Timeline Bar

Registered11 Oct 2023
Today3 Aug 2026
Promised13 Aug 2028

Timeline

Promised completion13 Aug 2028
Revised completion13 Aug 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹13,48,000
Project cost (in ₹ Lakhs)₹17,292 Lakhs
Project duration59 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Oct 2023

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9568006403
Emailblyda@nic.in
Coordinator9568006403
AddressVikas Jyoti Complex, Pyiyadarshini Nagar, Bareilly - 243122

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q245.0%
2025-Q395.2%
2025-Q495.5%
2026-Q195.9%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BDA GB SECTOR-2A/01614 Aug 202313 Aug 202813 Aug 202813 Aug 2031

Land Parcels

Khasra No.AreaPlot Type
2m,9m,10m,11,12,14,15,16,17,18,19,20,21,22,24,25,26,74,75,76,78,79,81,82,86,87,88,89KA,89Kha,91,91/208,92,93,94,95,96,98KA,98Kha,99Ka,99Kha,101,102,103,104,105,106,107,110,111,112,113,115,116,118,120,124,125,128,129,130,132,133,134,135,136m,138,139,141,142,144,146,147,148,155,156,157,160,161,162m,162,439,470,471,472,474,477,478,479,480,268515Khasra

Frequently Asked Questions

What is the RERA registration number of SECTOR 2A, GREATER BAREILLY?

The RERA registration number of SECTOR 2A, GREATER BAREILLY is UPRERAPRJ145066, as recorded on the UP-RERA portal.

What is the RERA status of SECTOR 2A, GREATER BAREILLY?

As reported by UP-RERA, the status of SECTOR 2A, GREATER BAREILLY is "Registered".

Where is SECTOR 2A, GREATER BAREILLY located?

As reported to UP-RERA, SECTOR 2A, GREATER BAREILLY is located at Bareilly, Bareilly, Uttar Pradesh.

When will SECTOR 2A, GREATER BAREILLY be completed?

The latest completion date reported to UP-RERA for SECTOR 2A, GREATER BAREILLY is 13 Aug 2028.

Is SECTOR 2A, GREATER BAREILLY delayed?

Measured against the latest completion date reported to UP-RERA, SECTOR 2A, GREATER BAREILLY is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026