Timeline Bar
Registered5 Oct 2017
Promised31 May 2021
Today29 Jul 2026
Timeline
Promised completion31 May 2021
Revised completion31 May 2021
Actual completion—
Possession delay62 mo delay
Registration & Cost Details
Registration fee (in ₹)₹19,000
Project cost (in ₹ Lakhs)₹1,051 Lakhs
Project duration53 months
Project categoryResidential
Locality—
Original start date16 Jul 2017
Proposed start date16 Jul 2017
Inventory
Total units42
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 12 | 31.04–59.95 |
| 2 BHK | 20 | 53.86–74.13 |
| 3 BHK | 10 | 56.72–103.48 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8294631800
Emailrera@agranihomes.in
Coordinator7080300122
AddressBRANCH OFFICE -D58/12 A-86 Gandhi Nagar Colony Sigra Varanasi UP 221002
contact no
7080300119
7080300112
7080300110
7080300100
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 32/N.A.V. | 1 Jun 2016 | 31 May 2021 | 31 May 2021 | 31 May 2021 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 79 | 2902.007 Sq mtr | — |
| 79 | 2902.007 | Khasra |
Approved Unit Plan
Unit plan rows on file42
Total flats (sum of rows)42
Blocksa
Floor types1 BHK, 2 BHK, 3 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| IN-UP00663003882949M | 14 Oct 2014 | — | — |
Frequently Asked Questions
What is the RERA registration number of AGRANI DAKSHA?
The RERA registration number of AGRANI DAKSHA is UPRERAPRJ11874, as recorded on the UP-RERA portal.
What is the RERA status of AGRANI DAKSHA?
As reported by UP-RERA, the status of AGRANI DAKSHA is "Registered".
Where is AGRANI DAKSHA located?
As reported to UP-RERA, AGRANI DAKSHA is located at Varanasi, Varanasi, Uttar Pradesh.
When will AGRANI DAKSHA be completed?
The latest completion date reported to UP-RERA for AGRANI DAKSHA is 31 May 2021.
Is AGRANI DAKSHA delayed?
Measured against the latest completion date reported to UP-RERA, AGRANI DAKSHA is 62 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026