Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi

UPRERARegistered

Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi is a RERA-registered residential project by Meerut Development Authority in Meerut (RERA ID UPRERAPRJ966656). Registered with a completion deadline of 25 Nov 2022.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ966656
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMeerut Development Authority
Proposed start1 Nov 2019
Project duration37 months
AddressMeerut, Meerut
TehsilMeerut
Applicant typeCompetent authority
Applicant addressCivil Lines, Vikas Bhawan, Meerut - 250001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Registered with RERA

  3. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. to

    Extension granted

  6. to

    Extension granted

  7. to

    Extension granted

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered19 Mar 2020
Original completion30 Aug 2020
Revised completion25 Nov 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,23,000
Sanctioning authorityMeerut Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors576 · 12 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK57612-23
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block No 1 · 1 BHK44823
Block No 10 · 1 BHK44823
Block No 11 · 1 BHK44823
Block No 12 · 1 BHK44823
Block No 2 · 1 BHK44823
Block No 3 · 1 BHK44823
Block No 4 · 1 BHK44812-23
Block No 5 · 1 BHK44823
Block No 6 · 1 BHK44823
Block No 7 · 1 BHK44823
Block No 8 · 1 BHK44823
Block No 9 · 1 BHK44823
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
NA
License NA
NA
Engineer
Varun Tyagi
Ist Floor Sharma Market Opposite Nai Sarak Meerut-250004
Contractor
Ms Sunil Garg And Company
150, East Model Town Ghaziabad, 201001
Sr.Development work declared to RERA
1Demarcation of Plots
Yes
2Boundary Wall
No
3Road Work
Yes. Internal Road will be made with interlocking tiles/Cement concrete as per direction of UP Government.
4Footpaths
Yes
5Water Supply Including Drinking Water Facilities
Yes. Jal Nigam will provide the water facilities.
6Sewer System
Yes. Sewer Line will be connect to existing STP at Jagriti Vihar, Garh Road, Meerut.
7Drain
Yes. U type Drain will be construct and connect to existing Nala at Jagriti Vihar, Garh Road, Meerut.
8Parks
Yes. Park will be construct by Meerut Development Authority, Meerut
9Tree Planting
Yes.. Arboriculture work will carried out by the Horticulture Department of Meerut Development Authority, Meerut
10Design For Electric Supply Including Street Lighting
Yes.. Electricity will be provided by UPPCL, Meerut.
11Community Buildings
No
12Treatment and Disposal System of Sewage and Sullage water
No
13Solid Waste Management And Disposal System
No
14Water Conservation System
No
15Energy Management System Including Use of Renewable Energy
No
16Fire Protection And Fire Safety System
No
17Social Infrastructure And Other Public Amenities Including Public Health Services
Yes
18Emergency Evacuation Services
Yes
19Other Miscellaneous Work
Yes
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 30 Aug 2020.

Sanctioned by Meerut Development Authority · 23,539 sqm of land · an approved plan of 12 blocks and 576 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
1564/PMAY/SECEMDAMRT30 Aug 202030 Aug 202026 Aug 2022
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 4 completion extensions for this project, the latest running to 25 Nov 2022.

#Granted fromExtended uptoNote
130 Aug 202028 Feb 2021Six months extension in view of force majeure caused by covid-19 pandemic
228 Feb 202127 Feb 2022—
327 Feb 202226 Aug 2022—
426 Aug 202225 Nov 2022—

Land & documents

21 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
137,138,147,149,150,151,152,157,158,159,160,16323539Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1422-1427
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New4 Mar 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New28 Jan 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New26 Feb 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New28 Jan 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New4 Mar 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New4 Mar 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New4 Mar 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New4 Mar 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New4 Mar 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New4 Mar 2020 ↗

Quarterly progress reports

1 filed report

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

1 quarterly progress report is on file with UPRERA, for 2022-Q2.

QuarterConstructionCertificates
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMeerut Development Authority
RolePromoter · current
RERA IDUPRERAPRM14597
PANAAALM0124D
CIN / TANMRTM00138F
Registered addressCivil Lines, Vikas Bhawan, Meerut - 250001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
MDABankAllahabad BankBranchMDA CampusA/C no.IFSCALLA0212075
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi

Is Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi RERA registered?

Yes. Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi is registered with UPRERA under registration number UPRERAPRJ966656, registered on 19 Mar 2020. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?

The completion date filed with UPRERA is 25 Nov 2022. No completion certificate is on record yet.

Who is the builder of Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?

Meerut Development Authority is the promoter entity that filed Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi with UPRERA (promoter RERA ID UPRERAPRM14597). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi more time to complete?

UPRERA's record carries 4 completion extensions for Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi, the latest running to 25 Nov 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi located?

Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi is registered in Meerut, as filed with UPRERA.

What configurations are available in Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?

The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?

The approved unit plan filed with UPRERA runs from 12 to 23 m² of carpet area (about 129 to 245 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?

The approved unit plan describes 12 blocks and 576 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?

About 99 units per acre: 576 planned units across 5.82 acres (23,539 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗