Ratan Galaxy Phase II

UPRERARegistered

Ratan Galaxy Phase II is a RERA-registered residential project by RATAN HOUSING DEVELOPMENT LIMITED in Lucknow (RERA ID UPRERAPRJ718664). Registered with a completion deadline of 13 Nov 2024.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ718664
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryU.P. Awas Evam Vikas Parishad
Proposed start1 Feb 2022
Project duration34 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant address113/70, SWAROOP NAGAR, KANPUR
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2179

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered30 Mar 2022
Original completion13 Nov 2024
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹39,000
Sanctioning authorityU.P. Awas Evam Vikas Parishad

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors137 · 1 · 10 (units from plan)
Homes · commercial units126 · 11 (shops and offices filed in the same plan)
  • 3 BHK72 53%
  • 2 BHK36 26%
  • 4 BHK18 13%
  • SHOP11 8%
ConfigurationUnitsCarpet area
4 BHK18170
3 BHK72118-132
2 BHK3689
SHOP1111-15
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · OTHER, 4 BHK, 3 BHK, 2 BHK, SHOP1013711-170
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
MUKUL SHARMA
License M-1702712
F-104, Punit Vrindavan, Sanjay Place, Agra
Engineer
NARENDRA SINGH
7/33 D Nagla Jawahar Maruti Dhawa Ke Piche Ki Gali Civil Lines Agra
Contractor
Self
Self
Sr.Development work declared to RERA
1Demarcation of Plots
Since this is a phase of the already complete project, the Demarcation of plots is already done.
2Boundary Wall
Around 230 mm thick Boundary wall exist in the project.
3Road Work
Around 20 ft wide road will be provided, All internal roads will have concrete pavers or equivalent finishes.
4Footpaths
Wide footpath in thick concrete pavers or equivalent finishes
5Water Supply Including Drinking Water Facilities
Ground Water Supply facility to be arranged .
6Sewer System
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.when come into force.
7Drain
Storm water drain shall be Provided. Storm water from Roads and other landscape area shall be connected to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
"We will provide green area with the different activities and the green area will have gaming facilities for kids."
9Tree Planting
Several small and big plants and trees shall be put in the park and the surroundings
10Design For Electric Supply Including Street Lighting
System has been designed as per local electricity Board and consider centralized Transformer,HT panel,LT Panel,Feeder Pillar and DG back for common service like External lighting, etc.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.,when come into force.
13Solid Waste Management And Disposal System
"There are a proper garbage collection area provided for the solid waste management."
14Water Conservation System
Rain water harvesting system shall be provided for the whole building complex to conserve water
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
16Fire Protection And Fire Safety System
All the fire norms shall be followed as NBC and approval of fire department
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
We are providing fire escape stair case with sufficient width that open to the wide corridor for the public to safely evacuate in the case of emergency.
19Other Miscellaneous Work
We are providing amenities like Gym
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 13 Aug 2024.

Sanctioned by U.P. Awas Evam Vikas Parishad · 6,741 sqm of land · an approved plan of 1 block and 137 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
217914 Aug 201913 Aug 202413 Aug 202713 Nov 2024
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH - 01 and GH -0216851Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 6786
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6784
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New4 Feb 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New4 Feb 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New4 Feb 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New4 Feb 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New8 Mar 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New8 Mar 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New8 Mar 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New4 Feb 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New24 Feb 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New23 Feb 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New23 Feb 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New4 Feb 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New4 Feb 2022 ↗

Quarterly progress reports

12 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

12 quarterly progress reports are on file with UPRERA, covering 2021-Q4 to 2024-Q3.

QuarterConstructionCertificates
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2024-Q3. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameRATAN HOUSING DEVELOPMENT LIMITED
RolePromoter · current
RERA IDUPRERAPRM15031
PANAACCR6099R
CIN / TANU17117UP1998PLC023288
Name of chairmanMR ATMA RAM KHATRI
Registered address113/70, SWAROOP NAGAR, KANPUR
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Ratan Housing Development Limited Galaxy Phase-2 RERA Collection AccountBankICICI BankBranchTelibagh LucknowBranch addressICICI Bank, Telibagh, Rai bareilly road, LucknowBranch districtLucknow, Uttar PradeshA/C no.IFSCICIC0001259
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Ratan Housing Development Limited Galaxy Phase 2 RERA Retention A/cBankICICI BankBranchTelibagh LucknowBranch addressICICI Bank, Telibagh, Raibarelly Road, LucknowBranch districtLucknow, Uttar PradeshA/C no.IFSCICIC0001259
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Ratan Housing Development Ltd RERA Transaction A/c for Ratan Galaxy Phase 2BankICICI BankBranchTelibagh, LucknowBranch addressICICI Bank, Telibagh, Raibarelly road, LucknowBranch districtKanpur Nagar, Uttar PradeshA/C no.IFSCICIC0001259
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Ratan Galaxy Phase II

Is Ratan Galaxy Phase II RERA registered?

Yes. Ratan Galaxy Phase II is registered with UPRERA under registration number UPRERAPRJ718664, registered on 30 Mar 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Ratan Galaxy Phase II?

The completion date filed with UPRERA is 13 Nov 2024. No completion certificate is on record yet.

Who is the builder of Ratan Galaxy Phase II?

RATAN HOUSING DEVELOPMENT LIMITED is the promoter entity that filed Ratan Galaxy Phase II with UPRERA (promoter RERA ID UPRERAPRM15031). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Ratan Galaxy Phase II have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Ratan Galaxy Phase II located?

Ratan Galaxy Phase II is registered in Lucknow, as filed with UPRERA.

What configurations are available in Ratan Galaxy Phase II?

The unit plan filed with UPRERA lists OTHER, 4 BHK, 3 BHK, 2 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Ratan Galaxy Phase II?

The approved unit plan filed with UPRERA runs from 11 to 170 m² of carpet area (about 119 to 1,834 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Ratan Galaxy Phase II?

The approved unit plan describes 1 block and 137 units of which 126 are homes and 11 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Ratan Galaxy Phase II?

About 82 units per acre: 137 planned units across 1.67 acres (6,741 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗