PHOOL NARAYAN VILLAS

UPRERARegistered

PHOOL NARAYAN VILLAS is a RERA-registered residential project by JANG BAHADUR SINGH in HARUNAGLA, Bareilly (RERA ID UPRERAPRJ459224). Registered with a completion deadline of 5 Jan 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
47.66%Q3'25
96%Q4'25
96%Q1'26
100%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ459224
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryBareily Development Authority
Proposed start8 Jan 2024
Project duration60 months
AddressKHASRA NO. 39/1/4 & 39/1/3 (P) VILLAGE HARUNAGLA , NEAR PHOOL NARAYAN PARK COLONY, HARUNAGLA, Bareilly, Bareilly
TehsilBareilly
Applicant typeIndividual
Applicant address14,MAAN SAROVAR GARDEN,,HARUNAGLA,,BAREILLY,UTTAR PRADESH,243001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLOTTED RESI DEVELOPMENT / PLOTTED HOUSING / 01993 / BDA/LD/23-24/0318/12082023

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered15 Jul 2024
Original completion5 Jan 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹37,500
Sanctioning authorityBareily Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
UDIT CHAUDHARY
License CA/2016/79004
9 PANCHSHEEL NAGAR , PILIBHIT BYEPASS ROAD, BAREILLY.
Engineer
CAD ARCHITECTS
9 PANCHSHEEL NAGAR , PILIBHIT BYEPASS ROAD , BAREILLY
Contractor
SHRI SHIVA ENTERPRISES
14 , MANSAROVAR GARDEN , HARUNAGLA , BAREILLY
Sr.Development work declared to RERA
1Demarcation of Plots
DEMARCATION OF ALL 23 RESIDENCIAL PLOTS WITH THREE COMMERCIAL PLOTS AND ROAD AND PARK DEMARCATION WILL BE DONE BY US AFTER THE APPROVAL FROM RERA.
2Boundary Wall
BOUNDARY WALL UPTO 2 MT. HEIGHT WILL BE CONSTRUCTED WITH BOTH SIDE PLASTER AND WHITE WASHING.
3Road Work
AFTER THE DEMARCATION THE EARTH FILLING WILL BE DONE FROM NATURAL GROUND LAVEL TO UPTO .60 MT FOR ROADS AND THEN C.C. ROAD WILL BE LAYED STEP BY STEP.
4Footpaths
FOOT PATHS OF .60 MT WIDE ON BOTH SIDE OF ROADS WILL BE DONE WITH CEMENT INTERLOCKING TILES AND ALSO IN THE PARK ALL THE SIDES A PATHWAY WILLBE CONSTRUCTED.
5Water Supply Including Drinking Water Facilities
AS PER DECLARED TO THE LOCAL AUTHORITY , THE INDIVIDUAL SUBMERSIBLES WILL BE PREPARED AND IMPLEMENTED TO EACH UNIT INDIVIDUALLY. SO THERE IS NO NEED OF WATER SUPPLY. PLEASE REFER TO SANCTIONED MAP FOR THE NOTE WRITTEN RELATED TO THIS.
6Sewer System
SEWER LINE WILL BE LAYED UNDER THE ROAD AND WILL BE CONNECTED TO THE SEWER LINE FOLLOWING THE MAIN ROAD.
7Drain
DRAIN LINE WILL ALSO BE PREPARED ON BOTH THE SIDES OF ROAD AND WILL BE CONNECTED TO THE MAIN DRAIN LINE FOLLOWING THE ROAD AFTER BEING CLEANED BY STP
8Parks
BOTH THE PARKS WILL BE BOUNDED BY M.S. GRILL AND TREES WILL BE PLANTED , ALSO THE PATHWAY WILL BE PROVIDED FOR WALKING WITH LIGHTING LAMP AND GRASS WILL ALSO BE PLANTED IN THE COMPLETE PARK
9Tree Planting
TOTAL NO OF 46 TREES WILL BE PLANTED INCLUDING BOTH THE PARKS AND ALSO IN FRONT OF THE HOUSES UNDER THE FOOTPATH AREA.
10Design For Electric Supply Including Street Lighting
WE WILL PROVIDE THE ELECTRICITY LINE WITH STREET LAMPS ALL OVER
11Community Buildings
N/A
12Treatment and Disposal System of Sewage and Sullage water
N/A
13Solid Waste Management And Disposal System
N/A
14Water Conservation System
RAIN WATER HARVESTING IS BEING PROVIDED AS PER THE SANCTIONED LAYOUT
15Energy Management System Including Use of Renewable Energy
N/A
16Fire Protection And Fire Safety System
N/A
17Social Infrastructure And Other Public Amenities Including Public Health Services
N/A
18Emergency Evacuation Services
N/A
19Other Miscellaneous Work
N/A
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 5 Jan 2029.

Sanctioned by Bareily Development Authority · 6,427 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLOTTED RESI DEVELOPMENT / PLOTTED HOUSING / 01993 / BDA/LD/23-24/0318/120820236 Jan 20245 Jan 20295 Jan 20325 Jan 2029
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

24 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
39/1/4 AND 39/1/3(P)6427.90Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 2018-2024
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Allotment letter from the authority · T201812130101026
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Sale deed · 123456789
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New30 Jan 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New30 Jan 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New30 Jan 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New30 Jan 2024 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New3 May 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New30 Jan 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New30 Jan 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New30 Jan 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New9 Jan 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Jan 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New27 Apr 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New30 Jan 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New30 Jan 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New27 Apr 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New30 Jan 2024 ↗

Quarterly progress reports

10 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

10 quarterly progress reports are on file with UPRERA, covering 2023-Q4 to 2026-Q1.

QuarterConstructionCertificates
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q247.66%CA ↗ · Arch ↗ · Eng ↗
2025-Q396%CA ↗ · Arch ↗ · Eng ↗
2025-Q496%CA ↗ · Arch ↗ · Eng ↗
2026-Q1100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameJANG BAHADUR SINGH
RolePromoter · current
RERA IDUPRERAPRM100367
PANBYGPS7899A
Registered address14,MAAN SAROVAR GARDEN,,HARUNAGLA,,BAREILLY,UTTAR PRADESH,243001
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameVIDYA DEVI
RoleCo-promoter
Applicant typeIndividual
Address14, MAANSAROVAR GARDEN, HARUNAGLA, BAREILLY, UP-243001
RERA contact

Nearby projects

Bareilly

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
MR. JANG BAHADUR SINGH - PNV COLLECTION ACCOUNTBankSTATE BANK OF INDIABranchCOMMERCIAL BRANCH , BAREILLYBranch address148 CIVIL LINES SBI ADMINISTRATIVE OFFICE, GROUND FLOOR, BAREILLYBranch districtBareilly, Uttar PradeshA/C no.IFSCSBIN0017644Branch emailSBI.17644@SBI.CO.IN
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
MR. JANG BAHADUR SINGH - PNV SEPARATE ACCOUNTBankSTATE BANK OF INDIABranchCOMMERCIAL BRANCH , BAREILLY.Branch address148 CIVIL LINE , SBI ADMINISTRATIVE OFFICE, GROUND FLOOR , BAREILLYBranch districtBareilly, Uttar PradeshA/C no.IFSCSBIN0017644
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
MR. JANG BAHADUR SINGH - PNV TRANSACTION ACCOUNTBankSTATE BANK OF INDIABranchCOMMERCIAL BRANCH, BAREILLYBranch address148 CIVIL LINES , SBI ADMINISTRATIVE OFFICE, GROUND FLOOR , BAREILLYBranch districtBareilly, Uttar PradeshA/C no.IFSCSBIN0017644
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Default-on-QPR flagtrue → false
changed in Estanzo’s record
23 Aug 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about PHOOL NARAYAN VILLAS

Is PHOOL NARAYAN VILLAS RERA registered?

Yes. PHOOL NARAYAN VILLAS is registered with UPRERA under registration number UPRERAPRJ459224, registered on 15 Jul 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for PHOOL NARAYAN VILLAS?

The completion date filed with UPRERA is 5 Jan 2029. No completion certificate is on record yet.

Who is the builder of PHOOL NARAYAN VILLAS?

JANG BAHADUR SINGH is the promoter entity that filed PHOOL NARAYAN VILLAS with UPRERA (promoter RERA ID UPRERAPRM100367). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does PHOOL NARAYAN VILLAS have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is PHOOL NARAYAN VILLAS located?

PHOOL NARAYAN VILLAS is registered in HARUNAGLA, Bareilly, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗