APEX NORTH CITYUPRERADelayed 4 mo
Home › Projects › Meerut › APEX NORTH CITY

APEX NORTH CITY

UPRERADelayed 4 moRegisteredConstruction 100% · 2025 Q3updated 4 Aug 2026

APEX NORTH CITY is a RERA-registered real-estate project in Meerut (RERA ID UPRERAPRJ291313). Its RERA-registered completion deadline (31 Mar 2026) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
4 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹48
Land area
not reported
Units
not reported
Density (derived)
not reported
Towers
not reported
Config
not reported
Carpet
not reported
Registered
28 Nov 2023

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2025 Q3
—Q4'23
—Q1'24
—Q2'24
—Q3'24
—Q4'24
—Q1'25
100%Q2'25
100%Q3'25

Basic details

RERA IDUPRERAPRJ291313
Applicant typeCompany
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start16 Aug 2023
Project duration32
AddressMeerut, Meerut

Registration & timeline

RERA registered28 Nov 2023
Promised completion31 Mar 2026
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹5,10,000

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
MDA/LD/22-23/106116 Aug 202321 Aug 202831 Mar 2026

Land & documents

26 filings
KhasraAreaType
3713467Khasra
3763693Khasra
376527.62Khasra
3765866Khasra
3762462Khasra
3764924Khasra
3767387Khasra
3763165Khasra
3842038Khasra
3847134Khasra
3841019Khasra
4013910Khasra
4012500Khasra
3831110Khasra
3711733Khasra
3763693Khasra
3842039Khasra
3934603.20Khasra
394270Khasra
3941360Khasra
4498850Khasra
44913280Khasra
4496850Khasra
450760Khasra
3763693Khasra
393-394-395-3826142Khasra

Quarterly progress reports

10 filed reports
QuarterConstructionCertificatesSource
2023-Q2—CA · Arch · Engview ↗
2023-Q3—CA · Arch · Engview ↗
2023-Q4—CA · Arch · Engview ↗
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q2100%CA · Arch · Engview ↗
2025-Q3100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3.

Nearby projects

Meerut

Other projects registered in Meerut.

"Ornate"
UPRERA ▲ 76 mo
131/144 Type Duplex and 69/142 Type Residential Houses in Sector-3, Scheme No. 11, Jagriti Vihar (Ext.), Meerut
UPRERA ▲ 15 mo
528 FLATS IN AIRPORT ENCLAVE, SECTOR-10, SHATABDI NAGAR, MEERUT
UPRERA ▲ 67 mo
A2Z COLONY
UPRERA no delay on record
Aashiyana Green Wood
UPRERA ▲ 16 mo
Abdullah Residency and Shoping Plaza
UPRERA no delay on record

Common questions about APEX NORTH CITY

Is APEX NORTH CITY RERA registered?

Yes. APEX NORTH CITY is registered with UPRERA under registration number UPRERAPRJ291313, registered on 28 Nov 2023. Estanzo reproduces that filing; it does not verify the work behind it.

Is APEX NORTH CITY delayed?

APEX NORTH CITY is 4 months past the completion date filed with UPRERA (31 Mar 2026), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is APEX NORTH CITY located?

APEX NORTH CITY is registered in Meerut, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 4 mo
QPR filingNo default reported
DistrictMeerut
Last updated4 Aug 2026

Location

AddressMeerut
View on map ↗

RERA buyer helpline

Coordinator7500314262
official grievance contact, as published by RERA