EDEN PROJECTS PRIVATE LIMITED (RERA ID: UPRERAPRM19109) is a company registered with UP-RERA since 2017. It has 1 project on record with Estanzo, of which 1 is on RERA's Default-on-QPR list.
One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.
Projects by this promoter
1 on record
Filings for more time
1 filing
| Extension filings | 1 |
| Projects with at least one | 1 of 1 |
| Longest single extension | 180 days - MANAS GARDEN EXTENSION |
| Latest extension runs to | 29 Mar 2021 - MANAS GARDEN EXTENSION |
| Permits carrying a revalidation | 1 across 1 project |
Directors & ownership
as reported by UPRERA
UPRERA filed no directors or partners for this promoter. Its “Name of chairman” box reads: BRAJ KISHORE MISHRA
Promoter timeline
29 Sept 2017 - 30 Sept 2025
- Permit revalidatedvalid to 30 Sept 2025as recorded by UPRERA: NILofficial source ↗
- Extension filednew completion date on file 29 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Project registeredofficial source ↗
Common questions about EDEN PROJECTS PRIVATE LIMITED
How many projects has EDEN PROJECTS PRIVATE LIMITED registered with RERA?
Estanzo holds 1 project on record with UPRERA, filed by EDEN PROJECTS PRIVATE LIMITED (promoter RERA ID UPRERAPRM19109). This counts filings by this legal entity only - a builder brand may file through several entities.
When was EDEN PROJECTS PRIVATE LIMITED registered with RERA?
EDEN PROJECTS PRIVATE LIMITED has been registered with UPRERA since 11 Aug 2017.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗