Aditi Apartments is a RERA-registered residential project by Lucknow Development Authority in Kaliya Khera, Lucknow (RERA ID UPRERAPRJ710087). Registered with a completion deadline of 28 May 2031.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ710087 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 25 Sept 2026 |
| Project duration | 57 months |
| Address | Khasra No/ Plot no. 170, 171, 172, 173, 174, 175, 177, 222, 223, 225, 226KH, 227, 228, 399, 400A, 400B, 401, 402, 403, 405, 407, 408, 409, 410, and 422 of village Kaliyakheda, Tehsil Sarojini Nagar, Lucknow, Kaliya Khera, Sarojini Nagar, Lucknow |
| Tehsil | Sarojini Nagar |
| Applicant type | Competent authority |
| Applicant address | Lucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
Government Building/Group Housing/19124/LDA/BP/26-27/1973/29052026
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 23 Sept 2026 |
| Original completion | 28 May 2031 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹97,500 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 2 BHK980 70%
- 1 BHK412 30%
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 980 | 39 |
| 1 BHK | 412 | 30 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Tower - A · 2 BHK, 1 BHK | 15 | 346 | 30-39 |
| Tower - B · 1 BHK | 15 | 174 | 30 |
| Tower - C · 2 BHK | 15 | 288 | 39 |
| Tower - D · 2 BHK | 15 | 404 | 39 |
| Tower - E · 1 BHK | 15 | 180 | 30 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots The project site has been demarcated as per the approved layout and building plans. All
development and construction activities shall be undertaken within the approved project
boundaries. The layout has been planned in accordance with the sanctioned drawings, and all
residential buildings, internal roads, utility services, landscaped areas and common facilities
shall be developed within the demarcated project limits. |
| 2 | Boundary Wall A peripheral boundary wall comprising RCC columns, plinth beams, masonry wall and MS grill
along with entrance gates and security infrastructure shall be constructed around the project
site as per the sanctioned plan. The boundary wall shall incorporate suitable entry and exit
gates, security cabins, pedestrian access points and other allied works required for ensuring
safety and controlled access to the residential campus. The boundary wall shall be designed in
accordance with the approved architectural and structural drawings. |
| 3 | Road Work Internal circulation roads, peripheral access roads, fire tender movement roads, cement
concrete pavements and paved vehicular areas will be 6mtr wide with thickness of 150mm shall be developed as per the sanctioned layout
plan. The internal road network shall provide safe and efficient circulation for residents, visitors,
service vehicles and emergency vehicles. The road system shall include suitable road markings,
kerb stones, traffic signage, speed calming measures, surface drainage arrangements and other
associated works necessary for smooth vehicular movement within the project. |
| 4 | Footpaths Pedestrian pathways with paving blocks, kerb stones, barrier-free access provisions and
landscape integration shall be with 1.5 mm width stamp concrete and 100 mm thickness of provided throughout the project for safe and convenient
movement of residents. The footpaths shall be constructed over suitable sub-base layers using
approved paving materials and shall be integrated with landscaped areas, building entrances
and common open spaces. Universal accessibility features shall be incorporated wherever
required in accordance with applicable guidelines. |
| 5 | Water Supply Including Drinking Water Facilities The project shall be provided with a comprehensive water supply system with pipes of 80-100 mm diameter comprising underground water reservoirs, overhead water tanks, pumping systems, distribution pipelines,
plumbing fixtures and associated infrastructure. Water supply shall be sourced from approved
municipal sources along with three operational tube wells and one standby tube well. The
project includes 956 KL underground domestic water storage, 319 KL overhead domestic water
storage, 159 KL overhead flushing water storage and 255 KL dedicated fire water storage
facilities.
Water from the approved source shall be conveyed through suitable pipelines to the
underground water storage tanks. The underground storage shall be suitably
compartmentalized for domestic, flushing and fire-fighting requirements as per applicable
norms. Water shall be pumped through hydro-pneumatic pumping systems 1591 LPM capacity
(530 LPM 3 Working + 530 One Standby) at 60 meters head to the overhead storage tanks.
Separate pumping arrangements for flushing water and irrigation, wherever required, shall also
be provided.
From the overhead storage tanks, water shall be distributed through gravity-based distribution
systems comprising vertical risers and horizontal pipelines to all dwelling units and common
facilities. The pumping system shall include control valves, non-return valves, pressure gauges,
isolation valves and all associated accessories necessary for efficient operation. The complete
water supply system shall be designed to ensure reliable, hygienic and adequate supply of
potable water, flushing water and fire-fighting water in accordance with NBC, CPWD and Local
Authority requirements. |
| 6 | Sewer System A separate sewerage network consisting of soil, waste and vent piping, inspection chambers,
manholes and underground sewer lines shall be provided. The sewer pipe would be of between 200 mm to 300 mm diameter. The internal sewerage system shall be connected to the sewage treatment system and approved disposal arrangements. 950 KLD
STP has been taken for sewage disposal.
All soil, waste and sewage generated from toilets, kitchens and other sanitary fixtures shall be
collected through a dedicated underground sewerage network laid at suitable gradients to
ensure efficient flow. Inspection chambers and manholes of 150 mm minimum internal
diametershall be provided at appropriate intervals, junctions, changes in direction and changes
in level as per the approved MEP design.
The sewage treatment plant shall be designed to treat wastewater to the standards prescribed
by the competent authorities. Treated water shall be reused for flushing, landscaping,
horticulture and other non-potable applications wherever feasible. Sludge generated from the
treatment process shall be disposed of through approved methods. The complete sewerage
system shall be designed to prevent leakage, backflow and odour nuisance and shall comply
with applicable NBC, CPWD and Local Authority guidelines. |
| 7 | Drain A comprehensive storm water drainage network along with rainwater harvesting and
groundwater recharge structures shall be developed with pipes of 150 mm diameter. The system shall ensure efficient collection
and disposal of storm water in accordance with approved plans.
Rainwater from terraces, roofs, paved areas and open spaces shall be collected through a
dedicated storm water drainage network comprising suitably designed drains, catch pits,
chambers and pipelines. The collected storm water shall be conveyed to rainwater harvesting
and groundwater recharge structures provided within the project. The project shall include 4
Nos. rainwater harvesting/recharge pits or other approved recharge structures as per the
detailed engineering design.
Adequate filter media, silt traps and desilting chambers shall be provided before groundwater
recharge to prevent choking and contamination. Excess storm water, after groundwater
recharge, shall be safely discharged into the approved municipal storm water drainage system.
The entire drainage system shall be designed to prevent waterlogging and ensure efficient
surface runoff management in accordance with NBC, CPWD and Local Authority guidelines. |
| 8 | Parks Landscaped parks, green courts, recreational open spaces and community greens shall be
developed as per the sanctioned landscape plan. The project incorporates extensive landscaped
open areas within the residential campus.
The landscaped areas shall include lawns, childrens play areas, seating spaces, walking
pathways, gazebos, ornamental plantations and other outdoor recreational facilities as
envisaged in the approved landscape plan. Appropriate hardscape and softscape elements shall
be provided to create a safe, aesthetically pleasing and environmentally sustainable residential
environment. All landscape development shall be carried out using suitable plant species and
approved horticultural practices. |
| 9 | Tree Planting Tree plantation, shrubs, lawns, ground covers and horticultural works shall be undertaken
throughout the project using suitable species as part of the approved landscape development
plan.
The plantation scheme shall comprise avenue trees, ornamental trees, flowering shrubs,
hedges, lawns, seasonal plants and other suitable species selected considering the local climatic
conditions. Adequate irrigation arrangements shall be provided for the maintenance of
landscaped areas. The plantation shall be carried out in accordance with the approved
landscape plan and applicable environmental guidelines. |
| 10 | Design For Electric Supply Including Street Lighting The project shall be provided with HT/LT electrical infrastructure including transformers, HT
panels, LT panels, feeder pillars, metering arrangements, earthing systems and associated
electrical installations. A 11/0.433 KV electrical substation, along with DG set backup for
common area, LED street lighting, landscape lighting and two-wheeler and four-wheeler EV
charging services shall be provided.
The electrical distribution system shall comprise HT/LT cabling, distribution panels, feeder
pillars, cable trenches, earthing network, lightning protection system and associated electrical
infrastructure for reliable power distribution throughout the project. A DG backup system of
1260 kVA capacity shall be provided for operation of essential services and common area
facilities during power failures.
Street lighting, landscape lighting, pathway lighting and common area lighting shall be provided
using energy-efficient LED luminaires. The project shall as required under applicable regulations.
The entire electrical system shall be designed in accordance with applicable IS Codes, CPWD
specifications, Electricity Department requirements and Local Authority guidelines. |
| 11 | Community Buildings No separate community building is proposed within the project. Common community spaces,
landscaped areas and resident-oriented amenities shall be provided as part of the overall
development in accordance with the sanctioned plan.
The project shall provide common recreational spaces, landscaped gathering areas, childrens
play areas, seating zones and other resident-oriented amenities integrated within the open
spaces. These facilities shall be developed as part of the overall residential environment to
encourage community interaction and improve the quality of life of the residents. |
| 12 | Treatment and Disposal System of Sewage and Sullage water A 950 KLD Sewage Treatment Plant (STP) shall be installed for treatment and reuse/disposal of
sewage generated within the project. The treated water shall be utilized for landscaping,
flushing and other permissible non-potable applications in accordance with applicable
regulations.
All sewage and sullage water generated from toilets, kitchens, wash areas and other sanitary
fixtures shall be conveyed through the underground sewerage network to the Sewage
Treatment Plant. The STP shall be designed to treat wastewater to the standards prescribed by
CPCB, UPPCB and other applicable statutory authorities.
The treated water shall be reused for flushing, landscaping, horticulture and other approved
non-potable applications wherever feasible. Excess treated water, if any, shall be disposed of
through the approved disposal system after meeting the prescribed discharge standards. Sludge
generated from the treatment process shall be handled and disposed of through approved
methods in accordance with applicable environmental regulations. The entire treatment and
disposal system shall be designed to prevent contamination, odour nuisance and environmental
pollution. |
| 13 | Solid Waste Management And Disposal System Adequate arrangements for segregation, collection and storage of solid waste shall be provided
within the project. Disposal shall be carried out through the authorized municipal agency in
accordance with applicable regulations.
Solid waste generated within the project shall be segregated at source into biodegradable,
recyclable and inert waste as per applicable guidelines. Separate collection bins and designated
waste collection areas shall be provided within the premises to facilitate efficient handling of
municipal solid waste.
Biodegradable waste shall be processed, wherever applicable, while recyclable waste shall be
stored separately and handed over to authorized recyclers. Non-recyclable waste shall be
disposed of through the authorized municipal agency. The entire solid waste management
system shall comply with the Solid Waste Management Rules, 2016 and other applicable
statutory provisions. |
| 14 | Water Conservation System Rainwater harvesting structures, groundwater recharge systems and water-efficient distribution
infrastructure shall be provided to promote sustainable water management within the project.
The project shall incorporate water conservation measures including rainwater harvesting,
groundwater recharge and reuse of treated wastewater for flushing, landscaping and other
approved non-potable purposes. Water-efficient plumbing fixtures such as low-flow fixtures,
dual flush cisterns and other water-saving devices shall be provided wherever applicable.
Separate plumbing arrangements for potable and recycled water shall be provided wherever
required. Water metering systems shall be installed at suitable locations for monitoring and
efficient management of water consumption. The overall water conservation system shall
comply with NBC, CPWD and applicable Local Authority guidelines. |
| 15 | Energy Management System Including Use of Renewable Energy Energy-efficient LED lighting shall be provided in common areas and external spaces. A 200 kWp
On-grid rooftop solar power system with net metering shall be installed for operation of
common services including lifts, water supply pumps and common area lighting. EV charging
infrastructure for two-wheelers and four-wheelers shall also be provided.
The project shall incorporate energy-efficient electrical systems and equipment to minimize
energy consumption. The rooftop solar photovoltaic system of 200 kWp capacity with net
metering shall supplement power requirements for common services. Common area lighting
shall utilize LED luminaires with suitable lighting controls wherever applicable.
The overall energy management system shall be developed in accordance with applicable
Energy Conservation Building Code (ECBC), GRIHA recommendations (where applicable) and
Local Authority guidelines. |
| 16 | Fire Protection And Fire Safety System The project shall be equipped with a comprehensive fire protection system including fire water
storage tanks, fire pumps, wet risers, hydrants, hose reels, sprinkler systems, addressable fire
alarm systems, emergency lighting, smoke detection systems and pressurized basement
ventilation systems. All fire safety installations shall conform to NBC provisions and Fire
Department requirements.
The fire protection system shall include dedicated fire water storage of 255 KL, comprising
underground and overhead storage, as required under the approved fire-fighting scheme. The
system shall further include main fire pumps of 2850 LPM capacity, jockey pumps of 180 LPM
capacity and standby fire pumps of 2850 LPM capacity for ensuring uninterrupted operation
during emergencies.
The fire-fighting network shall comprise wet risers, landing valves, yard hydrants, hose reels,
sprinkler systems, portable fire extinguishers, fire command centre, addressable fire alarm
system, smoke detection system, manual call points, hooters, emergency lighting and
illuminated exit signage at appropriate locations throughout the project.
Mechanical ventilation and smoke extraction systems shall be provided in the basement
wherever required. Fire pumps shall be connected to emergency power backup to ensure
uninterrupted operation during emergencies. The complete fire protection and life safety
system shall be designed, installed, tested and commissioned in accordance with NBC 2016
(Part-4), Uttar Pradesh Fire Service requirements and other applicable statutory regulations. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services The project shall provide landscaped open spaces, parks, pedestrian pathways, parking facilities,
security infrastructure, utility services and other common amenities as per the sanctioned plan
to ensure a healthy and comfortable residential environment.
The development shall include childrens play areas, landscaped recreational spaces, seating
areas, pedestrian circulation, universal accessibility provisions, security infrastructure and visitor
facilities integrated within the project. Adequate parking for residents and visitors, including
accessible parking wherever required, shall be provided in accordance with the sanctioned plan
and applicable building regulations. |
| 18 | Emergency Evacuation Services Multiple staircases, fire exits, emergency lighting, evacuation routes and life-safety systems shall
be provided in accordance with applicable fire and life-safety requirements.
The project shall provide adequate means of escape including protected staircases, fire exits,
refuge areas (where applicable), emergency lighting, illuminated exit signage and evacuation
routes. Emergency evacuation provisions shall be designed to facilitate safe and orderly
evacuation of occupants during emergencies in accordance with NBC and Fire Department
requirements. |
| 19 | Other Miscellaneous Work NA |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 28 May 2031.
Sanctioned by Lucknow Development Authority · 18,411 sqm of land · an approved plan of 5 blocks and 1392 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| Government Building/Group Housing/19124/LDA/BP/26-27/1973/29052026 | 29 May 2026 | 28 May 2031 | 28 May 2034 | 28 May 2031 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
39 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 170 | 207 | Khasra |
| 171 | 390 | Khasra |
| 172 | 92 | Khasra |
| 173 | 820 | Khasra |
| 174 | 689 | Khasra |
| 175 | 30 | Khasra |
| 177 | 677 | Khasra |
| 222 | 105 | Khasra |
| 223 | 105 | Khasra |
| 225 | 680 | Khasra |
| 226Kh | 1530 | Khasra |
| 227 | 113 | Khasra |
| 400A | 490 | Khasra |
| 400B | 340 | Khasra |
| 401 | 480 | Khasra |
| 402 | 99 | Khasra |
| 403 | 1171 | Khasra |
| 405 | 3067 | Khasra |
| 408 | 1800 | Khasra |
| 409 | 3054 | Khasra |
| 410 | 510 | Khasra |
| 422 | 267 | Khasra |
| 228 | 465 | Khasra |
| 407 | 402 | Khasra |
| 399 | 828 | Khasra |
| Khatauni extract · 1424F Khasra No. 170 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 171 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 172 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1415F, Khasra No. 173 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, khasra No. 222 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 223 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 228 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 400A An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 400B An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 177 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 401 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 402 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1425F, Khasra No. 175 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1425F, Khasra No. 403 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 405 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1424F, Khasra No. 408 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434F,Khasra No.174 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434F, Khasra No. 225 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434F, Khasra No. 226KHA An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434F, Khasra No. 227 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434F, Khasra No. 407 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434F, Khasra No. 410 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434F, Khasra No. 422 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Dhara 6 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1419F Khasra No. 409 with signed order An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Affidavit for Mohan Road Yojna An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Resumption Kaliyakheda Order 1 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Resumption Kaliyakheda Commissioner Order 2 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1429-1434 Khasra No. 399 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Certified Khatauni Resumption- Khasra No. 174, 225, 226Kh, 227, 407,410, 422 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Land Area Chart An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 7 Sept 2026 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 3 Aug 2026 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 27 Jun 2026 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 27 Jun 2026 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 7 Jul 2026 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 7 Jul 2026 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 3 Aug 2026 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 20 Jul 2026 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 4 Jul 2026 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 29 Aug 2026 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 29 Aug 2026 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 10 Sept 2026 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 4 Jul 2026 ↗ |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | New | 29 Aug 2026 ↗ |
Quarterly progress reports
1 filed report
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
1 quarterly progress report is on file with UPRERA, for 2026-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2026-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Lucknow Development Authority |
| Role | Promoter · current |
| RERA ID | UPRERAPRM10102 |
| PAN | AAALL0016F |
| CIN / TAN | LKNL00280A |
| Registered address | Lucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | M/S.LDA COLLECTION ACCOUNT FOR ADITI APARTMENTSBankICICI BANKBranchHAZRATGANJBranch address28/10, Ashok Marg, Hazratganj, Lucknow, Uttar Pradesh-226001Branch districtLucknow, Uttar PradeshA/C no.IFSCICIC0006281Branch emailvinesh.sondhiya@icicibank.com |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | M/S.LDA SEPARATE ACCOUNT FOR ADITI APARTMENTSBankICICI BANKBranchHAZRATGANJBranch address28/10, ASHOK MARG, HAZRATGANJ, LUCKNOW UTTAR PRADESH-226001Branch districtLucknow, Uttar PradeshA/C no.IFSCICIC0006281 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | M/S.LDA Transaction Account for Aditi ApartmentsBankICICI BANK LIMITEDBranchLucknow Hazratganj BranchBranch address28/10 ASHOK MARG, HAZRATGANJ, LUCKNOW, UTTAR PRADESHBranch districtLucknow, Uttar PradeshA/C no.IFSCICIC0006281 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 584 (Under Registration - 5 ) → 584 (Under Registration - 4 ) changed in Estanzo’s record | 13 Oct 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 13 Oct 2026 |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Aditi Apartments
Is Aditi Apartments RERA registered?
Yes. Aditi Apartments is registered with UPRERA under registration number UPRERAPRJ710087, registered on 23 Sept 2026. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Aditi Apartments?
The completion date filed with UPRERA is 28 May 2031. No completion certificate is on record yet.
Who is the builder of Aditi Apartments?
Lucknow Development Authority is the promoter entity that filed Aditi Apartments with UPRERA (promoter RERA ID UPRERAPRM10102). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does Aditi Apartments have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Aditi Apartments located?
Aditi Apartments is registered in Kaliya Khera, Lucknow, as filed with UPRERA.
What configurations are available in Aditi Apartments?
The unit plan filed with UPRERA lists 2 BHK and 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Aditi Apartments?
The approved unit plan filed with UPRERA runs from 30 to 39 m² of carpet area (about 327 to 424 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Aditi Apartments?
The approved unit plan describes 5 blocks and 1,392 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Aditi Apartments?
About 306 units per acre: 1,392 planned units across 4.55 acres (18,411 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗