Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 626/M.P./2014 | 26 Jun 2014 | 25 Jun 2019 | 30 Jun 2020 | 30 Jun 2020 |
| 626/M.P./2014 Revalidated: 259/MP/2-5/20 (7 Sept 2020) | 26 Jun 2014 | 25 Jun 2019 Revalidated upto: 25 Jun 2022 | 29 Dec 2020 | 25 Jun 2022 |
| 626/M.P./2014 Revalidated: 626/M.P./2014 (25 Jun 2021) | 25 Jun 2021 | 25 Jun 2021 Revalidated upto: 31 Mar 2026 | 2 Dec 2020 | 31 Mar 2026 |
| 626/M.P./2014 Revalidated: 618/LA/ZONE-5/2021 (31 Mar 2021) | 25 Jun 2021 | 25 Jun 2021 Revalidated upto: 31 Mar 2026 | 2 Dec 2020 | 31 Mar 2026 |
| 626/M.P./2014 Revalidated: 626/M.P./2014 (25 Jun 2021) | 25 Jun 2021 | 31 Mar 2026 Revalidated upto: 31 Dec 2025 | 2 Dec 2020 | 31 Mar 2026 |
| 626/M.P./2014 Revalidated: 626/M.P./2014 (25 Jun 2021) | 25 Jun 2021 | 31 Mar 2026 Revalidated upto: 1 Jan 1900 | 2 Dec 2020 | 18 Dec 2028 |
| 626/M.P./2014 Revalidated: 626/M.P./2014 (25 Jun 2021) | 25 Jun 2021 | 31 Mar 2026 Revalidated upto: 18 Mar 2028 | 31 Dec 2025 | 18 Mar 2028 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 1053 | 0.1640 | — |
| 1054/1 | 0.0130 | — |
| 1054/2 | 0.2150 | — |
| 1036/4 | 0.0105 | — |
| 1053 | 0.1640 | Khasra |
| 1054/1 | 0.0130 | Khasra |
| 1054/2 | 0.2150 | Khasra |
| 1036/4 | 0.0105 | Khasra |
Approved Unit Plan
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 1 | 25 Jun 2015 | — | — |
Frequently Asked Questions
What is the RERA registration number of The Core?
The RERA registration number of The Core is UPRERAPRJ9641, as recorded on the UP-RERA portal.
What is the RERA status of The Core?
As reported by UP-RERA, the status of The Core is "Registered".
Where is The Core located?
As reported to UP-RERA, The Core is located at Ghaziabad, Ghaziabad, Uttar Pradesh.
When will The Core be completed?
The latest completion date reported to UP-RERA for The Core is 31 Dec 2025.
Is The Core delayed?
Measured against the latest completion date reported to UP-RERA, The Core is 7 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.