ANANDAM CITY

UPRERARegistered

ANANDAM CITY is a RERA-registered residential project by HI-TECH COLONIZERS in Moradabad (RERA ID UPRERAPRJ270442). Registered with a completion deadline of 20 Nov 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
100%Q3'25
100%Q4'25
100%Q1'26
100%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ270442
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMoradabad Development Authority
Proposed start30 Nov 2021
Project duration60 months
AddressMoradabad, Moradabad
TehsilMoradabad
Applicant typePartnership Firm
Applicant addressPandit Nagla By Pass, Sambhal Road, Moradabad
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MBDA/LD/20-21/0342

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered10 Sept 2022
Original completion20 Nov 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹4,56,000
Sanctioning authorityMoradabad Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Rajat Anand and Associates
License CA201466472
21,Shivpuri, Moradabad
Engineer
Koncept Design Consortium Pvt Ltd
389,Ground Floor, IP Colony, Sec 30-33, Faridabad - 121003
Contractor
Pioneer Construction
G-23, Wave Green, Moradabad
Sr.Development work declared to RERA
1Demarcation of Plots
Plotting in East, Plotting in West, Plotting in North and main Road in South.
2Boundary Wall
On Going Construction on site, Boundary Wall is up to 6 Ft. in Height.
3Road Work
Survey and Marking Done, Inner Roads are 18 Meter,12 Meter,9 Meter and 7.5 Meter Wide and Service Lane is 3 Meter Wide.
4Footpaths
Footpaths are 7 Meter and 5 Meter wide as proposed by Architect.
5Water Supply Including Drinking Water Facilities
Water Supply will be provided by Developer through Pump Room.
6Sewer System
Sewer System will be Provided by Developer and STP System is Also Proposed by Developer.
7Drain
Drainage Lines are provided by developer with Manholes and Inspection Chamber. STP is proposed by developer
8Parks
Land has been reserved for Parks as per Layout. Green Area and Tree Planting will be provided by Developer in Parks.
9Tree Planting
Tree Planting will be done along the Roads and tree planting will be provided by Developer.
10Design For Electric Supply Including Street Lighting
Drawings are attached as provided by Electrical Consultant.
11Community Buildings
N/A
12Treatment and Disposal System of Sewage and Sullage water
STP system has been Proposed by Developer for Treatment and Disposal system of Sewage and Sullage Water
13Solid Waste Management And Disposal System
Solid Waste Management and Disposal System has been Provided by Developer as per Requirement.
14Water Conservation System
Rain water Harvesting Tanks will be constructed on site for Water Conservation.
15Energy Management System Including Use of Renewable Energy
N/A
16Fire Protection And Fire Safety System
N/A
17Social Infrastructure And Other Public Amenities Including Public Health Services
N/A
18Emergency Evacuation Services
N/A
19Other Miscellaneous Work
To be Executed on site as per Sanctioned Plan
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 22 Nov 2026.

Sanctioned by Moradabad Development Authority · 90,118 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MBDA/LD/20-21/034218 Nov 202122 Nov 202617 Nov 202920 Nov 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

42 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
315mi4010Khasra
317mi2920Khasra
4601300Khasra
461mi850Khasra
461mi790Khasra
464mi and 4641700Khasra
460mi and 460960Khasra
4662170Khasra
467/2650Khasra
467610Khasra
4682590Khasra
469mi7170Khasra
470530Khasra
4717250Khasra
4722020Khasra
4734850Khasra
4742510Khasra
4751740Khasra
4766190Khasra
4771170Khasra
4787090Khasra
479mi20390Khasra
479mi5380Khasra
4913720Khasra
4921230Khasra
4931730Khasra
4941300Khasra
495500Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 1735
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1221
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1295
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1294
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1220
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1222
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 825
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 822
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 821
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 823
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1219
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7704
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1174
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1173
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1294
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1175
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1417-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · AREA CHART
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 1245
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1246
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1247
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1248
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1249
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1292
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1293
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1296
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 546
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1172
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1713
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1715
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1717
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1726
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1729
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1779
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1836
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 2308
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 8054
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 1734
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 164
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New22 Aug 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New17 Jul 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New17 Jul 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New17 Jul 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New17 Jul 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New17 Jul 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New17 Jul 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New20 Aug 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New17 Jul 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New17 Jul 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New17 Jul 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New17 Jul 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New19 Aug 2022 ↗

Quarterly progress reports

19 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

19 quarterly progress reports are on file with UPRERA, covering 2021-Q3 to 2026-Q1.

QuarterConstructionCertificates
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q2100%CA ↗ · Arch ↗ · Eng ↗
2025-Q3100%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
2026-Q1100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameHI-TECH COLONIZERS
RolePromoter · current
RERA IDUPRERAPRM157342
PANAAFFH7844E
CIN / TANLKNH05568D
Registered addressPandit Nagla By Pass, Sambhal Road, Moradabad
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameMAPPLE INFRA
RoleCo-promoter
Applicant typePartnership Firm
AddressPt. Nagla Bye Pass, Sambhal Road, Moradabad
RERA contact

Nearby projects

Moradabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Hi-tech Colonizers Rera collection Account for Anandam CityBankICICI BankBranchGandhi Nagar BranchBranch addressA-17, Gandhi Nagar, Opp Old city Rly Stn. MoradabadBranch districtMoradabad, Uttar PradeshA/C no.IFSCICIC0001587
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Hi-Tech Colonizers Rera Separate Bank Account for Anandam CityBankICICI BankBranchGandhi Nagar BranchBranch addressA-17,Gandhi Nagar, Opp City Rly. Stn., MoradabadBranch districtMoradabad, Uttar PradeshA/C no.IFSCICIC0001587
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Hi-Tech Colonizers Rera Transaction Account For Anandam CityBankICICI BankBranchGandhi Nagar BranchBranch addressA-17,Gandhi Nagar, Opp Old City Rly. Stn., MoradabadBranch districtMoradabad, Uttar PradeshA/C no.IFSCICIC0001587
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ANANDAM CITY

Is ANANDAM CITY RERA registered?

Yes. ANANDAM CITY is registered with UPRERA under registration number UPRERAPRJ270442, registered on 10 Sept 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ANANDAM CITY?

The completion date filed with UPRERA is 20 Nov 2026. No completion certificate is on record yet.

Who is the builder of ANANDAM CITY?

HI-TECH COLONIZERS is the promoter entity that filed ANANDAM CITY with UPRERA (promoter RERA ID UPRERAPRM157342). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does ANANDAM CITY have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ANANDAM CITY located?

ANANDAM CITY is registered in Moradabad, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗