Estanzo

Timeline Bar

Registered16 Jul 2018
Promised1 Nov 2023
Revised14 Nov 2023
Today4 Aug 2026

Timeline

Promised completion1 Nov 2023
Revised completion14 Nov 2023
Actual completion
Possession delay33 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,54,000
Project cost (in ₹ Lakhs)₹39,352 Lakhs
Project duration73 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Nov 2018

Inventory

Total units1267
Unit TypeUnitsCarpet Area (sqm)
SHOP12676.85–147.37

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9310234107
Emailsagar@spectrummetro.com
Coordinator9891329075
AddressUnit-219 S/F Vasundhara Enclave, Plot No. 1, Vardhman Sunrise Plaza LSC, New Delhi-110096

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CAP/2015/IV-1482/85110 Dec 201510 Dec 20201 Nov 202310 Dec 2022

Revalidated: NOIDA/CAP/2015/IV-1482/1076 (16 Nov 2018)

1 Jan 190010 Dec 2020

Revalidated upto: 15 Nov 2023

14 Nov 202315 Nov 2025
NOIDA/CAP/2015/IV-1482/1076

Revalidated: NOIDA/CAP/2015/IV-1482/1076 (16 Nov 2018)

16 Nov 201815 Nov 2023

Revalidated upto: 14 Nov 2024

14 Nov 202314 Nov 2027

Land Parcels

Khasra No.AreaPlot Type
A + B34531Plot

Approved Unit Plan

Unit plan rows on file446
Total flats (sum of rows)1267
Total shops1267
BlocksB, C, D
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of SPECTRUM METRO?

The RERA registration number of SPECTRUM METRO is UPRERAPRJ17035, as recorded on the UP-RERA portal.

What is the RERA status of SPECTRUM METRO?

As reported by UP-RERA, the status of SPECTRUM METRO is "Registered".

Where is SPECTRUM METRO located?

As reported to UP-RERA, SPECTRUM METRO is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will SPECTRUM METRO be completed?

The latest completion date reported to UP-RERA for SPECTRUM METRO is 14 Nov 2023.

Is SPECTRUM METRO delayed?

Measured against the latest completion date reported to UP-RERA, SPECTRUM METRO is 33 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026