ANANT NAGAR YOJNA ADARSH KHAND

UPRERARegistered

ANANT NAGAR YOJNA ADARSH KHAND is a RERA-registered mixed project by Lucknow Development Authority in Kaliya Khera Pyarepur, Tehsil Sarojini Nagar, Lucknow (RERA ID UPRERAPRJ885169). Registered with a completion deadline of 9 Mar 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
1.25%Q3'25
2.82%Q4'25
5.64%Q1'26
7.35%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ885169
Project categoryMixed
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Apr 2025
Project duration60 months
AddressKaliya Khera Pyarepur, Tehsil Sarojini Nagar, Kaliya Khera Pyarepur, Tehsil Sarojini Nagar, Sarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompetent authority
Applicant addressLucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    7/3/AA-3/25

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered3 Apr 2025
Original completion9 Mar 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹16,56,000
Sanctioning authorityLucknow Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Muralage
License CA/2006/37491
A-3/269 Vibhav Khand, Gomti Nagar, Lucknow-226010
Engineer
Sanjeev Kumar
Pradhikaran Bhawan, Vipin Khand Gomti Nagar,Lucknow pin226010
Contractor
Lucknow Development Authority
Pradhikaran Bhawan, Gomti Nagar, Lucknow
Sr.Development work declared to RERA
1Demarcation of Plots
Demarcation of plots will be done after the development work will be completed
2Boundary Wall
No boundary wall is propsoed
3Road Work
The roads in sector 6 has been designed with varying width 24,12,18 & 9m. Pathways, Cycle Track, are provided to enhance mobility
4Footpaths
The footpath will be developed with interlocking tiles and electric trench will run through footpath. The footpath will be 1.2mtrs to 1.8 mtrs as per road width.
5Water Supply Including Drinking Water Facilities
The water will be supplied through borewell and Overhead Tanks and UG Tanks for commercial tanks. The diameter of the water pipeline is 100mm to 250mm as per population and load demand.
6Sewer System
The provision of seweage chamber for sector -06 to manage waste water efficiently. The diameter of sewage pipe is 200mm to 800mm as per population. The material of pipe is DWC SN8.
7Drain
Surafce drain is of RCC and the diameter is 300mm to 1200mm and depth is 300mm to 1800mm
8Parks
Parks will be developed as per sanction layout and the parks will have brick walls of height 5ft as per design
9Tree Planting
Landscaping & Tree Plantation on green belts along roads and parks to create a greener, healthier & more pleasant environment.
10Design For Electric Supply Including Street Lighting
Electric work is proposed including street light on each external road through electric pole. Street Lighting is provided for the road visibility. The main substation is 220/33KV and second tier substation is 33/11 KVA and sectoral 11/.433 KV substation.
11Community Buildings
A area of 3870.25Sqm 6/COM-01 is provided for community Buildings
12Treatment and Disposal System of Sewage and Sullage water
It Has been provided on the sector-08
13Solid Waste Management And Disposal System
A Big plot Has been provided for garbage of entire sector will be collected in sector-01 and A garbage plot has been provided for each sector.
14Water Conservation System
Rain water harvesting pits are provided on the parks.
15Energy Management System Including Use of Renewable Energy
100% Led Lighting Considered Instead Of Cfl Or Incandescent Lamps,Provision Of Minimum 3 Star Rated Electrical Equipments,Provision Of Energy Management Strategy & Analysis Provisions With Multifunction Meters Compatible With Scada,Considering 2 % Voltage Drop For Power Distribution In Lt & 4% In Ht,Plug In Provision In Feeder Panels For Other Renewable Sources To Reduce Distribution Losses ,Astronomical & Timer Based Switching For Street Lighting
16Fire Protection And Fire Safety System
1 FIRE STATION plot has been provided for sector 6 and 7. the area of 7/FS-01= 1978.00 Sqm is provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Area reserved for such amenities are demarcated in the sanction layout
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 9 Mar 2030.

Sanctioned by Lucknow Development Authority · 2,19,765 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
7/3/AA-3/2510 Mar 20259 Mar 20309 Mar 20339 Mar 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

245 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
5024390Khasra
3716920Khasra
3956590Khasra
1565130Khasra
3476840Khasra
657530Khasra
712840Khasra
7144430Khasra
4081800Khasra
320340Khasra
321130Khasra
3244810Khasra
433B560Khasra
350890Khasra
3591490Khasra
7361490Khasra
3992400Khasra
7425220Khasra
3193240Khasra
336250Khasra
7464440Khasra
373320Khasra
35860Khasra
3911770Khasra
7198850Khasra
315G6130Khasra
3175300Khasra
731A2670Khasra
731B300Khasra
522130Khasra
709190Khasra
711190Khasra
718K1480Khasra
763KH820Khasra
7641010Khasra
769950Khasra
7387080Khasra
156K60Khasra
383160Khasra
3981900Khasra
404130Khasra
2781260Khasra
3643160Khasra
7323510Khasra
721M1270Khasra
4162650Khasra
436510Khasra
6982280Khasra
4382340Khasra
381630Khasra
3821010Khasra
7202880Khasra
274190Khasra
708190Khasra
276280Khasra
7222530Khasra
770KH7590Khasra
4053920Khasra
6611240Khasra
3921680Khasra
656550Khasra
3752990Khasra
353130Khasra
354130Khasra
367380Khasra
3691260Khasra
371230Khasra
2283700Khasra
171390Khasra
724KH2280Khasra
6962500Khasra
4203160Khasra
4032670Khasra
7452330Khasra
475380Khasra
6651620Khasra
667A250Khasra
667B890Khasra
335K220Khasra
346630Khasra
671760Khasra
7459320Khasra
7292210Khasra
222190Khasra
7331000Khasra
6632530Khasra
726B50Khasra
7262930Khasra
412380Khasra
756840Khasra
330700Khasra
715K160Khasra
7681480Khasra
7403400Khasra
221190Khasra
519130Khasra
521130Khasra
666A920Khasra
666B380Khasra
400A490Khasra
400B340Khasra
676KH3040Khasra
315KH630Khasra
3963780Khasra
6606150Khasra
5182660Khasra
3701140Khasra
3773220Khasra
385810Khasra
1663020Khasra
7495100Khasra
679K1670Khasra
682K1260Khasra
7506900Khasra
172220Khasra
36660Khasra
704250Khasra
516kh1520Khasra
1593560Khasra
7583820Khasra
401480Khasra
7002350Khasra
3621140Khasra
3631260Khasra
3321800Khasra
7015900Khasra
721MI3790Khasra
6541510Khasra
5141170Khasra
7577700Khasra
7702020Khasra
710250Khasra
7711930Khasra
502A1900Khasra
502B630Khasra
425K110Khasra
426K260Khasra
763K190Khasra
50590Khasra
765K510Khasra
7661320Khasra
5061220Khasra
7551940Khasra
3341260Khasra
335KH310Khasra
741A3670Khasra
335G160Khasra
348510Khasra
741B540Khasra
3491900Khasra
279630Khasra
4022010Khasra
724K4430Khasra
315K4640Khasra
3167120Khasra
6621210Khasra
3652530Khasra
3254740Khasra
681510Khasra
4131150Khasra
414510Khasra
658470Khasra
3317410Khasra
719340Khasra
7235850Khasra
6692780Khasra
335G440Khasra
511250Khasra
321KH1260Khasra
322690Khasra
677630Khasra
4321630Khasra
333750Khasra
3358330Khasra
1551330Khasra
330760Khasra
3775220Khasra
507S130Khasra
3361280Khasra
3574110Khasra
436S890Khasra
4042820Khasra
349190Khasra
3502530Khasra
3728340Khasra
3928370Khasra
353630Khasra
333S1510Khasra
50430Khasra
3676610Khasra
4712960Khasra
381250Khasra
17212760Khasra
3756930Khasra
43150Khasra
1474830Khasra
4094450Khasra
333S760Khasra
334S3430Khasra
3913650Khasra
4698840Khasra
333S630Khasra
508250Khasra
3135850Khasra
3631440Khasra
405S2120Khasra
405S360Khasra
4063340Khasra
4231520Khasra
3647630Khasra
398/21060Khasra
4074960Khasra
358130Khasra
35913080Khasra
360380Khasra
40170Khasra
3511650Khasra
4706300Khasra
1671010Khasra
1733410Khasra
1719550Khasra
433A1000Khasra
504650Khasra
372510Khasra
3707910Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · 182/AC/PR/2025
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Khatauni extract · 1427-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New26 Mar 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New12 Mar 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New12 Mar 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New12 Mar 2025 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New12 Mar 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New12 Mar 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New12 Mar 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New12 Mar 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New12 Mar 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New26 Mar 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New26 Mar 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New26 Mar 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New12 Mar 2025 ↗

Quarterly progress reports

5 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

5 quarterly progress reports are on file with UPRERA, covering 2025-Q2 to 2026-Q2.

QuarterConstructionCertificates
2025-Q21.25%CA ↗ · Arch ↗ · Eng ↗
2025-Q32.82%CA ↗ · Arch ↗ · Eng ↗
2025-Q45.64%CA ↗ · Arch ↗ · Eng ↗
2026-Q17.35%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameLucknow Development Authority
RolePromoter · current
RERA IDUPRERAPRM10102
PANAAALL0016F
CIN / TANLKNL00280A
Registered addressLucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SECRETARY LDA COLLECTION ACCOUNT FOR ANANT NAGAR YOJNA ADARSH KHANDBankICICI BANKBranchASHOK MARGBranch address28/10 ASHOK MARG HAZRATGANJBranch districtLucknowA/C no.IFSCICIC0006281Branch emailvinesh.sondhiya@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SECRETARY LDA SEPARATE ACCOUNT FOR ANANT NAGAR YOJNA ADARSH KHANDBankICICI BANKBranchASHOK MARGBranch address28/10 ASHOK MARG HAZRATGANJBranch districtLucknow, Uttar PradeshA/C no.IFSCICIC0006281
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SECRETARY LDA TRANSACTION ACCOUNT FOR ANANT NAGAR YOJNA ADARSH KHANDBankICICI BANKBranchASHOK MARGBranch address28/10 ASHOK MARG HAZRATGANJ LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCICIC0006281
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

9 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
Promoter’s complaints tally (all their projects)584 (Under Registration - 5 ) → 584 (Under Registration - 4 )
changed in Estanzo’s record
13 Oct 2026
Promoter’s complaints tally (all their projects)583 (Under Registration - 4 ) → 584 (Under Registration - 5 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)583 (Under Registration - 5 ) → 583 (Under Registration - 4 )
changed in Estanzo’s record
19 Sept 2026
Promoter’s complaints tally (all their projects)583 (Under Registration - 7 ) → 583 (Under Registration - 5 )
changed in Estanzo’s record
9 Sept 2026
Promoter’s complaints tally (all their projects)582 (Under Registration - 7 ) → 583 (Under Registration - 7 )
changed in Estanzo’s record
7 Sept 2026
Promoter’s complaints tally (all their projects)580 (Under Registration - 5 ) → 582 (Under Registration - 7 )
changed in Estanzo’s record
31 Aug 2026
Promoter’s complaints tally (all their projects)579 (Under Registration - 5 ) → 580 (Under Registration - 5 )
changed in Estanzo’s record
23 Aug 2026
Promoter’s complaints tally (all their projects)578 (Under Registration - 4 ) → 579 (Under Registration - 5 )
changed in Estanzo’s record
16 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 13 Oct 2026 · 8 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ANANT NAGAR YOJNA ADARSH KHAND

Is ANANT NAGAR YOJNA ADARSH KHAND RERA registered?

Yes. ANANT NAGAR YOJNA ADARSH KHAND is registered with UPRERA under registration number UPRERAPRJ885169, registered on 3 Apr 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ANANT NAGAR YOJNA ADARSH KHAND?

The completion date filed with UPRERA is 9 Mar 2030. No completion certificate is on record yet.

Who is the builder of ANANT NAGAR YOJNA ADARSH KHAND?

Lucknow Development Authority is the promoter entity that filed ANANT NAGAR YOJNA ADARSH KHAND with UPRERA (promoter RERA ID UPRERAPRM10102). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does ANANT NAGAR YOJNA ADARSH KHAND have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ANANT NAGAR YOJNA ADARSH KHAND located?

ANANT NAGAR YOJNA ADARSH KHAND is registered in Kaliya Khera Pyarepur, Tehsil Sarojini Nagar, Lucknow, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗