Sobha Aurum

UPRERARegistered

Sobha Aurum is a RERA-registered residential project by SOBHA LIMITED in Sector 36, Gautam Budh Nagar (RERA ID UPRERAPRJ361748). Registered with a completion deadline of 30 Apr 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
1%Q3'25
4%Q4'25
7%Q1'26
9%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ361748
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Jul 2025
Project duration58 months
AddressB-255, Sector 36, Greater Noida, U.P., Sector 36, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressSobha Limited, Sarjapur-Marthahalli Outer Ring Road, Bellandur Post, Bangalore - 560103
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    SM-09-Apr-2025/24454

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered17 Jun 2025
Original completion30 Apr 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹75,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors420 · 2 · 46 (units from plan)
  • 3 BHK272 65%
  • 2 BHK71 17%
  • 4 BHK45 11%
  • 1 BHK32 8%
ConfigurationUnitsCarpet area
2 BHK7171-77
3 BHK27291-103
1 BHK3240
4 BHK45130
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower 1 · 2 BHK, 3 BHK, 1 BHK3624640-100
Tower 2 · 3 BHK, 4 BHK, OTHER46174101-130
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VENKATESH GUDI
License CA/2005/36913
Sarjapur- Marthahalli Outer Ring Road, Bellandur Post, Bangalore - 560103
Engineer
MR. OUSEPPACHAN C. AMBOOKEN
Sarjapur- Marthahalli ORR, Bellandur Post, Bangalore - 560103
Contractor
SOBHA LIMITED
Sarjapur- Marthahalli Outer Ring Road, Bellandur Post, Bangalore - 560103
Sr.Development work declared to RERA
1Demarcation of Plots
Not Applicable
2Boundary Wall
Boundary Wall 1.5m high all around.
3Road Work
9.0m wide internal road finished in a combination of pavers and greenscaping.
4Footpaths
As per Landscape Drawing, pavers
5Water Supply Including Drinking Water Facilities
Water supply to be taken from GNIDA. WTP to be installed in the project.
6Sewer System
Underground sewer line will be laid. STP will be installed. Sewer connection will be obtained from authority.
7Drain
Drain line will be laid and connection will be obtained from authority.
8Parks
As per Landscape Drawing, Approx 6000 sqm Green Area.
9Tree Planting
As per Landscape Drawing, 60 Nos. Trees
10Design For Electric Supply Including Street Lighting
HT power connection will be taken from NPCL. Electrical yard will be provided with dedicated Transformers, HT/LT Panels and DG Sets. Street lights will be installed with EB power supply as well as backup power supply.
11Community Buildings
Recreation Area, Gym, Lounge etc.
12Treatment and Disposal System of Sewage and Sullage water
Dedicated Sewage Treatment Plant will be installed for Sewage Treatment.
13Solid Waste Management And Disposal System
Organic waste composter will be installed for solid waste management. Disposal of inorganic waste will be done thru authorised agency.
14Water Conservation System
Terrace rain water tank will be provided for storage and reuse, Surface rain water recharge tank will be provided.
15Energy Management System Including Use of Renewable Energy
EB Power Supply thru NPCL Backup Power - DG following CPCB guidelines Emergency power - UPS Renewable power - Solar as per MOEF guidelines Equipment selection - with proper energy efficiency as per green building norms.
16Fire Protection And Fire Safety System
As per provisional Fire NOC
17Social Infrastructure And Other Public Amenities Including Public Health Services
Community building, Swimming Pool
18Emergency Evacuation Services
Fire Staircase provided as per sanction plan, Signages and Fire Evacuation plan will be installed.
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 14 May 2030.

Sanctioned by Greater Noida Authority · 14,001 sqm of land · an approved plan of 2 blocks and 420 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
SM-09-Apr-2025/2445415 May 202514 May 203014 May 203530 Apr 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
B-255, Sector 36, Greater Noida14001Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 39719
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 42564
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New14 May 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New14 May 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New14 May 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New15 May 2025 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New28 May 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New14 May 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New14 May 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New14 May 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New14 May 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New15 May 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New15 May 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New14 May 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New14 May 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New15 May 2025 ↗

Quarterly progress reports

4 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

4 quarterly progress reports are on file with UPRERA, covering 2025-Q2 to 2026-Q1.

QuarterConstructionCertificates
2025-Q21%CA ↗ · Arch ↗ · Eng ↗
2025-Q34%CA ↗ · Arch ↗ · Eng ↗
2025-Q47%CA ↗ · Arch ↗ · Eng ↗
2026-Q19%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSOBHA LIMITED
RolePromoter · current
RERA IDUPRERAPRM361331
PANAABCS7723E
CIN / TANBLRS03591A
Name of chairmanRavi P N C Menon
Registered addressSobha Limited, Sarjapur-Marthahalli Outer Ring Road, Bellandur Post, Bangalore - 560103
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SOBHA LTD- COLLECTION ACC FOR SOBHA AURUMBankHDFC BANKBranchSECTOR 128 JAYPEE WISHTOWN NOIDABranch addressGRD FLOOR, SHOP NO IMA0010006, IMPERIAL ARCADE PROJECTS, POCKET-C2A, SECTOR 128, JAYPEE WISHTOWN, NOIDA, DIST GAUTAM BUDDHA NAGAR NOIDA 201304Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0006962Branch emailAshwin.subramanian@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SOBHA LIMITED- SEPARATE BANK ACCOUNT FOR SOBHA AURUMBankHDFC BANKBranchSECTOR 128 JAYPEE WISHTOWN NOIDABranch addressGRD FLOOR, SHOP NO IMA0010006, IMPERIAL ARCADE PROJECTS, POCKET-C2A, SECTOR 128, JAYPEE WISHTOWN, NOIDA, DIST GAUTAM BUDDHA NAGAR NOIDA 201304Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0006962
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SOBHA LTD- RERA TRANS AC FOR SOBHA AURUMBankHDFC BANKBranchSECTOR 128 JAYPEE WISHTOWN NOIDABranch addressGRD FLOOR, SHOP NO IMA0010006, IMPERIAL ARCADE PROJECTS, POCKET-C2A, SECTOR 128, JAYPEE WISHTOWN, NOIDA, DIST GAUTAM BUDDHA NAGAR NOIDA 201304Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0006962
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

20 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Filed document
viewprojects · 19
Proforma of Agreement for Sale
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 18
ENGINEERS CERTIFICATE
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 17
ARCHITECT CERTIFICATE
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 16
CA CERTIFICATE
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 15
Affidavit (Form-B)
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 14
Development Work Plan
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 13
Electricity Supply Plan
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 12
Water Supply Plan
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 11
Waste Disposal Plan
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 10
Proforma of Completion Certificate(Occupancy)
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 9
Proforma of Conveyance Deed
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 8
Proforma of Allotment Letter
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 7
Proforma of Application Form
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 6
Other Plan(If Any)
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 5
Commencement Certificate
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 4
Details of Encumbrances
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 3
Other
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 2
Proforma of Completion Certificate(Occupancy)
newly filed with RERA
31 Aug 2026
Filed document
viewprojects · 1
Proforma of Completion Certificate(Occupancy)
newly filed with RERA
31 Aug 2026
Filed document
summary · 23
Details of Encumbrances
no longer on the record
31 Aug 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Sobha Aurum

Is Sobha Aurum RERA registered?

Yes. Sobha Aurum is registered with UPRERA under registration number UPRERAPRJ361748, registered on 17 Jun 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Sobha Aurum?

The completion date filed with UPRERA is 30 Apr 2030. No completion certificate is on record yet.

Who is the builder of Sobha Aurum?

SOBHA LIMITED is the promoter entity that filed Sobha Aurum with UPRERA (promoter RERA ID UPRERAPRM361331). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Sobha Aurum have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Sobha Aurum located?

Sobha Aurum is registered in Sector 36, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Sobha Aurum?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK, 1 BHK, 4 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Sobha Aurum?

The approved unit plan filed with UPRERA runs from 40 to 130 m² of carpet area (about 434 to 1,400 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Sobha Aurum?

The approved unit plan describes 2 blocks and 420 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Sobha Aurum?

About 121 units per acre: 420 planned units across 3.46 acres (14,001 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗