Timeline Bar

Registered10 Aug 2017
Promised31 Mar 2020
NCLT20 Oct 2023

Timeline

Promised completion31 Mar 2020
Revised completion31 Mar 2020
Actual completion
Possession delay76 mo delay

Registration & Cost Details

Registration fee (in ₹)₹58,000
Project cost (in ₹ Lakhs)₹16,500 Lakhs
Project duration107 months
Project categoryResidential
Locality
Original start date8 Nov 2011
Proposed start date29 Nov 2012

Inventory

Total units313
Unit TypeUnitsCarpet Area (sqm)
2 BHK9962.26–78.95
3 BHK21491.55–111.14

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator9910177724
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLNG/(B.P.)1534-GH/FB-3242

Revalidated: PLG/(BP)1534/2433 (16 Apr 2018)

8 Jun 20177 Jun 2022

Revalidated upto: 15 Apr 2023

31 Mar 202014 Apr 2028

Approved Unit Plan

Unit plan rows on file6
Total flats (sum of rows)313
BlocksT3, T4, T5
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
2303228 Oct 2015

Frequently Asked Questions

What is the RERA registration number of SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D?

The RERA registration number of SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D is UPRERAPRJ8951, as recorded on the UP-RERA portal.

What is the RERA status of SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D?

As reported by UP-RERA, the status of SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D is "NCLT".

Where is SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D located?

As reported to UP-RERA, SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D be completed?

The latest completion date reported to UP-RERA for SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D is 31 Mar 2020.

Is SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D delayed?

Measured against the latest completion date reported to UP-RERA, SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D is 76 months beyond that date.