Timeline Bar

Registered2 Aug 2017
Promised31 Dec 2022
Today4 Aug 2026

Timeline

Promised completion31 Dec 2022
Revised completion31 Dec 2022
Actual completion
Possession delay43 mo delay

Registration & Cost Details

Registration fee (in ₹)₹4,94,500
Project cost (in ₹ Lakhs)₹63,687 Lakhs
Project duration81 months
Project categoryResidential
Locality
Original start date1 Oct 2016
Proposed start date1 Oct 2016

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emailcelerity@atsgreens.com
Coordinator9643007884
AddressATS Tower, Plot-16, Sector-135, Noida-201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
M/V/N/2016/IV-14785 Aug 20164 Aug 202131 Dec 20224 Aug 2026
NOIDA/M/V/N/2016/IV-1478/922

Revalidated: NOIDA/M/V/N/2016/IV-1478/922 (5 Aug 2016)

5 Aug 20164 Aug 2021

Revalidated upto: 1 Jan 1900

31 Dec 20224 Aug 2026

Land Parcels

Khasra No.AreaPlot Type
PLOT NO- SC-01/C,A2,A4,A6,A11 & A12,SEC-150,NOIDA97813Plot

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
54107 Jun 2014
602915 Sept 2015
284424 Apr 2015

Frequently Asked Questions

What is the RERA registration number of ATS PRISTINE GOLF VILLAS ( Phase -1 )?

The RERA registration number of ATS PRISTINE GOLF VILLAS ( Phase -1 ) is UPRERAPRJ3796, as recorded on the UP-RERA portal.

What is the RERA status of ATS PRISTINE GOLF VILLAS ( Phase -1 )?

As reported by UP-RERA, the status of ATS PRISTINE GOLF VILLAS ( Phase -1 ) is "Registered".

Where is ATS PRISTINE GOLF VILLAS ( Phase -1 ) located?

As reported to UP-RERA, ATS PRISTINE GOLF VILLAS ( Phase -1 ) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will ATS PRISTINE GOLF VILLAS ( Phase -1 ) be completed?

The latest completion date reported to UP-RERA for ATS PRISTINE GOLF VILLAS ( Phase -1 ) is 31 Dec 2022.

Is ATS PRISTINE GOLF VILLAS ( Phase -1 ) delayed?

Measured against the latest completion date reported to UP-RERA, ATS PRISTINE GOLF VILLAS ( Phase -1 ) is 43 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026