Registered28 Feb 2020
Revised31 Dec 2022
Promised1 Jan 2023
Completed29 Dec 2023

Timeline

Promised completion1 Jan 2023
Revised completion31 Dec 2022
Actual completion29 Dec 2023
Possession delay12 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,95,500
Project cost (in ₹ Lakhs)₹2,422 Lakhs
Project duration42 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jan 2020

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9568006403
Emailblyda@nic.in
Coordinator9568006403
AddressVikas Jyoti Complex, Pyiyadarshini Nagar, Bareilly - 243122

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BDA/RGN/SEC(7)/001/202017 Jan 202016 Jan 202531 Dec 202216 Jan 2028

Land Parcels

Khasra No.AreaPlot Type
956P, 961, 939, 964, 949, 950, 947P, 941P, 940P38038Khasra

Frequently Asked Questions

What is the RERA registration number of Ramganga Nagar Scheme Neer Khand Part (Sector-7)?

The RERA registration number of Ramganga Nagar Scheme Neer Khand Part (Sector-7) is UPRERAPRJ517600, as recorded on the UP-RERA portal.

What is the RERA status of Ramganga Nagar Scheme Neer Khand Part (Sector-7)?

As reported by UP-RERA, the status of Ramganga Nagar Scheme Neer Khand Part (Sector-7) is "Registered".

Where is Ramganga Nagar Scheme Neer Khand Part (Sector-7) located?

As reported to UP-RERA, Ramganga Nagar Scheme Neer Khand Part (Sector-7) is located at Bareilly, Bareilly, Uttar Pradesh.

Is Ramganga Nagar Scheme Neer Khand Part (Sector-7) completed?

As reported to UP-RERA, Ramganga Nagar Scheme Neer Khand Part (Sector-7) was completed on 29 Dec 2023.

Is Ramganga Nagar Scheme Neer Khand Part (Sector-7) delayed?

Measured against the latest completion date reported to UP-RERA, Ramganga Nagar Scheme Neer Khand Part (Sector-7) is 12 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026