Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi is a RERA-registered residential project by Meerut Development Authority in Meerut (RERA ID UPRERAPRJ966656). Registered with a completion deadline of 25 Nov 2022.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ966656 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Meerut Development Authority |
| Proposed start | 1 Nov 2019 |
| Project duration | 37 months |
| Address | Meerut, Meerut |
| Tehsil | Meerut |
| Applicant type | Competent authority |
| Applicant address | Civil Lines, Vikas Bhawan, Meerut - 250001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
- to
Extension granted
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 19 Mar 2020 |
| Original completion | 30 Aug 2020 |
| Revised completion | 25 Nov 2022 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹1,23,000 |
| Sanctioning authority | Meerut Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 576 | 12-23 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Block No 1 · 1 BHK | 4 | 48 | 23 |
| Block No 10 · 1 BHK | 4 | 48 | 23 |
| Block No 11 · 1 BHK | 4 | 48 | 23 |
| Block No 12 · 1 BHK | 4 | 48 | 23 |
| Block No 2 · 1 BHK | 4 | 48 | 23 |
| Block No 3 · 1 BHK | 4 | 48 | 23 |
| Block No 4 · 1 BHK | 4 | 48 | 12-23 |
| Block No 5 · 1 BHK | 4 | 48 | 23 |
| Block No 6 · 1 BHK | 4 | 48 | 23 |
| Block No 7 · 1 BHK | 4 | 48 | 23 |
| Block No 8 · 1 BHK | 4 | 48 | 23 |
| Block No 9 · 1 BHK | 4 | 48 | 23 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Yes |
| 2 | Boundary Wall No |
| 3 | Road Work Yes. Internal Road will be made with interlocking tiles/Cement concrete as per direction of UP Government. |
| 4 | Footpaths Yes |
| 5 | Water Supply Including Drinking Water Facilities Yes. Jal Nigam will provide the water facilities. |
| 6 | Sewer System Yes. Sewer Line will be connect to existing STP at Jagriti Vihar, Garh Road, Meerut. |
| 7 | Drain Yes. U type Drain will be construct and connect to existing Nala at Jagriti Vihar, Garh Road, Meerut. |
| 8 | Parks Yes. Park will be construct by Meerut Development Authority, Meerut |
| 9 | Tree Planting Yes.. Arboriculture work will carried out by the Horticulture Department of Meerut Development Authority, Meerut |
| 10 | Design For Electric Supply Including Street Lighting Yes.. Electricity will be provided by UPPCL, Meerut. |
| 11 | Community Buildings No |
| 12 | Treatment and Disposal System of Sewage and Sullage water No |
| 13 | Solid Waste Management And Disposal System No |
| 14 | Water Conservation System No |
| 15 | Energy Management System Including Use of Renewable Energy No |
| 16 | Fire Protection And Fire Safety System No |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Yes |
| 18 | Emergency Evacuation Services Yes |
| 19 | Other Miscellaneous Work Yes |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 30 Aug 2020.
Sanctioned by Meerut Development Authority · 23,539 sqm of land · an approved plan of 12 blocks and 576 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 1564/PMAY/SECEMDAMRT | 30 Aug 2020 | 30 Aug 2020 | 26 Aug 2022 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
UPRERA’s record carries 4 completion extensions for this project, the latest running to 25 Nov 2022.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 30 Aug 2020 | 28 Feb 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 28 Feb 2021 | 27 Feb 2022 | — |
| 3 | 27 Feb 2022 | 26 Aug 2022 | — |
| 4 | 26 Aug 2022 | 25 Nov 2022 | — |
Land & documents
21 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 137,138,147,149,150,151,152,157,158,159,160,163 | 23539 | Khasra |
| Khatauni extract · 1422-1427 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | not reported | — |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | not reported | — |
| Water supply plan How the project proposed to supply water, as filed at registration. | not reported | — |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 4 Mar 2020 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 28 Jan 2020 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 26 Feb 2020 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 28 Jan 2020 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 4 Mar 2020 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 4 Mar 2020 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 4 Mar 2020 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 4 Mar 2020 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 4 Mar 2020 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 4 Mar 2020 ↗ |
Quarterly progress reports
1 filed report
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
1 quarterly progress report is on file with UPRERA, for 2022-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Meerut Development Authority |
| Role | Promoter · current |
| RERA ID | UPRERAPRM14597 |
| PAN | AAALM0124D |
| CIN / TAN | MRTM00138F |
| Registered address | Civil Lines, Vikas Bhawan, Meerut - 250001 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Meerut
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | MDABankAllahabad BankBranchMDA CampusA/C no.IFSCALLA0212075 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi
Is Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi RERA registered?
Yes. Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi is registered with UPRERA under registration number UPRERAPRJ966656, registered on 19 Mar 2020. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?
The completion date filed with UPRERA is 25 Nov 2022. No completion certificate is on record yet.
Who is the builder of Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?
Meerut Development Authority is the promoter entity that filed Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi with UPRERA (promoter RERA ID UPRERAPRM14597). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi more time to complete?
UPRERA's record carries 4 completion extensions for Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi, the latest running to 25 Nov 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi located?
Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi is registered in Meerut, as filed with UPRERA.
What configurations are available in Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?
The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?
The approved unit plan filed with UPRERA runs from 12 to 23 m² of carpet area (about 129 to 245 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?
The approved unit plan describes 12 blocks and 576 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Pradhanmantri Awasiya Yojana 576 Flats in Gram Saria Kazi?
About 99 units per acre: 576 planned units across 5.82 acres (23,539 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗