Keltech Infrastructure Limited

UPRERACompany

Keltech Infrastructure Limited (RERA ID: UPRERAPRM7872) is a company registered with UP-RERA since 2017. It has 2 projects on record with Estanzo.

Summarize this record with:ChatGPTPerplexityClaudeGrok

One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.

Promoters sharing a director

none matched

Linked by a director’s DIN, never by name alone. Each company is its own record.

No other promoter shares a director with Keltech Infrastructure Limited on record. RERA lists its directors without a DIN, and names alone are never matched.

Filings for more time

4 filings
Extension filings4
Projects with at least one1 of 2
Longest single extension1,248 days - Kumar Imperial Greens
Latest extension runs to28 Jun 2025 - Kumar Imperial Greens
Permits carrying a revalidation9 across 2 projects

Directors & ownership

1 named by UPRERA
Director
NARINDER KUMAR

Promoter timeline

14 Oct 2016 - 31 Dec 2023
  1. Extension filed
    new completion date on file 28 Jun 2025official source ↗
  2. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP/3195/500official source ↗
  3. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP/3195/500official source ↗
  4. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP3195/500official source ↗
  5. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP3195/500official source ↗
  6. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP3195/500official source ↗
  7. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP3195/500official source ↗
  8. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP/3195/500official source ↗
  9. Permit revalidated
    valid to 28 Jun 2025as recorded by UPRERA: BP/3195/500official source ↗
  10. Extension filed
    new completion date on file 31 Dec 2023official source ↗
  11. Extension filed
    new completion date on file 31 Dec 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  12. Extension filed
    new completion date on file 30 Jan 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
Show 3 earlier filings
  1. Project registered
    official source ↗
  2. Project registered
    official source ↗
  3. Permit revalidated
    as recorded by UPRERA: 192/MP/ZONE5/2016official source ↗

Quarterly reports filed, by financial year

FY 2020-21
4 reports across 1 project
FY 2021-22
4 reports across 1 project
FY 2022-23
4 reports across 1 project
FY 2023-24
4 reports across 1 project
FY 2024-25
4 reports across 1 project
FY 2025-26
1 report across 1 project
Counts the reports UPRERA publishes as filed.
A filing is not an outcome.

Common questions about Keltech Infrastructure Limited

How many projects has Keltech Infrastructure Limited registered with RERA?

Estanzo holds 2 projects on record with UPRERA, filed by Keltech Infrastructure Limited (promoter RERA ID UPRERAPRM7872). This counts filings by this legal entity only - a builder brand may file through several entities.

Who are the directors of Keltech Infrastructure Limited?

Keltech Infrastructure Limited disclosed 1 director or partner to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.

When was Keltech Infrastructure Limited registered with RERA?

Keltech Infrastructure Limited has been registered with UPRERA since 28 Jul 2017.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗