JP Parks

UPRERARegistered

JP Parks is a RERA-registered commercial project by Ganadhi Pati Construction Private Limited in Sector PI-1, Greater NOIDA, Gautam Budh Nagar (RERA ID UPRERAPRJ775503). Registered with a completion deadline of 19 Jul 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
0%Q2'25
2%Q3'25
5%Q4'25
11%Q1'26
5%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ775503
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Apr 2025
Project duration52 months
AddressPlot No. C-3 , Sector PI-1, Greater NOIDA, Gautam Buddha Nagar, Uttar Pradesh, Sector PI-1, Greater NOIDA, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRegd. Office - 401, Capital Tower Block-B , Frezar Road, PS-Gandhi Maidan, Patna, Bihar. Corporate office - Bishnauli Road, Khasra No. 513 & 516, Dujana Road, Dadri, Gautam Buddha Nagar, Uttar Pradesh, PIN-203207
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/BP SM-28-Dec-2023.19989

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered30 Jun 2025
Original completion19 Jul 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹54,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors378 · 1 · 19 (units from plan)
Homes · commercial units173 · 205 (shops and offices filed in the same plan)
  • SHOP205 54%
  • STUDIO165 44%
  • OTHER8 2%
ConfigurationUnitsCarpet area
SHOP2055-49
OTHER847-1,263
STUDIO16526-82
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Commercial · SHOP, OTHER, STUDIO193785-82
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Amit Kumar
License CA/1998/22706
2330, Govind Puri, Modi Nagar, Ghaziabad, Uttar Pradesh.
Engineer
Mr. VD Sharma
B-24, Sector - 67, Noida, Gautam Buddha Nagar, Uttar Pradesh.
Contractor
Ganadhi Pati Construction Pvt. Ltd.
Bishnauli Road, Khasra No. 513 and 516, Dujana Road, Dadri, Gautam Buddha Nagar, Uttar Pradesh.
Sr.Development work declared to RERA
1Demarcation of Plots
Designated Plot is demarcated as per Lease Plan issued by Greater Noida Authority.
2Boundary Wall
Boundary Wall on 2 sides of land will be of 230 mm brickwork with column and MS Grills and 2 sides with RCC.
3Road Work
Road work will be done using RCC/ interlocking tiles as per layout plan.
4Footpaths
NO Footpath inside premises.
5Water Supply Including Drinking Water Facilities
Drinking Water will be provided by government supply and it will be stored in under Ground and over Head tanks.
6Sewer System
Proper Sewage system will be constructed using RCC/ UPVC pipes and will be connected to the main sewage line.
7Drain
Drainage system will be constructed using RCC/ UPVC pipes as per approved sanctioned plan by Noida Authority.
8Parks
Not Applicable
9Tree Planting
Not Applicable
10Design For Electric Supply Including Street Lighting
Electricity supply and street lighting is provided as per layout plan.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
To be connected in external sewage.
13Solid Waste Management And Disposal System
Collection and disposal through authorised vendors.
14Water Conservation System
Water Conversion will be done by Rain Water Harvesting System plan as per approved plan by NOIDA.
15Energy Management System Including Use of Renewable Energy
Not Applicable
16Fire Protection And Fire Safety System
Hydrants with automatic sprinkler and detection system shall be provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Fire Staircase and Fire exit doors will be provided as per sanctioned Drawings for evacuation in case of any emergency.
19Other Miscellaneous Work
CCTV Cameras and controlled Access will be made available as per requirements of the Project.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 19 Jul 2029.

Sanctioned by Greater Noida Authority · 4,376 sqm of land · an approved plan of 1 block and 378 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/BP SM-28-Dec-2023.1998920 Jul 202419 Jul 202919 Jul 203419 Jul 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Plot No. C-3, PI-1, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh.4375.75Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · Lease Deed No. 29856
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · Allotment Letter No. 3095
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Possession Letter No. 900
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New24 May 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New24 May 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New24 May 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New28 May 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New24 May 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New24 May 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New24 May 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New24 May 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New24 May 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New28 May 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New24 May 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New24 May 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New24 May 2025 ↗

Quarterly progress reports

5 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

5 quarterly progress reports are on file with UPRERA, covering 2025-Q1 to 2026-Q1.

QuarterConstructionCertificates
2025-Q10%CA ↗ · Arch ↗ · Eng ↗
2025-Q22%CA ↗ · Arch ↗ · Eng ↗
2025-Q35%CA ↗ · Arch ↗ · Eng ↗
2025-Q411%CA ↗ · Arch ↗ · Eng ↗
2026-Q15%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGanadhi Pati Construction Private Limited
RolePromoter · current
RERA IDUPRERAPRM365833
PANAADCM2976R
CIN / TANPTNG04971B
Name of chairmanJanardan Prasad
Registered addressRegd. Office - 401, Capital Tower Block-B , Frezar Road, PS-Gandhi Maidan, Patna, Bihar. Corporate office - Bishnauli Road, Khasra No. 513 & 516, Dujana Road, Dadri, Gautam Buddha Nagar, Uttar Pradesh, PIN-203207
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Ganadhi Pati Construction Pvt. Ltd. Collection Account Project JP ParksBankPunjab National BankBranchGreater Noida- GAMA SectorBranch addressShop No. 12, Shopping Complex, Gamma-1 Sec, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN-201308Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCPUNB0089810Branch emailbo089810@pnb.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Ganadhi Pati Construction Pvt. Ltd. Separate Bank Account for JP ParksBankPunjab National BankBranchGreater NOIDA- GAMMA SectorBranch addressShop No. 12, Shopping Complex , Gamma-1 Sec, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN-201308Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCPUNB0089810
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Ganadhi Pati Construction Pvt. Ltd. Transaction Account Project JP ParksBankPunjab National BankBranchGreater Noida- GAMMA SectorBranch addressShop No. 12, Shopping Complex, Gamma-1 Sec, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN-201308Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCPUNB0089810
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about JP Parks

Is JP Parks RERA registered?

Yes. JP Parks is registered with UPRERA under registration number UPRERAPRJ775503, registered on 30 Jun 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for JP Parks?

The completion date filed with UPRERA is 19 Jul 2029. No completion certificate is on record yet.

Who is the builder of JP Parks?

Ganadhi Pati Construction Private Limited is the promoter entity that filed JP Parks with UPRERA (promoter RERA ID UPRERAPRM365833). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does JP Parks have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is JP Parks located?

JP Parks is registered in Sector PI-1, Greater NOIDA, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in JP Parks?

The unit plan filed with UPRERA lists SHOP, OTHER and STUDIO. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in JP Parks?

The approved unit plan filed with UPRERA runs from 5 to 1,263 m² of carpet area (about 50 to 13,595 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in JP Parks?

The approved unit plan describes 1 block and 378 units of which 173 are homes and 205 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is JP Parks?

About 350 units per acre: 378 planned units across 1.08 acres (4,376 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗