Timeline Bar
Registered4 Aug 2017
Promised31 Dec 2022
Today4 Aug 2026
Timeline
Promised completion31 Dec 2022
Revised completion31 Dec 2022
Actual completion—
Possession delay43 mo delay
Registration & Cost Details
Registration fee (in ₹)₹1,21,000
Project cost (in ₹ Lakhs)₹34,580 Lakhs
Project duration107 months
Project categoryCommercial
Locality—
Original start date2 Aug 2014
Proposed start date2 Aug 2014
Inventory
Total units1700160
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| SHOP | 160206 | 6.37–76.76 |
| OTHER | 1539954 | 6.82–394.45 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9650090225
EmailDIRECTORDOWNTOWN@GMAIL.COM
Coordinator9650090225
AddressC-60 PREET VIHAR
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| IV-1388/685 | 19 Jul 2013 | 18 Jul 2018 | 31 Dec 2022 | 31 Dec 2022 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| C-1/B SECTOR 98 NOIDA | 11068 | — |
| C-1/B SECTOR 98 NOIDA | 11068 | Plot |
Approved Unit Plan
Unit plan rows on file1886
Total flats (sum of rows)1700160
Total shops160206
BlocksBASEMENT, KAPITAL GRAND, KROWN GALLERIA, MALL OF NOIDA
Floor typesSHOP, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| NOIDA/COMMERCIAL/2010/1224 | 21 Dec 2010 | — | — |
Frequently Asked Questions
What is the RERA registration number of THE DOWNTOWN?
The RERA registration number of THE DOWNTOWN is UPRERAPRJ5805, as recorded on the UP-RERA portal.
What is the RERA status of THE DOWNTOWN?
As reported by UP-RERA, the status of THE DOWNTOWN is "Registered".
Where is THE DOWNTOWN located?
As reported to UP-RERA, THE DOWNTOWN is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will THE DOWNTOWN be completed?
The latest completion date reported to UP-RERA for THE DOWNTOWN is 31 Dec 2022.
Is THE DOWNTOWN delayed?
Measured against the latest completion date reported to UP-RERA, THE DOWNTOWN is 43 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026