Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
3.75%Q3'25
3.89%Q4'25
3.95%Q1'26
4.18%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ487319
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryPrayagraj(Allahabad) Development Authority
Proposed start1 Dec 2023
Project duration59 months
AddressArazi no.18 (minjumala) and part of Arazi no. 145 at Village Dhanuha, Pergana- Arail, Tehsil- Karchhana, District- Prayagraj (UP)., Village Dhanuha, Pergana- Arail, Tehsil- Karchhana, District- Prayagraj (UP)., Karchhana, Prayagraj
TehsilKarchhana
Applicant typeCompany
Applicant address17 Industrial Colony Naini, Allahabad -211008
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    Group Housing/05648/PDA/BP/25-26/0803/27022026

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Feb 2024
Original completion24 Oct 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹85,000
Sanctioning authorityPrayagraj(Allahabad) Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors433 · 2 · 15 (units from plan)
Homes · commercial units422 · 11 (shops and offices filed in the same plan)
  • 2 BHK230 53%
  • 3 BHK192 44%
  • SHOP11 3%
ConfigurationUnitsCarpet area
3 BHK19287-89
2 BHK23071-76
SHOP1115-15
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · 3 BHK, 2 BHK, SHOP1523415-89
2 · 3 BHK, 2 BHK1419972-89
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
AKHILESHWAR SINGH
License CA/94/16740
SHOP NO.49/G-7, LOTUS APARTMENT, TASHKAND MARG, CIVIL LINES, PRAYAGRAJ -211001
Engineer
MR. AKHILESH KUMAR SINGH
D-27, INDIRA NAGAR, LUCKNOW
Contractor
MAHIMA CONSTRUCTION- Mr. Lavkush Mishra
207/8 Beniganj, Prayagraj-211016
Sr.Development work declared to RERA
1Demarcation of Plots
We have one plot size of 16000 sq Mtr well demarcated having main gate at 12 mtr wide road.
2Boundary Wall
1.8 Mtr high and 230/115mm thick brick work and at the entrance 12 Mtr wide RCC road there will be 2 gate for entry/exit having name of the project over it.
3Road Work
From the main entrance gate we have 80 mm thick interlocking brick /CC road through out the project at Driveway whose wideness start from 6Mtr width.
4Footpaths
We will provide footpath at the periphery at back portion.
5Water Supply Including Drinking Water Facilities
We will provide Two nos. of borewell for the all water requirement of blocks through underground pipelines i.e. well connected with the under ground tanks.
6Sewer System
All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system,when come into force.
7Drain
Storm water from Roads and other landscape area shall be connected to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connected with Municipal drain line., when come into force.
8Parks
We will provide green area in our project and the green area will have gaming facilities for kids.
9Tree Planting
We will provide many type of trees all along the boundary wall & green area in our project.
10Design For Electric Supply Including Street Lighting
We will design & implement the system as per local electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG back for common service like External lighting, STP, Pump room etc.
11Community Buildings
We will provide community space as per approved map.
12Treatment and Disposal System of Sewage and Sullage water
All Sewerage water shall be go to the STP and overflow from the STP and treated water will be used for washing, Garndening etc.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management in corporation with the agencies appointed by the Muncipal Corporation board for disposal and for that there are provision for garbage collection dust bins (as per the sacntioned map) and disposal will be managed by the agency appointed by the Muncipal corporation.
14Water Conservation System
Rain Water Harvesting system will be provided as per norms to improve the Ground water Level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
16Fire Protection And Fire Safety System
We will provide fire protection and fire safety system as per NBC and NOC norms given by the fire Department
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
We will have staircases with the emergency doors. Adequate number of staircase for fire escape will provided as per the NOC provided by the fire department for emergency evacuation
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 24 Oct 2028. 1 of them carries a revalidation, valid to 26 Feb 2031.

Sanctioned by Prayagraj(Allahabad) Development Authority · 16,000 sqm of land · an approved plan of 2 blocks and 433 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Affordable Housing/02407/PDA/BP/22-23/0606/0205202325 Oct 202324 Oct 202824 Oct 203124 Oct 2028—
Group Housing/05648/PDA/BP/25-26/0803/2702202625 Oct 202324 Oct 202824 Oct 203124 Oct 202825 Oct 2023
valid to 26 Feb 2031
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Part of Arazi 18 Min and Part of Arazi 14516000Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 10516
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1426-1431
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New19 Dec 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New24 Nov 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New24 Nov 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New24 Nov 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New24 Nov 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New24 Nov 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New24 Nov 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New24 Nov 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New11 Jan 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New12 Dec 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Dec 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Dec 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New11 Jan 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New18 Dec 2023 ↗

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2023-Q3 to 2026-Q1.

QuarterConstructionCertificates
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q23.75%CA ↗ · Arch ↗ · Eng ↗
2025-Q33.89%CA ↗ · Arch ↗ · Eng ↗
2025-Q43.95%CA ↗ · Arch ↗ · Eng ↗
2026-Q14.18%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameHK INFRAZONE PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM1534
PANAACCH9169E
CIN / TANU70102UP2012PTC050473
Name of chairmanHemant Kumar Sindhi Babita Aailani Piyush Aailani
Registered address17 Industrial Colony Naini, Allahabad -211008
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameSANJEEV KUMAR
RoleCo-promoter · current
RERA IDUPRERAPRM12778
Applicant typeIndividual
PANAKFPK4257L
CIN / TANDELV07493D
Name of chairmanSANJEEV KUMAR
Registered addressC-26, 1ST FLOOR, SECTOR-3, NOIDA
RERA contact
Registered since2017
Legal nameHIMANSHU KESARWANI
RoleCo-promoter
Applicant typeIndividual
Address593, Mutthiganj, Prayagraj (U.P.)-211003
RERA contact
Legal nameYASHARTH KESARWANI
RoleCo-promoter
Applicant typeIndividual
Address326/167/20/1, Bai Ka Bagh, Prayagraj (U.P.)
RERA contact
Legal nameSHIVBALAK KESARWANI
RoleCo-promoter
Applicant typeIndividual
Address326/167, Bai Ka Bagh, Prayagraj (U.P.)
RERA contact
Legal nameBAL KRISHNA KESARWANI
RoleCo-promoter
Applicant typeIndividual
Address326/167, Bai Ka Bagh, Prayagraj (U.P.)
RERA contact
Legal nameATUL KUMAR AGARWAL
RoleCo-promoter
Applicant typeIndividual
Address504/16/12, Elgin Road, Prayagraj (U.P.)
RERA contact
Legal nameAKSHAY AGARWAL
RoleCo-promoter
Applicant typeIndividual
Address504/16/12, Elgin Road, Prayagraj (U.P.)
RERA contact
Legal nameRAJEEV KUMAR
RoleCo-promoter
Applicant typeIndividual
Address271, Mutthiganj, Prayagraj
RERA contact
Legal nameRUCHI KESARWANI
RoleCo-promoter
Applicant typeIndividual
Address271, Mutthiganj, Prayagraj
RERA contact
Legal nameSMITA KESARWANI
RoleCo-promoter
Applicant typeIndividual
Address271, Mutthiganj, Prayagraj
RERA contact
Legal nameSARITA AGARWAL
RoleCo-promoter
Applicant typeIndividual
Address504/16/12, Elgin Road, Prayagraj (U.P.)
RERA contact

Nearby projects

Prayagraj

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
HK Infrazone Private Limited Sunshine Imperial Heights Collection AccountBankICICI BankBranchAllahabadBranch addressSardar Patel Marg, Civil Lines, Allahabad, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCICIC0006282Branch emailsandeep.singh31@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
HK Infrazone Private Limited Sunshine Imperial Heights Separate AccountBankICICI BankBranchAllahabadBranch addressSardar Patel Marg, Civil Lines, Allahabad, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCICIC0006282
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
HK Infrazone Private Limited Sunshine Imperial Heights Transaction AccountBankICICI BankBranchAllahabadBranch addressSardar Patel Marg, Civil Lines, Allahabad, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCICIC0006282
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Sunshine Imperial Heights

Is Sunshine Imperial Heights RERA registered?

Yes. Sunshine Imperial Heights is registered with UPRERA under registration number UPRERAPRJ487319, registered on 24 Feb 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Sunshine Imperial Heights?

The completion date filed with UPRERA is 24 Oct 2028. No completion certificate is on record yet.

Who is the builder of Sunshine Imperial Heights?

HK INFRAZONE PRIVATE LIMITED is the promoter entity that filed Sunshine Imperial Heights with UPRERA (promoter RERA ID UPRERAPRM1534). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Sunshine Imperial Heights have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Sunshine Imperial Heights located?

Sunshine Imperial Heights is registered in Village Dhanuha, Pergana- Arail, Tehsil- Karchhana, District- Prayagraj (UP)., Prayagraj, as filed with UPRERA.

What configurations are available in Sunshine Imperial Heights?

The unit plan filed with UPRERA lists 3 BHK, 2 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Sunshine Imperial Heights?

The approved unit plan filed with UPRERA runs from 15 to 89 m² of carpet area (about 157 to 960 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Sunshine Imperial Heights?

The approved unit plan describes 2 blocks and 433 units of which 422 are homes and 11 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Sunshine Imperial Heights?

About 110 units per acre: 433 planned units across 3.95 acres (16,000 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗