use of Renewable Energy
YES - Through solar system
16Fire Protection And Fire Safety System
YES - through water sprinkler and hydrant system
17Social Infrastructure And Other Public Amenities Including Public Health Services
YES - Basketball Court, Badminton Court, Cricket practice pitch, Skating Court etc.
18Emergency Evacuation Services
YES - Fire fighting staircase and alarm system
19Other Miscellaneous Work
YES -The expansion of other residential unit, school, Children playground, fountain, Commercial complex with three tier security
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1ALMIGHTY INFRAESTATE PVT LTDUPRERAAGT10163
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 29 Jul 2023.

Sanctioned by Allahabad Development Authority · 1,048 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
73/Pra. Aa. (Tec. Cel.) Zone-2/Prasta/L.O.P./2018-201930 Jul 201829 Jul 202329 Jul 202610 Jun 2026
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

22 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
94,951048Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · Book No 1, Block 336, Page 363/464, S NO. 2479
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1425-1430 (01 July, 2017 - 30 June, 2023)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430 (01 July, 2017 - 30 June, 2023)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New23 Dec 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 Nov 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 Nov 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New25 Nov 2022 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New25 Nov 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New25 Nov 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New25 Nov 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New25 Nov 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New25 Nov 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Nov 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New24 Jan 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New25 Nov 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New25 Nov 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New12 Dec 2022 ↗

Quarterly progress reports

15 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

15 quarterly progress reports are on file with UPRERA, covering 2022-Q4 to 2026-Q2.

QuarterConstructionCertificates
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q218%CA ↗ · Arch ↗ · Eng ↗
2025-Q321%CA ↗ · Arch ↗ · Eng ↗
2025-Q423%CA ↗ · Arch ↗ · Eng ↗
2026-Q127.8%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameThe Innovators Digital Ads Pvt. Ltd
RolePromoter · current
RERA IDUPRERAPRM2380
PANAACCT2262N
CIN / TANU70102UP2005PTC029615
Name of chairmanMr. Mayank Jaiswal
Registered address93, Katghar road, Allahabad U.P.
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameTHE INNOVATORS DIGITAL ADS PVT. LTD.
RoleCo-promoter
Applicant typeCompany
Address91 KATGHAR ALLAHABAD U.P.
RERA contact

Nearby projects

Prayagraj

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
THE INNOVATORS DIGITAL ADS PVT LTD COLLECTION ACCOUNT SOLITAIRE PRIDEBankBANK OF BARODABranchALLAHABAD - V N MARGBranch addressALLAHABAD, ALLAH, UP, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCBARB0VJVNMA
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
THE INNOVATORS DIGITAL ADS PVT LTD SEPARATE ACCOUNT SOLITAIRE PRIDEBankBANK OF BARODABranchALLAHABAD- V N MARGBranch addressALLAHABAD, ALLAH, UP, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCBARB0VJVNMA
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
THE INNOVATORS DIGITAL ADS PVT LTD TRANSACTION ACCOUNT SOLITAIRE PRIDEBankBANK OF BARODABranchALLAHABAD- V N MARGBranch addressALLAHABAD, ALLAH, UP, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCBARB0VJVNMA
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
13 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Solitaire Pride

Is Solitaire Pride RERA registered?

Yes. Solitaire Pride is registered with UPRERA under registration number UPRERAPRJ222610, registered on 3 Feb 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Solitaire Pride?

The completion date filed with UPRERA is 10 Jun 2026. No completion certificate is on record yet.

Who is the builder of Solitaire Pride?

The Innovators Digital Ads Pvt. Ltd is the promoter entity that filed Solitaire Pride with UPRERA (promoter RERA ID UPRERAPRM2380). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Solitaire Pride have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Solitaire Pride located?

Solitaire Pride is registered in Prayagraj, as filed with UPRERA.

What configurations are available in Solitaire Pride?

The unit plan filed with UPRERA lists 3 BHK, 1 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Solitaire Pride?

The approved unit plan filed with UPRERA runs from 33 to 117 m² of carpet area (about 357 to 1,263 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗