Supertech Upcountry GH-02 Phase-01 is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ8263). RERA status: NCLT (since 25 Mar 2022). Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: NCLT.| RERA ID | UPRERAPRJ8263 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | NCLT |
| Proposed start | 16 Aug 2010 |
| Original start | 16 Aug 2010 |
| Project duration | 113 |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| RERA registered | 8 Aug 2017 |
| Promised completion | 30 Jun 2019 |
| Revised completion | 31 Dec 2019 |
| Completion certificate filed | — not on record |
| Registration fee | ₹90,500 |
| NCLT order date | 25 Mar 2022 |
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 1,004 | 27–28 |
| VILLA | 32 | 153–797 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| BP-71/17371/2017 | 21 Feb 2017 | 12 Aug 2017 | 31 Dec 2019 |
| Khasra | Area | Type |
|---|---|---|
| TS-01 Sector 17A | 407949.94 | Plot |
Other projects registered in Gautam Budh Nagar.
Yes. Supertech Upcountry GH-02 Phase-01 is registered with UPRERA under registration number UPRERAPRJ8263, registered on 8 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Supertech Upcountry GH-02 Phase-01 is 79 months past the completion date filed with UPRERA (31 Dec 2019), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Supertech Upcountry GH-02 Phase-01 is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗