Registered16 Oct 2017
Promised31 Mar 2021
Completed8 Apr 2022

Timeline

Promised completion31 Mar 2021
Revised completion31 Mar 2021
Actual completion8 Apr 2022
Possession delay12 mo delay

Registration & Cost Details

Registration fee (in ₹)₹8,05,000
Project cost (in ₹ Lakhs)₹4,950 Lakhs
Project duration48 months
Project categoryResidential
Locality
Original start date20 Oct 2004
Proposed start date9 Oct 2017

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9568006403
Emailblyda@nic.in
Coordinator9568006091
AddressVikas Jyoti Complex, Pyiyadarshini Nagar, Bareilly - 243122

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
RGN-SEC-3(1)20 Oct 200431 Mar 202131 Mar 202131 Mar 2021

Land Parcels

Khasra No.AreaPlot Type
706P2120
707760
7086320
7091770
710P230
711P440
712P440
713P535
7142810
715250
716440
717P390
718P420
721260
7222920
723P500
7245020
7253440
7267780
727430
7282930
7295230
7306020
740P330
7412580
7422000
744P1076
7552590
7562780
7576150
758380
759890
7601910
7611090
7621000
7631270
7641880
7651860
7661230
7674470
7681050
7692120
77011350
7714920
7725550
7734290
7741810
775P350
790500
7911510
792P90
7931310
7941350
795P350
7968860
797790
7983360
790/103760
7993350
8005510
8033640
804930
8051850
8063580
8073170
8081280
809200
8262020
706P, 707 to 709, 710P to 713P, 714 to 71616115.00Khasra
717P, 718P, 721, 722, 723P, 724 to 73035340.00Khasra
740P, 741, 742, 744P, 755 to 77464576.00Khasra
775P, 790, 791, 792P, 793, 7945110.00Khasra
795P, 796 to 798, 790/1037, 799, 80022280.00Khasra
803 to 809, 82616670.00Khasra

Frequently Asked Questions

What is the RERA registration number of Sector 3 RGN?

The RERA registration number of Sector 3 RGN is UPRERAPRJ13458, as recorded on the UP-RERA portal.

What is the RERA status of Sector 3 RGN?

As reported by UP-RERA, the status of Sector 3 RGN is "Registered".

Where is Sector 3 RGN located?

As reported to UP-RERA, Sector 3 RGN is located at Bareilly, Bareilly, Uttar Pradesh.

Is Sector 3 RGN completed?

As reported to UP-RERA, Sector 3 RGN was completed on 8 Apr 2022.

Is Sector 3 RGN delayed?

Measured against the latest completion date reported to UP-RERA, Sector 3 RGN is 12 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.