ALANKAR is a RERA-registered real-estate project in Lucknow (RERA ID UPRERAPRJ11683). Its RERA-registered completion deadline (31 Mar 2019) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ11683 |
| Applicant type | Partnership Firm |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 20 Dec 2011 |
| Original start | 20 Dec 2011 |
| Project duration | 88 |
| Address | Lucknow, Lucknow |
| RERA registered | 15 Aug 2017 |
| Promised completion | 31 Mar 2019 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹9,050 |
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | 3 | 414 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 35151 | 21 Dec 2011 | 20 Dec 2016 | 31 Mar 2019 |
| Khasra | Area | Type |
|---|---|---|
| PLOT NO 7 MUNICIPAL NO 12/163 | 905 SQ MTR | — |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 14375/307-464/14550/1 | 27 Jul 2012 | — | — |
Yes. ALANKAR is registered with UPRERA under registration number UPRERAPRJ11683, registered on 15 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
ALANKAR is 88 months past the completion date filed with UPRERA (31 Mar 2019), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
ALANKAR is registered in Lucknow, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗