Registered12 Aug 2017
Promised26 Dec 2018
Completed7 Aug 2020

Timeline

Promised completion26 Dec 2018
Revised completion26 Dec 2018
Actual completion7 Aug 2020
Possession delay19 mo delay

Registration & Cost Details

Registration fee (in ₹)₹21,500
Project cost (in ₹ Lakhs)₹1,395 Lakhs
Project duration70 months
Project categoryResidential
Locality
Original start date26 Mar 2013
Proposed start date26 Mar 2013

Inventory

Total units76
Unit TypeUnitsCarpet Area (sqm)
2 BHK7652.87–53.34

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9897740047
Emailapicalbuildtech@gmail.com
Coordinator9997195382
AddressAPICAL BUILDTECH PRIVATE LIMITED REGD. ADD.: - 1449/188, GALI NO. – 03, BLOCK – A, DURGA PURI, DELH

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
341/01/GH/12

Revalidated: 341/01/GH/12 (29 Dec 2017)

29 Dec 201229 Dec 2017

Revalidated upto: 28 Dec 2020

26 Dec 201828 Dec 2020
341/01/GH/12

Revalidated: 341/01/GH/12 (29 Dec 2017)

29 Dec 201229 Dec 2017

Revalidated upto: 28 Dec 2020

26 Dec 201828 Dec 2020
341/01/GH/12

Revalidated: 341/01/GH/12 (29 Dec 2012)

29 Dec 201228 Dec 2017

Revalidated upto: 28 Dec 2020

26 Dec 201828 Dec 2020

Land Parcels

Khasra No.AreaPlot Type
3723150 sqm
373145 sqm
3723150Khasra
373145Khasra

Approved Unit Plan

Unit plan rows on file16
Total flats (sum of rows)76
BlocksA, B
Floor types2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
287321 Mar 2012

Frequently Asked Questions

What is the RERA registration number of ANANDAM HOMES?

The RERA registration number of ANANDAM HOMES is UPRERAPRJ9935, as recorded on the UP-RERA portal.

What is the RERA status of ANANDAM HOMES?

As reported by UP-RERA, the status of ANANDAM HOMES is "Registered".

Where is ANANDAM HOMES located?

As reported to UP-RERA, ANANDAM HOMES is located at Bareilly, Bareilly, Uttar Pradesh.

Is ANANDAM HOMES completed?

As reported to UP-RERA, ANANDAM HOMES was completed on 7 Aug 2020.

Is ANANDAM HOMES delayed?

Measured against the latest completion date reported to UP-RERA, ANANDAM HOMES is 19 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.