Rudra Vardaan Heights, Phase-1

UPRERARegistered

Rudra Vardaan Heights, Phase-1 is a RERA-registered residential project by RUDRA INFRASOLUTIONS LLP in Lucknow (RERA ID UPRERAPRJ529962). Registered with a completion deadline of 31 Dec 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
83.93%Q3'25
91.52%Q4'25
89.62%Q1'26
93.76%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ529962
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 May 2022
Project duration56 months
AddressMohanlalganj, Lucknow
TehsilMohanlalganj
Applicant typePartnership Firm
Applicant addressRUDRA HOUSE, 15/63, CIVIL LINES KANPUR-208001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/04288/LDA/BP/21-22/0538/15022022

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered6 Jul 2022
Original completion31 Dec 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹20,500
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors120 · 1 · 15 (units from plan)
Homes · commercial units112 · 8 (shops and offices filed in the same plan)
  • 3 BHK56 47%
  • 2 BHK54 45%
  • SHOP8 7%
  • OTHER2 2%
ConfigurationUnitsCarpet area
SHOP812-14
3 BHK5667-77
2 BHK5448-53
OTHER232
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER-1 · SHOP, 3 BHK, 2 BHK, OTHER1512012-77
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. GAURAV SRIVASTAVA
License CA/97/21296
15/63, Rudra House, Civil Lines, Kanpur - 208001 (U.P.)
Engineer
MAQSUD E NAZAR [NNC DESIGN INTERNATION]
"G-70, 2nd Floor, Jaswant Plaza, Near Kalindi Kunj, Main Sarita Vihar Road, Shaheen Bagh, Okhla, New Delhi-110025 G-70, 2nd Floor, Jaswant Plaza, Near Kalindi Kunj, Main Sarita Vihar Road, Shaheen Bagh, Okhla, New Delhi-110025 "
Contractor
Self
Self
Sr.Development work declared to RERA
1Demarcation of Plots
This is single plot polygon shaped , having total 1 no. of entry/exit gate from the 24 m wide front road, Site is surronded by other plots of farmers from three sides.
2Boundary Wall
1.8 - 2.1m high and 150 mm thick Boundary wall designed . Brick Work of 4.5 inches and rcc work in column and beam may be used as per design. MS Broad entrance and exit gates are developed with boundary.
3Road Work
C.C. road will be used as per deisgn suggested by the Architect for internal road. 6 m. wide driveway with kurb stone.
4Footpaths
Footpaths shown will have matt finish tiles pavers or equivalent finishes. Aprox. 0.9m to 1.8m. Wide paved footpath of varrying width as per site.
5Water Supply Including Drinking Water Facilities
Ground water may also be used, Also end user shall be used their individual RO system as per their requirement. Overhead tanks shall be provided on building terrace for distribution through gravity.
6Sewer System
Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatement. after treatement ,water shall be recycled and it will use in gardening, flush tanks and vehicle washing, oveflow from the STP shall be connect with the Municiple sewarage system in future or a seasonal natural drain running along the site boundary. sewage system with suitable dia of mainhole 0.9m to 1.5m.
7Drain
Storm water system shall be Provided. Storm water from Roads and other lanscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municiple drain line. drain with 600x600 mm mainhole & 150-200 mm dia pvc pipe.
8Parks
There are many green/ landscape area in front/ side of building including green parks, play areas for childrens and different recretional activities. 2-no of green patchs.
9Tree Planting
There are diffrent type of tree plantation is proposed at site in order to maintatin greenary and natural view. Proposed 63 trees.
10Design For Electric Supply Including Street Lighting
We have designed the system as per local electricity Board and consider centralized Transformer,HT panel,LT Panel and DG back up for common service like External lighting,STP,Pump room etc. 1no.-Transformar-1600 KVA 1no.-DG set = 380 KVA.
11Community Buildings
Club House/community center is provided, swimming poolwith sitting area and garden .Proposed ground + two floor, height of each = 3 m.
12Treatment and Disposal System of Sewage and Sullage water
Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatement. after treatement ,water shall be recycled and it will use in gardening, flush tanks and vehicle washing, oveflow from the STP shall be connect with the Municiple sewarage system in future or a seasonal natural drain running along the site boundary. 210 KLD CAPACITY STP
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
A well designed rain water harvesting system shall be provided for the whole building complex to conserve water.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In STP and Pump room all the equipment shall have energy efficient motor.Terrace will be provided with Solar Voltaic Panels to provide Renewable source of energy for common areas in building complex.
16Fire Protection And Fire Safety System
Since the building is less than 45m in height all the fire norms shall be followed as NBC and approval of fire department
17Social Infrastructure And Other Public Amenities Including Public Health Services
Sewerage ,Storm water and water supply system shall be Provided. We have Proposed common Pump Room with Primary filteration, Transfer pumps to fill the domestic overhead tank. Water for domestic use & Flushing go down through gravity from domestic as well as flushing tanks. All Sewgage shall be go to the STP for recycling the water. Storm water for Roof,Roads and other area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municiple drain or a seasonal natural drain running along the site boundary.
18Emergency Evacuation Services
Fire Staircase is provided in the each building, with fire exit signboards & sprinklers in basements. There will be 1 (one) access and exit in case of emergency
19Other Miscellaneous Work
Luxurious entrance lobby in each block, convenience store for day to day small purchasings, lush green shurbs at every vacant space on ground.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 26 Apr 2027.

Sanctioned by Lucknow Development Authority · 3,066 sqm of land · an approved plan of 1 block and 120 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/04288/LDA/BP/21-22/0538/1502202227 Apr 202226 Apr 202726 Apr 203031 Dec 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
9841520Khasra
98510120Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 3849
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4457
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · Name Change Certificate
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1427-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Reply to objection letter - Rudra Vardhan
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Integrated Khasra
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New11 May 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New11 May 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New11 May 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New11 May 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New11 May 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New11 May 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New11 May 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New16 May 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New16 May 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New17 May 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New16 May 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New17 May 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New16 May 2022 ↗

Quarterly progress reports

17 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

17 quarterly progress reports are on file with UPRERA, covering 2022-Q1 to 2026-Q1.

QuarterConstructionCertificates
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q283.93%CA ↗ · Arch ↗ · Eng ↗
2025-Q391.52%CA ↗ · Arch ↗ · Eng ↗
2025-Q489.62%CA ↗ · Arch ↗ · Eng ↗
2026-Q193.76%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameRUDRA INFRASOLUTIONS LLP
RolePromoter · current
RERA IDUPRERAPRM170147
PANAAZFR3428C
CIN / TANKNPR03587D
Registered addressRUDRA HOUSE, 15/63, CIVIL LINES KANPUR-208001
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
RISLLP-COLL A/C FOR RUDRA VARDAAN HEIGHTS PH 1BankSTATE BANK OF INDIABranchSTATE BANK OF INDIA, HAZRATGANJ,LUCKNOWBranch address1, SHAHANAJAF ROAD, HAZRATGANJ LUCKNOW -226001Branch districtLucknow, Uttar PradeshA/C no.IFSCSBIN0016882
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
RISLLP-SEP BANK A/C FOR RUDRA VARDAAN HEIGHTS PH 1BankSTATE BANK OF INDIABranchSTATE BANK OF INDIA, HAZRATGANJ, LUCKNOWBranch address1, SHAHANAJAF ROAD, HAZRATGANJ LUCKNOW -226001Branch districtLucknow, Uttar PradeshA/C no.IFSCSBIN0016882
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
RISLLP-RERA TRANS A/C FOR RUDRA VARDAAN HEIGHTS PH 1BankSTATE BANK OF INDIABranchSTATE BANK OF INDIA, HAZRATGANJ, LUCKNOWBranch address1, SHAHANAJAF ROAD, HAZRATGANJ LUCKNOW -226001Branch districtLucknow, Uttar PradeshA/C no.IFSCSBIN0016882
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Rudra Vardaan Heights, Phase-1

Is Rudra Vardaan Heights, Phase-1 RERA registered?

Yes. Rudra Vardaan Heights, Phase-1 is registered with UPRERA under registration number UPRERAPRJ529962, registered on 6 Jul 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Rudra Vardaan Heights, Phase-1?

The completion date filed with UPRERA is 31 Dec 2026. No completion certificate is on record yet.

Who is the builder of Rudra Vardaan Heights, Phase-1?

RUDRA INFRASOLUTIONS LLP is the promoter entity that filed Rudra Vardaan Heights, Phase-1 with UPRERA (promoter RERA ID UPRERAPRM170147). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Rudra Vardaan Heights, Phase-1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Rudra Vardaan Heights, Phase-1 located?

Rudra Vardaan Heights, Phase-1 is registered in Lucknow, as filed with UPRERA.

What configurations are available in Rudra Vardaan Heights, Phase-1?

The unit plan filed with UPRERA lists SHOP, 3 BHK, 2 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Rudra Vardaan Heights, Phase-1?

The approved unit plan filed with UPRERA runs from 12 to 77 m² of carpet area (about 134 to 830 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Rudra Vardaan Heights, Phase-1?

The approved unit plan describes 1 block and 120 units of which 112 are homes and 8 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Rudra Vardaan Heights, Phase-1?

About 158 units per acre: 120 planned units across 0.76 acres (3,066 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗