Timeline Bar

Registered18 Jun 2020
Promised31 Dec 2020
Revised1 Nov 2021
Today4 Aug 2026

Timeline

Promised completion31 Dec 2020
Revised completion1 Nov 2021
Actual completion
Possession delay57 mo delay

Registration & Cost Details

Registration fee (in ₹)₹48,000
Project cost (in ₹ Lakhs)₹850 Lakhs
Project duration42 months
Project categoryCommercial
Locality
Original start date
Proposed start date30 Nov 2018

Inventory

Total units36
Unit TypeUnitsCarpet Area (sqm)
4 BHK1250.8
SHOP35870.5

Promoters & Contact

Contact Details

Applicant TypeIndividual
Mobile6393521560
Emailanandmani0007@rediffmail.com
Coordinator9935791000
AddressH.NO-C/140/11, CHARANLAL CHOWK, SANTOSHI MATA KA MANDIR, RUDRAPUR, GORAKHPUR

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
12/201724 Mar 201823 Mar 20231 Nov 202123 Mar 2024

Land Parcels

Khasra No.AreaPlot Type
932MI, 933MI2490Khasra

Approved Unit Plan

Unit plan rows on file5
Total flats (sum of rows)36
Total shops35
BlocksTHE GRAND AASHIRWAD COMMERCIAL BUILDING
Floor types4 BHK, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of THE GRAND AASHIRWAD COMMERCIAL BUILDING?

The RERA registration number of THE GRAND AASHIRWAD COMMERCIAL BUILDING is UPRERAPRJ332211, as recorded on the UP-RERA portal.

What is the RERA status of THE GRAND AASHIRWAD COMMERCIAL BUILDING?

As reported by UP-RERA, the status of THE GRAND AASHIRWAD COMMERCIAL BUILDING is "Registered".

Where is THE GRAND AASHIRWAD COMMERCIAL BUILDING located?

As reported to UP-RERA, THE GRAND AASHIRWAD COMMERCIAL BUILDING is located at Gorakhpur, Gorakhpur, Uttar Pradesh.

When will THE GRAND AASHIRWAD COMMERCIAL BUILDING be completed?

The latest completion date reported to UP-RERA for THE GRAND AASHIRWAD COMMERCIAL BUILDING is 1 Nov 2021.

Is THE GRAND AASHIRWAD COMMERCIAL BUILDING delayed?

Measured against the latest completion date reported to UP-RERA, THE GRAND AASHIRWAD COMMERCIAL BUILDING is 57 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026