Registered22 Jul 2019
Promised25 Apr 2024
Today4 Aug 2026

Timeline

Promised completion25 Apr 2024
Revised completion25 Apr 2024
Actual completion
Possession delay27 mo delay

Registration & Cost Details

Registration fee (in ₹)₹85,000
Project cost (in ₹ Lakhs)₹32,550 Lakhs
Project duration64 months
Project categoryResidential
Locality
Original start date
Proposed start date15 Jul 2019

Inventory

Total units231
Unit TypeUnitsCarpet Area (sqm)
3 BHK183130.67–153.75
4 BHK42156.45–201.87
PENTHOUSE6274.43–547.761

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9999697788
Emailsumit@bcc.in
Coordinator7838191972
AddressPlot No. 19A, Sector 16A, Filmcity, Noida Gautam Buddha Nagar, UP -201301

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Noida/ CAP/2019/ IV-1522/ 111826 Apr 201925 Apr 202425 Apr 202425 Apr 2029

Land Parcels

Khasra No.AreaPlot Type
SC-01/ C-A 10, Sportcity, Sector 150, Noida16000Plot

Approved Unit Plan

Unit plan rows on file231
Total flats (sum of rows)231
BlocksTower A, Tower B
Floor types3 BHK, 4 BHK, PENTHOUSE

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of The Resident Tower?

The RERA registration number of The Resident Tower is UPRERAPRJ987428, as recorded on the UP-RERA portal.

What is the RERA status of The Resident Tower?

As reported by UP-RERA, the status of The Resident Tower is "Registered".

Where is The Resident Tower located?

As reported to UP-RERA, The Resident Tower is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will The Resident Tower be completed?

The latest completion date reported to UP-RERA for The Resident Tower is 25 Apr 2024.

Is The Resident Tower delayed?

Measured against the latest completion date reported to UP-RERA, The Resident Tower is 27 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026