TOWN CENTRAL - PHASE-II is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ7355). Its RERA-registered completion deadline (14 Feb 2024) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ7355 |
| Applicant type | Company |
| Project category | Commercial |
| Project type | other |
| RERA status | Registered |
| Proposed start | 15 Aug 2017 |
| Project duration | 99 |
| Address | Dadri, Gautam Budh Nagar |
| RERA registered | 1 Aug 2017 |
| Promised completion | 15 Aug 2023 |
| Revised completion | 14 Feb 2024 |
| Completion certificate filed | — not on record |
| Registration fee | ₹90,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 157 | 8–1,870 |
| OTHER | 6 | 188–21,100 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| PLG/(BP)3788/S/9407 | 30 Dec 2016 | 30 Dec 2021 | 15 Aug 2023 |
| PLG/(BP)3788/S/9407 | 30 Dec 2016 | 30 Dec 2021 | 14 Feb 2024 |
| Khasra | Area | Type |
|---|---|---|
| C-4 | 18001.75 | Plot |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 7644 | 31 Mar 2016 | — | — |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | — | CA · Arch · Eng | view ↗ |
| 2023-Q4 | — | CA · Arch · Eng | view ↗ |
| 2024-Q1 | — | CA · Arch · Eng | view ↗ |
| 2024-Q2 | — | CA · Arch · Eng | view ↗ |
| 2024-Q3 | — | CA · Arch · Eng | view ↗ |
| 2024-Q4 | — | CA · Arch · Eng | view ↗ |
| 2025-Q1 | — | CA · Arch · Eng | view ↗ |
| 2025-Q2 | 94.63% | CA · Arch · Eng | view ↗ |
| 2025-Q3 | 95.71% | CA · Arch · Eng | view ↗ |
Other projects registered in Gautam Budh Nagar.
Yes. TOWN CENTRAL - PHASE-II is registered with UPRERA under registration number UPRERAPRJ7355, registered on 1 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
TOWN CENTRAL - PHASE-II is 30 months past the completion date filed with UPRERA (14 Feb 2024), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
TOWN CENTRAL - PHASE-II is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗