Timeline Bar

Registered10 Aug 2017
Promised30 Sept 2021
NCLT20 Oct 2023

Timeline

Promised completion30 Sept 2021
Revised completion30 Sept 2021
Actual completion
Possession delay58 mo delay

Registration & Cost Details

Registration fee (in ₹)₹40,500
Project cost (in ₹ Lakhs)₹9,000 Lakhs
Project duration93 months
Project categoryResidential
Locality
Original start date19 Mar 2012
Proposed start date15 Jul 2014

Inventory

Total units198
Unit TypeUnitsCarpet Area (sqm)
2 BHK19862.26–78.95

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator9910177724
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLNG/(B.P.)1534-GH/FB-32428 Jun 20177 Jun 202230 Sept 20216 Jun 2028

Approved Unit Plan

Unit plan rows on file4
Total flats (sum of rows)198
BlocksT10, T11
Floor types2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
2303228 Oct 2015

Frequently Asked Questions

What is the RERA registration number of SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T?

The RERA registration number of SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T is UPRERAPRJ4938, as recorded on the UP-RERA portal.

What is the RERA status of SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T?

As reported by UP-RERA, the status of SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T is "NCLT".

Where is SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T located?

As reported to UP-RERA, SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T be completed?

The latest completion date reported to UP-RERA for SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T is 30 Sept 2021.

Is SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T delayed?

Measured against the latest completion date reported to UP-RERA, SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T is 58 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.