Kanpur Development Authority (RERA ID: UPRERAPRM7482) is a promoter entity registered with UP-RERA since 2017. It has 24 projects on record with Estanzo, of which 1 is on RERA's Default-on-QPR list.
One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.
Projects by this promoter
24 on record
Showing 20 of 24 projects on record. See all 24 projects
Filings for more time
11 filings
| Extension filings | 11 |
| Projects with at least one | 8 of 24 |
| Longest single extension | 366 days - PMAY at bhagirath and janhavi yojna |
| Latest extension runs to | 30 Jun 2027 - BHAGIRATHI AND JANHVI ENCLAVE NAGWAN |
| Permits carrying a revalidation | 2 across 2 projects |
Directors & ownership
1 named by UPRERA
Promoter timeline
28 Feb 2015 - 31 Dec 2026
- Extension filednew completion date on file 30 Jun 2027as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 18 Dec 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 31 Dec 2021official source ↗
- Extension filednew completion date on file 2 Jan 2022official source ↗
- Extension filednew completion date on file 31 Dec 2021official source ↗
Show 33 earlier filings
- Extension filednew completion date on file 18 Jan 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 2 Jan 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Dec 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 31 Mar 2019official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 31 Mar 2019official source ↗
- Extension filednew completion date on file 25 Jan 2019official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 1 Feb 2021as recorded by UPRERA: D/432/CTP/KDA/15-16official source ↗
- Permit revalidatedas recorded by UPRERA: D/167/AA-2/KDA/14-15official source ↗
Quarterly reports filed, by financial year
Common questions about Kanpur Development Authority
How many projects has Kanpur Development Authority registered with RERA?
Estanzo holds 24 projects on record with UPRERA, filed by Kanpur Development Authority (promoter RERA ID UPRERAPRM7482). This counts filings by this legal entity only - a builder brand may file through several entities.
Who are the directors of Kanpur Development Authority?
Kanpur Development Authority disclosed 1 director or partner to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.
When was Kanpur Development Authority registered with RERA?
Kanpur Development Authority has been registered with UPRERA since 28 Jul 2017.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗