Estanzo

Timeline Bar

Registered11 Aug 2017
Promised31 Mar 2022
Today29 Jul 2026

Timeline

Promised completion31 Mar 2022
Revised completion
Actual completion
Possession delay52 mo delay

Registration & Cost Details

Registration fee (in ₹)
Project cost (in ₹ Lakhs)
Project duration
Project category
Locality
Original start date
Proposed start date

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator7060345700
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001

No promoter data available.

Frequently Asked Questions

What is the RERA registration number of SUSHANT TAJ CITY EWS LIG PHASE-1?

The RERA registration number of SUSHANT TAJ CITY EWS LIG PHASE-1 is UPRERAPRJ5593, as recorded on the UP-RERA portal.

What is the RERA status of SUSHANT TAJ CITY EWS LIG PHASE-1?

As reported by UP-RERA, the status of SUSHANT TAJ CITY EWS LIG PHASE-1 is "Registered".

Where is SUSHANT TAJ CITY EWS LIG PHASE-1 located?

As reported to UP-RERA, SUSHANT TAJ CITY EWS LIG PHASE-1 is located at Kiraoli, Agra, Uttar Pradesh.

When will SUSHANT TAJ CITY EWS LIG PHASE-1 be completed?

The latest completion date reported to UP-RERA for SUSHANT TAJ CITY EWS LIG PHASE-1 is 31 Mar 2022.

Is SUSHANT TAJ CITY EWS LIG PHASE-1 delayed?

Measured against the latest completion date reported to UP-RERA, SUSHANT TAJ CITY EWS LIG PHASE-1 is 52 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026