SUPERTECH LIMITED (RERA ID: UPRERAPRM1754) is a company registered with UP-RERA since 2017. It has 27 projects on record with Estanzo, of which 27 are on RERA's NCLT list and 18 are on RERA's Default-on-QPR list.
One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.
Projects by this promoter
27 on record
Showing 20 of 27 projects on record. See all 27 projects
Filings for more time
23 filings
| Extension filings | 23 |
| Projects with at least one | 20 of 27 |
| Longest single extension | 365 days - SUPERTECH ECO VILLAGE-II (PHASE-II) |
| Latest extension runs to | 30 Jun 2023 - SPORTS VILLAGE (PHASE-III, Commercial) |
| Permits carrying a revalidation | 5 across 5 projects |
Directors & ownership
7 named by UPRERA
Promoter timeline
21 Feb 2017 - 30 Sept 2024
- Permit revalidatedvalid to 30 Sept 2024as recorded by UPRERA: WILL BE APPLIEDofficial source ↗
- Permit revalidatedvalid to 30 Sept 2024as recorded by UPRERA: WILL BE APPLIEDofficial source ↗
- Permit revalidatedvalid to 30 Sept 2024as recorded by UPRERA: WILL BE APPLIEDofficial source ↗
- Extension filednew completion date on file 30 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Jan 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
Show 73 earlier filings
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- Extension filednew completion date on file 29 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Permit revalidatedvalid to 5 Nov 2024as recorded by UPRERA: PLG/(BP)2366 FTS No-8115official source ↗
- Extension filednew completion date on file 30 Nov 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Nov 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 27 Aug 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Jun 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Jun 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Jun 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Dec 2021official source ↗
- Extension filednew completion date on file 28 Apr 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 29 Dec 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Dec 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 29 Oct 2020official source ↗
- Extension filednew completion date on file 31 Dec 2019official source ↗
- Extension filednew completion date on file 29 Jun 2020official source ↗
- Extension filednew completion date on file 30 Nov 2019official source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 30 Sept 2018official source ↗
- Extension filednew completion date on file 30 Sept 2018official source ↗
- Extension filednew completion date on file 30 Jun 2018official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedas recorded by UPRERA: BP-71/17371/2017official source ↗
Quarterly reports filed, by financial year
Common questions about SUPERTECH LIMITED
How many projects has SUPERTECH LIMITED registered with RERA?
Estanzo holds 27 projects on record with UPRERA, filed by SUPERTECH LIMITED (promoter RERA ID UPRERAPRM1754). This counts filings by this legal entity only - a builder brand may file through several entities.
Who are the directors of SUPERTECH LIMITED?
SUPERTECH LIMITED disclosed 7 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.
When was SUPERTECH LIMITED registered with RERA?
SUPERTECH LIMITED has been registered with UPRERA since 26 Jul 2017.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗