Shaurya Nagar is a RERA-registered residential project by Dhanraj Builders Consortium in Bareilly (RERA ID UPRERAPRJ488135). Registered with a completion deadline of 9 Nov 2021. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ488135
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryBareily Development Authority
Proposed start10 May 2019
Project duration30 months
AddressBareilly, Bareilly
TehsilBareilly
Applicant typePartnership Firm
Applicant addressB-1, EKTA NAGAR, BAREILLY, UP-243122
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    9714 ???/??? ??? ??? ??/2018

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered6 Aug 2019
Original completion10 May 2021
Revised completion9 Nov 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹72,000
Sanctioning authorityBareily Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors480 · 4 · 5 (units from plan)
ConfigurationUnitsCarpet area
1 BHK48023
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · 1 BHK512023
2 · 1 BHK512023
3 · 1 BHK512023
4 · 1 BHK512023
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Anil Kumar Saxena
License CA-7315/82
B-340, Rajendra Nagar, Bareilly
Engineer
Brajpal Singh
A-64, Vaibhav Suncity Vistar, Bareilly
Contractor
Tasleem Khan
Siklapur Chaudhary, Bareilly
Sr.Development work declared to RERA
1Demarcation of Plots
Each block is having length-69.54Mtr and width 10.510Mtr
2Boundary Wall
1.67Mtr High Boundary wall has been raised
3Road Work
Roads will be provided as per the sanctioned plan of 6Mtr,5Mtr,4Mtr respectively.
4Footpaths
Footpaths are provided inside the parks
5Water Supply Including Drinking Water Facilities
Total 2 No.tube-wells are proposed to meet total daily water demand (141KLD Per Day) of the colony. Anticipated yield of one tube-well 15000 Ltrs per day. One Tube-well will yield 180 Cum of water for 12Hours running a day. Depth of tube-well of diameter 450mm would be in the range 125-175m.
6Sewer System
Sewer drains will be provided as per sanctioned plan
7Drain
Drains will be provided as per sanctioned plan
8Parks
2003 Sqm area is proposed in the project for Parks
9Tree Planting
Around 110 Nos of trees will be planted in the parks as well as along the road side
10Design For Electric Supply Including Street Lighting
650KVA transformer, poll mounted, Oil filled with off load tap changer will be provided. Roads and parks will be lighted with duel function light and wire polls. All Blocks will have the electric connection from the Meter room provided at the Ground Floor on stair case area wall.
11Community Buildings
Three Convenient shops are provided as community building
12Treatment and Disposal System of Sewage and Sullage water
Bio Sewage Treatment Plant of 110 KLD with Burmi Compost Technology will be used in the Project. Sewer line will be installed for disposal of Sullage water till the STP.
13Solid Waste Management And Disposal System
A Common garbage area with three side covered walls will be provided in the project.
14Water Conservation System
2 Rainwater recharge pits will be provided in the project and Drains will be provided for Water Conservation.
15Energy Management System Including Use of Renewable Energy
Eco Friendly Flyash bricks will also be used along with Red Bricks in the project.
16Fire Protection And Fire Safety System
A 5000 Ltr Fire Storage Tank is provided over each mumty. therefore around 40000 Ltrs water will always be stored for fire safety measures.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Shri Ram Murti Smarak Medical College 3.5Km from Proposed site
18Emergency Evacuation Services
2 Stair Cases in each block are provided for Emergency Evacuation.
19Other Miscellaneous Work
Lush Green Parks, Wide Roads, Open Parking along with Continent Shops.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 29 Feb 2024.

Sanctioned by Bareily Development Authority · 13,330 sqm of land · an approved plan of 4 blocks and 480 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
9714 ???/??? ??? ??? ??/20181 Mar 201929 Feb 202428 Feb 202510 May 2021
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 9 Nov 2021.

#Granted fromExtended uptoNote
110 May 20219 Nov 2021Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1327,132813330Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 4543
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New7 Jul 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New7 Jul 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New7 Jul 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New21 Jul 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New21 Jul 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New21 Jul 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New7 Jul 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New7 Jul 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New21 Jul 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New7 Jul 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New21 Jul 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New28 Jul 2019 ↗

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameDhanraj Builders Consortium
RolePromoter · current
RERA IDUPRERAPRM87365
PANAAPFD1525J
CIN / TANLKND08667B
Registered addressB-1, EKTA NAGAR, BAREILLY, UP-243122
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Bareilly

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
RAKESH SHARMA LEAD MEMBER AND RAMESH GUPTA PARTNERBankPunjab National BankBranchEkta Nagar Bareilly U.PA/C no.IFSCPUNB0879400
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Shaurya Nagar

Is Shaurya Nagar RERA registered?

Yes. Shaurya Nagar is registered with UPRERA under registration number UPRERAPRJ488135, registered on 6 Aug 2019. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Shaurya Nagar?

The completion date filed with UPRERA is 9 Nov 2021. No completion certificate is on record yet.

Who is the builder of Shaurya Nagar?

Dhanraj Builders Consortium is the promoter entity that filed Shaurya Nagar with UPRERA (promoter RERA ID UPRERAPRM87365). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does Shaurya Nagar show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Has UPRERA granted Shaurya Nagar more time to complete?

UPRERA's record carries 1 completion extension for Shaurya Nagar, the latest running to 9 Nov 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Shaurya Nagar have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Shaurya Nagar located?

Shaurya Nagar is registered in Bareilly, as filed with UPRERA.

What configurations are available in Shaurya Nagar?

The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in Shaurya Nagar?

The approved unit plan describes 4 blocks and 480 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Shaurya Nagar?

About 146 units per acre: 480 planned units across 3.29 acres (13,330 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗