Timeline Bar

Registered31 Jul 2017
Promised21 Sept 2023
NCLT25 Feb 2025

Timeline

Promised completion21 Sept 2023
Revised completion21 Sept 2023
Actual completion
Possession delay34 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,40,000
Project cost (in ₹ Lakhs)₹1,231 Lakhs
Project duration102 months
Project categoryResidential
Locality
Original start date23 Jun 2011
Proposed start date22 Sept 2015

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator6389022193
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
4077219 Aug 201618 Aug 202121 Sept 202318 Aug 2024

Land Parcels

Khasra No.AreaPlot Type
1299, 1300, 1301, 1302, 1306, 1396, 1397, 1398, 1326994.26 Sq. Meters
1299160Khasra
1300160Khasra
13013160Khasra
1302630Khasra
1306190Khasra
139619600Khasra
1397510Khasra
1398310Khasra
1399310Khasra
14003410Khasra

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
229330 Jan 2014
2707 Jan 2011
22728 Feb 2013
299628 Feb 2011
57022 Nov 2012
1844 May 2012

Frequently Asked Questions

What is the RERA registration number of ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY?

The RERA registration number of ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY is UPRERAPRJ7132, as recorded on the UP-RERA portal.

What is the RERA status of ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY?

As reported by UP-RERA, the status of ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY is "NCLT".

Where is ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY located?

As reported to UP-RERA, ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY is located at Sarojini Nagar, Lucknow, Uttar Pradesh.

When will ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY be completed?

The latest completion date reported to UP-RERA for ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY is 21 Sept 2023.

Is ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY delayed?

Measured against the latest completion date reported to UP-RERA, ANSAL API - POCKET 3 SECTOR P SUSHANT GOLF CITY is 34 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026