Timeline Bar

Registered4 Aug 2017
Promised31 Dec 2022
Today4 Aug 2026

Timeline

Promised completion31 Dec 2022
Revised completion31 Dec 2022
Actual completion
Possession delay43 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,21,000
Project cost (in ₹ Lakhs)₹34,580 Lakhs
Project duration107 months
Project categoryCommercial
Locality
Original start date2 Aug 2014
Proposed start date2 Aug 2014

Inventory

Total units1700160
Unit TypeUnitsCarpet Area (sqm)
SHOP1602066.37–76.76
OTHER15399546.82–394.45

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9650090225
EmailDIRECTORDOWNTOWN@GMAIL.COM
Coordinator9650090225
AddressC-60 PREET VIHAR

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
IV-1388/68519 Jul 201318 Jul 201831 Dec 202231 Dec 2022

Land Parcels

Khasra No.AreaPlot Type
C-1/B SECTOR 98 NOIDA11068
C-1/B SECTOR 98 NOIDA11068Plot

Approved Unit Plan

Unit plan rows on file1886
Total flats (sum of rows)1700160
Total shops160206
BlocksBASEMENT, KAPITAL GRAND, KROWN GALLERIA, MALL OF NOIDA
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
NOIDA/COMMERCIAL/2010/122421 Dec 2010

Frequently Asked Questions

What is the RERA registration number of THE DOWNTOWN?

The RERA registration number of THE DOWNTOWN is UPRERAPRJ5805, as recorded on the UP-RERA portal.

What is the RERA status of THE DOWNTOWN?

As reported by UP-RERA, the status of THE DOWNTOWN is "Registered".

Where is THE DOWNTOWN located?

As reported to UP-RERA, THE DOWNTOWN is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will THE DOWNTOWN be completed?

The latest completion date reported to UP-RERA for THE DOWNTOWN is 31 Dec 2022.

Is THE DOWNTOWN delayed?

Measured against the latest completion date reported to UP-RERA, THE DOWNTOWN is 43 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.