Timeline Bar

Registered12 Aug 2017
Promised31 Dec 2020
Completed2 Jan 2024

Timeline

Promised completion31 Dec 2020
Revised completion31 Dec 2020
Actual completion2 Jan 2024
Possession delay36 mo delay

Registration & Cost Details

Registration fee (in ₹)₹50,000
Project cost (in ₹ Lakhs)₹12,247 Lakhs
Project duration79 months
Project categoryCommercial
Locality
Original start date10 Dec 2015
Proposed start date10 Dec 2015

Inventory

Total units118
Unit TypeUnitsCarpet Area (sqm)
SHOP1189–2086.5

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9310234107
Emailsagar@spectrummetro.com
Coordinator+919891329075
AddressUnit-219 S/F Vasundhara Enclave, Plot No. 1, Vardhman Sunrise Plaza LSC, New Delhi-110096

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOI/CAP/2015/IV-1480/85010 Dec 201510 Dec 202031 Dec 202010 Dec 2025
NOI/CAP/2015/IV-1480/850

Revalidated: NOI/CAP/2015/IV-1480/850 (10 Dec 2015)

10 Dec 201510 Dec 2020

Revalidated upto: 1 Jan 1900

31 Dec 202010 Dec 2025

Land Parcels

Khasra No.AreaPlot Type
NIL0
C&D25471Plot

Approved Unit Plan

Unit plan rows on file84
Total flats (sum of rows)118
Total shops118
BlocksB
Floor typesSHOP

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
108411 Dec 2011

Frequently Asked Questions

What is the RERA registration number of spectrum@metro(Phase-2)?

The RERA registration number of spectrum@metro(Phase-2) is UPRERAPRJ6028, as recorded on the UP-RERA portal.

What is the RERA status of spectrum@metro(Phase-2)?

As reported by UP-RERA, the status of spectrum@metro(Phase-2) is "Registered".

Where is spectrum@metro(Phase-2) located?

As reported to UP-RERA, spectrum@metro(Phase-2) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is spectrum@metro(Phase-2) completed?

As reported to UP-RERA, spectrum@metro(Phase-2) was completed on 2 Jan 2024.

Is spectrum@metro(Phase-2) delayed?

Measured against the latest completion date reported to UP-RERA, spectrum@metro(Phase-2) is 36 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026