Estanzo

Timeline Bar

Registered5 Aug 2017
Promised31 Dec 2017
Completed26 Apr 2019

Timeline

Promised completion31 Dec 2017
Revised completion31 Dec 2017
Actual completion26 Apr 2019
Possession delay16 mo delay

Registration & Cost Details

Registration fee (in ₹)₹62,000
Project cost (in ₹ Lakhs)₹15,600 Lakhs
Project duration31 months
Project categoryResidential
Locality
Original start date18 Jun 2014
Proposed start date18 Jun 2015

Inventory

Total units496
Unit TypeUnitsCarpet Area (sqm)
2 BHK14667.77–69
3 BHK30482.02–85.41
4 BHK19145.43
SHOP2713.44–124.26

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9899996528
Emailinfo.infrra@arihantgroup.co.in
Coordinator8447731805
AddressARIHANT INFRRA REALTORS PRIVATE LIMITED OFFICE NO. 601, PLOT NO. 17, 6TH FLOOR,, SACHDEVA TOWER, CO

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BP2487/GH/FB/3430

Revalidated: BP-2487/44/FS-5023 (18 Jun 2015)

18 Jun 201516 May 2018

Revalidated upto: 18 Jun 2020

31 Dec 201718 Jun 2025

Land Parcels

Khasra No.AreaPlot Type
GH-07A, Sector-1, Greater Noida West39400Plot

Approved Unit Plan

Unit plan rows on file230
Total flats (sum of rows)496
Total shops27
BlocksBLOCK K, BLOCK L, BLOCK M, BLOCK N
Floor types2 BHK, 3 BHK, 4 BHK, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of arihant arden phase 3( towers K,L,M,N)?

The RERA registration number of arihant arden phase 3( towers K,L,M,N) is UPRERAPRJ8415, as recorded on the UP-RERA portal.

What is the RERA status of arihant arden phase 3( towers K,L,M,N)?

As reported by UP-RERA, the status of arihant arden phase 3( towers K,L,M,N) is "Registered".

Where is arihant arden phase 3( towers K,L,M,N) located?

As reported to UP-RERA, arihant arden phase 3( towers K,L,M,N) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is arihant arden phase 3( towers K,L,M,N) completed?

As reported to UP-RERA, arihant arden phase 3( towers K,L,M,N) was completed on 26 Apr 2019.

Is arihant arden phase 3( towers K,L,M,N) delayed?

Measured against the latest completion date reported to UP-RERA, arihant arden phase 3( towers K,L,M,N) is 16 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026