Timeline Bar

Registered1 Feb 2024
Today3 Aug 2026
Promised19 Oct 2028

Timeline

Promised completion19 Oct 2028
Revised completion19 Oct 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹5,92,500
Project cost (in ₹ Lakhs)₹9,963 Lakhs
Project duration58 months
Project categoryResidential
LocalityMOHANPUR URF RAMNAGAR
Original start date
Proposed start date1 Jan 2024

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9568006403
Emailblyda@nic.in
Coordinator9568006403
AddressVikas Jyoti Complex, Pyiyadarshini Nagar, Bareilly - 243122

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q227.6%
2025-Q363.8%
2025-Q465.0%
2026-Q166.9%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BDA GB SECTOR 1B/01720 Oct 202319 Oct 202819 Oct 202818 Oct 2031

Land Parcels

Khasra No.AreaPlot Type
406M, 407, 408, 409, 410/1, 410/2, 412, 432, 433, 434, 435, 436, 437, 439, 440, 441, 466, 468M, 469, 470, 484, 486, 487, 488, 489, 491, 492, 493, 494, 495, 496, 497, 498M, 510, 512, 513, 514A, 514B155687Khasra

Frequently Asked Questions

What is the RERA registration number of SECTOR 1B GREATER BAREILLY?

The RERA registration number of SECTOR 1B GREATER BAREILLY is UPRERAPRJ428280, as recorded on the UP-RERA portal.

What is the RERA status of SECTOR 1B GREATER BAREILLY?

As reported by UP-RERA, the status of SECTOR 1B GREATER BAREILLY is "Registered".

Where is SECTOR 1B GREATER BAREILLY located?

As reported to UP-RERA, SECTOR 1B GREATER BAREILLY is located at BAREILLY DEVELOPMENT AUTHORITY, BAREILLY, MOHANPUR URF RAMNAGAR, Bareilly, Bareilly, Uttar Pradesh.

When will SECTOR 1B GREATER BAREILLY be completed?

The latest completion date reported to UP-RERA for SECTOR 1B GREATER BAREILLY is 19 Oct 2028.

Is SECTOR 1B GREATER BAREILLY delayed?

Measured against the latest completion date reported to UP-RERA, SECTOR 1B GREATER BAREILLY is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026