Estanzo

Timeline Bar

Registered10 Aug 2017
Promised31 Mar 2022
NCLT20 Oct 2023

Timeline

Promised completion31 Mar 2022
Revised completion31 Mar 2022
Actual completion
Possession delay52 mo delay

Registration & Cost Details

Registration fee (in ₹)₹58,000
Project cost (in ₹ Lakhs)₹16,600 Lakhs
Project duration99 months
Project categoryResidential
Locality
Original start date2 Jun 2012
Proposed start date15 Jul 2014

Inventory

Total units294
Unit TypeUnitsCarpet Area (sqm)
1 BHK14942.68
3 BHK9591.55–111.14
STUDIO5031.8

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator9810602017
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLNG/(B.P.)1534-GH/FB-32428 Jun 20177 Jun 202231 Mar 20225 Jun 2028

Approved Unit Plan

Unit plan rows on file4
Total flats (sum of rows)294
BlocksT12, T8
Floor types1 BHK, 3 BHK, STUDIO

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
2303228 Oct 2015

Frequently Asked Questions

What is the RERA registration number of SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E&?

The RERA registration number of SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& is UPRERAPRJ4969, as recorded on the UP-RERA portal.

What is the RERA status of SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E&?

As reported by UP-RERA, the status of SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& is "NCLT".

Where is SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& located?

As reported to UP-RERA, SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& be completed?

The latest completion date reported to UP-RERA for SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& is 31 Mar 2022.

Is SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& delayed?

Measured against the latest completion date reported to UP-RERA, SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& is 52 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026