Shanker Greens- Phase 2 is a RERA-registered real-estate project in Agra (RERA ID UPRERAPRJ6663). Its RERA-registered completion deadline (31 Dec 2020) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ6663 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Mar 2015 |
| Original start | 1 Mar 2015 |
| Project duration | 76 |
| Address | Agra, Agra |
| RERA registered | 10 Aug 2017 |
| Promised completion | 31 Dec 2020 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹14,500 |
| Configuration | Units | Carpet area |
|---|---|---|
| 4 BHK | 66,318 | 162–228 |
| PENTHOUSE | 15,523 | 0–307 |
| 2 BHK | 403 | 94 |
| 3 BHK | 21,199 | 119–127 |
| OTHER | 809 | 0 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| NFT/VC/03/16-17 | 23 Mar 2017 | 22 Mar 2022 | 31 Dec 2020 |
| Khasra | Area | Type |
|---|---|---|
| c-1 | 20344.63 | Plot |
Yes. Shanker Greens- Phase 2 is registered with UPRERA under registration number UPRERAPRJ6663, registered on 10 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Shanker Greens- Phase 2 is 67 months past the completion date filed with UPRERA (31 Dec 2020), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Shanker Greens- Phase 2 is registered in Agra, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗