Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ3579
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryU.P. Awas Evam Vikas Parishad
Proposed start18 Oct 2015
Original start18 Oct 2015
Project duration64 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant address5/50, VINEET KHAND, GOMTI NAGAR, LUCKNOW-226010
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    917

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Completion certificate filed

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered1 Aug 2017
Original completion31 Jul 2020
Revised completion30 Jan 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary29 Oct 2020
Registration fee₹38,500
Sanctioning authorityU.P. Awas Evam Vikas Parishad

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors144 · 2 · 12 (units from plan)
  • 3 BHK50 35%
  • 2 BHK48 33%
  • OTHER46 32%
ConfigurationUnitsCarpet area
2 BHK4862
3 BHK50103-114
OTHER46114
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · 2 BHK, 3 BHK, OTHER127262-114
B · 2 BHK, 3 BHK, OTHER127262-114
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VANDANA SRIVASTAVA
License CA/95/18946
13/262 A INDIRANAGAR LUCKNOW
Engineer
MADAN SINGH
S.F.-202 AMBER VIHAR COLONY,PAKKAPUL,BANDHA ROAD LUCKNOW-22
Contractor
SWARNABHUMI INFRAVENTURES PRIVATE LIMITED
2/169,VIVEK KHAND ,LUCKNOW ,U.P
Sr.Development work declared to RERA
1Demarcation of Plots
COMPLETED
2Boundary Wall
COMPLETED
3Road Work
IN-PROCESS
4Footpaths
IN-PROCESS
5Water Supply Including Drinking Water Facilities
IN-PROCESS
6Sewer System
IN-PROCESS
7Drain
IN-PROCESS
8Parks
IN-PROCESS
9Tree Planting
IN-PROCESS
10Design For Electric Supply Including Street Lighting
IN-PROCESS
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
IN-PROCESS
13Solid Waste Management And Disposal System
AS PER MCD
14Water Conservation System
IN-PROCESS
15Energy Management System Including Use of Renewable Energy
IN-PROCESS
16Fire Protection And Fire Safety System
IN-PROCESS
17Social Infrastructure And Other Public Amenities Including Public Health Services
IN-PROCESS
18Emergency Evacuation Services
IN-PROCESS
19Other Miscellaneous Work
IN-PROCESS
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 24 Apr 2019.

Sanctioned by U.P. Awas Evam Vikas Parishad · 6,650 sqm of land · an approved plan of 2 blocks and 144 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
91725 Apr 201424 Apr 201923 Apr 202231 Jul 2020
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Jan 2021.

#Granted fromExtended uptoNote
131 Jul 202030 Jan 2021Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
13C6650Plot
13c6650Plot
13C6650Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 16736
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 12075
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New15 Oct 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New15 Oct 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New17 Oct 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New15 Oct 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New15 Oct 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New15 Oct 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New15 Oct 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New15 Oct 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New15 Oct 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New15 Oct 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New15 Oct 2019 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old28 Feb 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterPROVIDED
Fire safety (as filed with RERA)PROVIDED
Renewable energySOLAR ENERGY PARTIALLY
Other facilitiesCLUB,GYM,SWIMMING POOL,PLAY AREA,LANDSCAPED AREA,SECURITY,POWER BACK UP, STP , RWH, WATER FILTERATION PLANT , GAS PIPE LINE , CAR WASHING FACILITY ETC

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

5 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

5 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameARSHA INFRADEVELOPERS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM2725
PANAAHCA9967C
CIN / TANU45400UP2009PTC038233
Name of chairmanMathuresh Srivastava
Registered address5/50, VINEET KHAND, GOMTI NAGAR, LUCKNOW-226010
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
ARSHA INFRADEVELOPERS PRIVATE LIMITEDBankKOTAK MAHINDRA BANKBranchGOMTI NAGARA/C no.IFSCKKBK0005196
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about ARSHA SUMANGALAM

Is ARSHA SUMANGALAM RERA registered?

Yes. ARSHA SUMANGALAM is registered with UPRERA under registration number UPRERAPRJ3579, registered on 1 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has ARSHA SUMANGALAM been completed?

UPRERA still lists ARSHA SUMANGALAM as Registered, so it is not shown as completed here. A completion certificate dated 29 Oct 2020 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of ARSHA SUMANGALAM?

ARSHA INFRADEVELOPERS PRIVATE LIMITED is the promoter entity that filed ARSHA SUMANGALAM with UPRERA (promoter RERA ID UPRERAPRM2725). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted ARSHA SUMANGALAM more time to complete?

UPRERA's record carries 1 completion extension for ARSHA SUMANGALAM, the latest running to 30 Jan 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does ARSHA SUMANGALAM have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ARSHA SUMANGALAM located?

ARSHA SUMANGALAM is registered in Lucknow, as filed with UPRERA.

What configurations are available in ARSHA SUMANGALAM?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in ARSHA SUMANGALAM?

The approved unit plan filed with UPRERA runs from 62 to 114 m² of carpet area (about 665 to 1,229 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in ARSHA SUMANGALAM?

The approved unit plan describes 2 blocks and 144 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is ARSHA SUMANGALAM?

About 88 units per acre: 144 planned units across 1.64 acres (6,650 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗