VVIP ADDRESSES GREATER NOIDA (WEST)

UPRERARegistered

VVIP ADDRESSES GREATER NOIDA (WEST) is a RERA-registered residential project by Vibhor Vaibhav infrahome Pvt. Ltd. in Greater Noida, Gautam Budh Nagar (RERA ID UPRERAPRJ600767). Registered with a completion deadline of 18 Sept 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
10.46%Q3'25
13.02%Q4'25
14.58%Q1'26
17.13%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ600767
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start19 Sept 2024
Project duration60 months
AddressPlot No. GH-03A, Sector 12, Greater Noida, Greater Noida, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressS-551, School Block, Shakarpur, Delhi-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    PLG/BP/SM-28-FEB-2024-20506

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered27 Nov 2024
Original completion18 Sept 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,05,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors339 · 5 · 33 (units from plan)
Homes · commercial units312 · 27 (shops and offices filed in the same plan)
  • 4 BHK216 64%
  • 3 BHK96 28%
  • SHOP27 8%
ConfigurationUnitsCarpet area
4 BHK216157-216
3 BHK96116-149
SHOP2724-25
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Commercial · SHOP12724-25
Tower A (T-1) · 4 BHK, 3 BHK30114116-173
Tower B (T-2) · 4 BHK3263158-215
Tower C (T-3) · 4 BHK3263157-216
Tower D (T-4) · 3 BHK, 4 BHK1972116-173
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VISHAL MITTAL
License CA/98/23185
A-14 , VIVEK VIHAR-II, DELHI
Engineer
V.D. Sharma
B-24,Sector-67, Noida
Contractor
Faith building Construction Pvt Limited
Ashirvad Apartments, flat-85, kondli,Gharoli, Mayur Vihar Pahse -03, Delhi-110096
Sr.Development work declared to RERA
1Demarcation of Plots
All sides of the Plot Description :-1. 24 MT Wide Road, 2.Plot no-GH-4A, 3. Plot No.- GH-3B & 4. 24 MT Wide Road
2Boundary Wall
RCC wall /column and brickwork as per drawings 2.40 Mtr height.
3Road Work
All Internal Road work in PCC/Concrete Paver Block/VDF and Footpaths in Interlocking Pavers
4Footpaths
Interlocking Pavers & stones as per drawings
5Water Supply Including Drinking Water Facilities
To be Provided by the Authority and Storage will be done in under ground water tank.
6Sewer System
Under ground Sewerage system. Feeder pipeline of PVC and final discharge through RCC pipes. Raw sewerage will be processed through STP of required capacity as per norms. Treated water shall be used for flushing, irrigation and cleaning purpose. Excess water shell be discharge in the authority drain.
7Drain
Storm water is going to harvesting recharge pits. Excess water if any, will be discharge to authority drain.
8Parks
Landscape and Tree Planting has been designed by as per authority guidelines
9Tree Planting
Landscape and Tree Planting has been designed by as per authority guidelines
10Design For Electric Supply Including Street Lighting
Designed has been done as per UP electricity board guidelines
11Community Buildings
Community Building has been designed as per authority norms and Facilities Like:- Party Hall, Gaming Zone, Entertainment Area, Gym area etc.
12Treatment and Disposal System of Sewage and Sullage water
STP of capacity as per norms shall be provided. Treated water shall be used for flushing, irrigation, carwash, pathways cleaning and excess sewage shall be discharged in the municipal sewer line.
13Solid Waste Management And Disposal System
Door to Door Collection and will be disposed up to garbage point of authority
14Water Conservation System
Recycling of treated water and rain water syestem to be provide.
15Energy Management System Including Use of Renewable Energy
Mix of Solar panel light & LED Lights
16Fire Protection And Fire Safety System
Fire tender path shall be provided as per NBC. Fire fighting systems along with pumps and water storage tanks shall be provided as per NBC & NOC from fire dept.
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per Norms
18Emergency Evacuation Services
Fire Scape Staircase will be provided as required by Fire norms.
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

4 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1NIDHI DAGARUPRERAAGT25017
2PROPFIN SOLUTIONS PVT LTDUPRERAAGT14948
3PROPSHOPUPRERAAGT10129
4SUMIT CHAUDHARYUPRERAAGT18651
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 18 Sept 2029. 1 of them carries a revalidation, valid to 20 Sept 2029.

Sanctioned by Greater Noida Authority · 20,000 sqm of land · an approved plan of 5 blocks and 339 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
PLG/BP/SM-28-FEB-2024-2050619 Sept 202418 Sept 202917 Sept 203218 Sept 2029—
PLG/BP/SM-28-FEB-2024-2050619 Sept 202418 Sept 202912 Feb 203018 Sept 202919 Sept 2024
valid to 20 Sept 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-03A, Sector - 12, Greater Noida20000Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 10906
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Registry document · I-54033/2024
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New21 Oct 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New21 Oct 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New9 Nov 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New21 Oct 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New21 Oct 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New21 Oct 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New21 Oct 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New21 Oct 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New21 Oct 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New13 Nov 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New13 Nov 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New13 Nov 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New9 Nov 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New21 Oct 2024 ↗

Quarterly progress reports

9 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

9 quarterly progress reports are on file with UPRERA, covering 2024-Q2 to 2026-Q2.

QuarterConstructionCertificates
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q210.46%CA ↗ · Arch ↗ · Eng ↗
2025-Q313.02%CA ↗ · Arch ↗ · Eng ↗
2025-Q414.58%CA ↗ · Arch ↗ · Eng ↗
2026-Q117.13%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameVibhor Vaibhav infrahome Pvt. Ltd.
RolePromoter · current
RERA IDUPRERAPRM1796
PANAABCF2720J
CIN / TANU70101DL2007PTC170268
Name of chairmanMr. Praveen Tyagi
Registered addressS-551, School Block, Shakarpur, Delhi-110092
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameLOTUS SRS BUILDTECH PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
Address203, 2nd Floor, Mercantile House, 15, K.G. Marg, New Delhi - 110001
RERA contact

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
VVIPL COLLECTION AC-VVIP ADDRESSES GREATER NOIDA (WEST)BankState Bank of IndiaBranchGaur CityBranch addressShop UGF 1 to 4, Exotica Dreamville, Plot GH01, Sector 16C, Greater Noida WestBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCSBIN0018934Branch emailsbi.18934@sbi.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
VVIPL SEPARATE AC-VVIP ADDRESSES GREATER NOIDA (WEST)BankState Bank of IndiaBranchGaur CityBranch addressShop 1 to 4, Exotica Dreamville Arcade, Plot GH01, Sector 16C, Greater Noida WestBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCSBIN0018934
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
VVIPL TRANSACTION AC- VVIP ADDRESSES GREATER NOIDA (WEST)BankState Bank of IndiaBranchGaur CityBranch addressShop UGF 1 to 4, Exotica Dreamville Arcade, Plot GH01, Sector 16C, Greater Noida WestBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCSBIN0018934
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

7 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
Permit paperwork
2 · Project Specifications
Project Specifications
newly filed with RERA
31 Aug 2026
Permit paperwork
2 · Floor Plan Of All Types
Floor Plan Of All Types
newly filed with RERA
31 Aug 2026
Permit paperwork
2 · Approved Map
Approved Map
newly filed with RERA
31 Aug 2026
Permit paperwork
2 · Sanctioned Letter
Sanctioned Letter
newly filed with RERA
31 Aug 2026
Permit paperwork
2 · Approved Layout
Approved Layout
newly filed with RERA
31 Aug 2026
Sanctioning permit
no. 2
PLG/BP/SM-28-FEB-2024-20506
newly filed with RERA
31 Aug 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about VVIP ADDRESSES GREATER NOIDA (WEST)

Is VVIP ADDRESSES GREATER NOIDA (WEST) RERA registered?

Yes. VVIP ADDRESSES GREATER NOIDA (WEST) is registered with UPRERA under registration number UPRERAPRJ600767, registered on 27 Nov 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for VVIP ADDRESSES GREATER NOIDA (WEST)?

The completion date filed with UPRERA is 18 Sept 2029. No completion certificate is on record yet.

Who is the builder of VVIP ADDRESSES GREATER NOIDA (WEST)?

Vibhor Vaibhav infrahome Pvt. Ltd. is the promoter entity that filed VVIP ADDRESSES GREATER NOIDA (WEST) with UPRERA (promoter RERA ID UPRERAPRM1796). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does VVIP ADDRESSES GREATER NOIDA (WEST) have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is VVIP ADDRESSES GREATER NOIDA (WEST) located?

VVIP ADDRESSES GREATER NOIDA (WEST) is registered in Greater Noida, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in VVIP ADDRESSES GREATER NOIDA (WEST)?

The unit plan filed with UPRERA lists 4 BHK, 3 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in VVIP ADDRESSES GREATER NOIDA (WEST)?

The approved unit plan filed with UPRERA runs from 24 to 216 m² of carpet area (about 258 to 2,325 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in VVIP ADDRESSES GREATER NOIDA (WEST)?

The approved unit plan describes 5 blocks and 339 units of which 312 are homes and 27 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is VVIP ADDRESSES GREATER NOIDA (WEST)?

About 69 units per acre: 339 planned units across 4.94 acres (20,000 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗