Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ6815
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start10 Apr 2017
Original start10 Apr 2017
Project duration63 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRegistered Office Address- Shop No. 6/1-B-2, Ground Floor, East Guru Angad Nagar, Kaley Ram Chamber, East Delhi, Delhi, PIN - 110092. Corporate Office Address- Sports City, Plot No. GH-02, Adjoining Techzone-IV, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh, PIN -201009. Site Address- Sports City, Plot No. GH-02, Adjoining Techzone-IV, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh, PIN -201009.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    BP-3477/FB-3696

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. to

    Extension granted

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion31 Mar 2020
Revised completion28 Jun 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹55,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors183 · 2 · 26 (units from plan)
  • 3 BHK82 45%
  • 4 BHK42 23%
  • 2 BHK41 22%
  • PENTHOUSE18 10%
ConfigurationUnitsCarpet area
4 BHK42110
3 BHK8271-91
PENTHOUSE18167-196
2 BHK4157
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Ambrose (Block-C) · 4 BHK, 3 BHK, PENTHOUSE269371-196
Aspen (Block-D) · 2 BHK, 3 BHK, PENTHOUSE259057-167
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Andleys Associates Private Limited
License CA/99/24866
39, Housing Society, South Extension Part 1, South Extension, New Delhi, Delhi 110049
Engineer
Andleys Associates Private Limited
39, Housing Society, South Extension Part 1, South Extension, New Delhi, Delhi 110049
Contractor
SUKRITI REALCON PVT LTD
A-210, KARKARDOOMA VILLAGE, DAYANAND VIHAR, DELHI - 110092
Sr.Development work declared to RERA
1Demarcation of Plots
CONSTRCUTION WORK IN PROGRESS
2Boundary Wall
YES
3Road Work
YES
4Footpaths
YES
5Water Supply Including Drinking Water Facilities
YES
6Sewer System
YES
7Drain
YES
8Parks
YES
9Tree Planting
YES
10Design For Electric Supply Including Street Lighting
YES
11Community Buildings
YES
12Treatment and Disposal System of Sewage and Sullage water
YES
13Solid Waste Management And Disposal System
YES
14Water Conservation System
YES
15Energy Management System Including Use of Renewable Energy
YES
16Fire Protection And Fire Safety System
YES
17Social Infrastructure And Other Public Amenities Including Public Health Services
YES
18Emergency Evacuation Services
YES
19Other Miscellaneous Work
YES
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 29 Jun 2020.

Sanctioned by Greater Noida Authority · 10,000 sqm of land · an approved plan of 2 blocks and 183 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
BP-3477/FB-369630 Jun 201529 Jun 202029 Jun 202528 Jun 2022
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 28 Jun 2022.

#Granted fromExtended uptoNote
131 Mar 202030 Sept 2020Six months extension in view of force majeure caused by covid-19 pandemic
230 Sept 202029 Sept 2021—
329 Sept 202128 Jun 2022—

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-0210000Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

2 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 6 Feb 2014.

Registry no.DateTypeArea
150496 Feb 2014self—
150496 Feb 2014self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 15049
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · Layout Maps Revalidation Application to GNIDA
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · 9 Month Project Extension Application
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New26 Sept 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New28 Sept 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New28 Sept 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New28 Sept 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New28 Sept 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New28 Sept 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New28 Sept 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New28 Sept 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New28 Sept 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New28 Sept 2020 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAs per Standard Norms
Fire safety (as filed with RERA)As per NBC
Renewable energyAs per Statndard Norms

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

9 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

9 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2022-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameDEVSAI CONSTRUCTION PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM10224
PANAAECD7517N
CIN / TANDELD16457A
Name of chairmanGulshan Kumar
Registered addressRegistered Office Address- Shop No. 6/1-B-2, Ground Floor, East Guru Angad Nagar, Kaley Ram Chamber, East Delhi, Delhi, PIN - 110092. Corporate Office Address- Sports City, Plot No. GH-02, Adjoining Techzone-IV, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh, PIN -201009. Site Address- Sports City, Plot No. GH-02, Adjoining Techzone-IV, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh, PIN -201009.
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
DEVSAI CONSTRUCTION PRIVATE LIMITEDBankDCB BANK LIMITEDBranchLAXMI NAGARA/C no.IFSCDCBL0000185
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about SPORTSHOME

Is SPORTSHOME RERA registered?

Yes. SPORTSHOME is registered with UPRERA under registration number UPRERAPRJ6815, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for SPORTSHOME?

The completion date filed with UPRERA is 28 Jun 2022. No completion certificate is on record yet.

Who is the builder of SPORTSHOME?

DEVSAI CONSTRUCTION PRIVATE LIMITED is the promoter entity that filed SPORTSHOME with UPRERA (promoter RERA ID UPRERAPRM10224). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted SPORTSHOME more time to complete?

UPRERA's record carries 3 completion extensions for SPORTSHOME, the latest running to 28 Jun 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does SPORTSHOME have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is SPORTSHOME located?

SPORTSHOME is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in SPORTSHOME?

The unit plan filed with UPRERA lists 4 BHK, 3 BHK, PENTHOUSE and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in SPORTSHOME?

The approved unit plan filed with UPRERA runs from 57 to 196 m² of carpet area (about 615 to 2,111 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in SPORTSHOME?

The approved unit plan describes 2 blocks and 183 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is SPORTSHOME?

About 74 units per acre: 183 planned units across 2.47 acres (10,000 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗