Suraksha Enclave Phase 2 is a RERA-registered real-estate project in Lucknow (RERA ID UPRERAPRJ915727). Its RERA-registered completion deadline (26 Nov 2024) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ915727 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Nov 2020 |
| Project duration | 49 |
| Address | Mohanlalganj, Lucknow |
| RERA registered | 16 Jan 2021 |
| Promised completion | 26 Nov 2024 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹1,05,500 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 20190906135735083 | 27 Nov 2019 | 26 Nov 2024 | 26 Nov 2024 |
| MAP-20190906135735083 | 27 Nov 2019 | 26 Nov 2024 | 26 Nov 2024 |
| Khasra | Area | Type |
|---|---|---|
| 366 | 11950 | Khasra |
| 396 | 4530 | Khasra |
| 383 | 1040 | Khasra |
| 397 | 2530 | Khasra |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | — | CA · Arch · Eng | view ↗ |
| 2023-Q4 | — | CA · Arch · Eng | view ↗ |
| 2024-Q1 | — | CA · Arch · Eng | view ↗ |
| 2024-Q2 | — | CA · Arch · Eng | view ↗ |
| 2024-Q3 | — | CA · Arch · Eng | view ↗ |
Yes. Suraksha Enclave Phase 2 is registered with UPRERA under registration number UPRERAPRJ915727, registered on 16 Jan 2021. Estanzo reproduces that filing; it does not verify the work behind it.
Suraksha Enclave Phase 2 is 20 months past the completion date filed with UPRERA (26 Nov 2024), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Suraksha Enclave Phase 2 is registered in Lucknow, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗