Timeline Bar
Registered11 Aug 2017
Promised31 Dec 2018
Completed16 Feb 2024
Timeline
Promised completion31 Dec 2018
Revised completion—
Actual completion16 Feb 2024
Possession delay62 mo delay
Registration & Cost Details
Registration fee (in ₹)₹2,91,500
Project cost (in ₹ Lakhs)₹93,33,00,000 Lakhs
Project duration56 months
Project categoryResidential
Locality—
Original start date17 Jun 2010
Proposed start date12 May 2014
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9718407818
Emailkushagr.ansal@ansals.com
Coordinator9810605517
Address606, 6th Floor Indraprakash, 21 Barakhamba Road, New Delhi 110001
No promoter data available.
Quarterly Progress Reports
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 1573/2,1574/2,15753/3,1576/2,1581/1,1580,1579,1578 | 1.5891,1/2 Hectare | — |
| 1573/2,1572/2,1575/3,1576/2,1578,1579,1581/1,1580, | 1.2713,1/4Hectare | — |
| 1573/2,1574/2,1575/3,1576/2,1578,1579,1581/1,1580, | 0.3178 Hectare | — |
| 1573/2,1572/2,1575/3,1576/2,1578,1579,1581/1,1580, | 0.2682,1/2 Hectare | — |
| 1573/2,1572/2,1575/3,1576/2,1578,1579,1581/1,1580, | 0.2460 Hectare | — |
| 21/1 | 0.0240 Hectare | — |
| 1561,1566/2,1567/2,1568/1,1570/2,1664/2,1667,1669M | 1.3397,1/2 Hectare | — |
| 1561,1566/2,1567/2,1664/2,1667,1669,1678Min,1679Mi | 1.3397,1/2 Hectare | — |
| 1562,1565Min,1569,1570,1571Min,1572,1574,1575Min,1 | 1.6490 Hectare | — |
| 1561,1566/2,1567/2,1568/1,1570/2,1664/2,1667,1669M | 1.0220 Hectare | — |
| 1571/2Min,1575/2,1573/1,1583,1668,1671/1 | 0.3870 Hectare | — |
| 1570/1 | .0130 Hectare | — |
| 1588,1563/1,1564/1,1570/1Min,1589Min | .3324,5/6 Hectare | — |
| 1577 | .0285 Hectare | — |
| 1577 | .0095 Hectare | — |
| 1590/1 | .0060 Hectare | — |
| 1570/2Min | .0036 Hectare | — |
| 1570/2Min | .0144 Hectare | — |
| 1561,1566/2,1567/2,1568/1,1570/2Min,1586/1Min | .3111 Hectare | — |
| 20/1Min | .7000 Hectare | — |
| 1591/1,1720/1Min | .0310 Hectare | — |
| 1563/1,1564/1,1570/1Min | .1037,1/3 Hectare | — |
| 1563/1,1564/1,1570/1Min | .0188,61/100 Hectare | — |
| 20/1Min,21/1 | .3070 Hectare | — |
| 20/1Min | 1.3500 Hectare | — |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 10616 | 3 Nov 2006 | — | — |
| 10387 | 30 Oct 2006 | — | — |
| 12057 | 26 Nov 2007 | — | — |
| 5772 | 3 Jun 2006 | — | — |
| 1587 | 13 Feb 2008 | — | — |
| 12633 | 5 Dec 2008 | — | — |
| 279 | 12 Jan 2007 | — | — |
| 280 | 12 Jan 2007 | — | — |
| 4064 | 11 Apr 2008 | — | — |
| 4062 | 11 Apr 2008 | — | — |
| 115 | 4 Jan 2007 | — | — |
| 12631 | 5 Dec 2008 | — | — |
| 7138 | 7 Jul 2008 | — | — |
| 7253 | 19 Jul 2006 | — | — |
| 9670 | 19 Sept 2007 | — | — |
| 2032 | 20 Feb 2010 | — | — |
| 2883 | 12 Mar 2010 | — | — |
| 6577 | 21 May 2010 | — | — |
| 6576 | 21 May 2010 | — | — |
| 172 | 7 Jan 2009 | — | — |
| 12629 | 5 Dec 2008 | — | — |
| 2028 | 20 Feb 2010 | — | — |
| 9662 | 7 Jul 2014 | — | — |
| 10230 | 18 Jul 2014 | — | — |
| 4061 | 11 Apr 2008 | — | — |
| 4063 | 11 Apr 2008 | — | — |
Frequently Asked Questions
What is the RERA registration number of ANSAL TOWN MEERUT PHASE-III?
The RERA registration number of ANSAL TOWN MEERUT PHASE-III is UPRERAPRJ6019, as recorded on the UP-RERA portal.
What is the RERA status of ANSAL TOWN MEERUT PHASE-III?
As reported by UP-RERA, the status of ANSAL TOWN MEERUT PHASE-III is "Registered".
Where is ANSAL TOWN MEERUT PHASE-III located?
As reported to UP-RERA, ANSAL TOWN MEERUT PHASE-III is located at Sardhana, Meerut, Uttar Pradesh.
Is ANSAL TOWN MEERUT PHASE-III completed?
As reported to UP-RERA, ANSAL TOWN MEERUT PHASE-III was completed on 16 Feb 2024.
Is ANSAL TOWN MEERUT PHASE-III delayed?
Measured against the latest completion date reported to UP-RERA, ANSAL TOWN MEERUT PHASE-III is 62 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026