Timeline Bar
Registered14 Aug 2017
Promised31 Dec 2017
Completed28 Jul 2020
Timeline
Promised completion31 Dec 2017
Revised completion—
Actual completion28 Jul 2020
Possession delay31 mo delay
Registration & Cost Details
Registration fee (in ₹)₹94,000
Project cost (in ₹ Lakhs)₹16,937 Lakhs
Project duration82 months
Project categoryResidential
Locality—
Original start date19 Mar 2011
Proposed start date19 Mar 2011
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeSocieties
Mobile9818396678
EmailRCOGN3@GMAIL.COM
Coordinator9818396678
AddressAWHO, SOUTH HUTMENTS, KASHMIR HOUSE, RAJAJI MARG, NEW DELHI-110011
No promoter data available.
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| Plot No-10, Informal Sector | 17730.02sqm | — |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 4284 | 12 Feb 2009 | — | — |
Frequently Asked Questions
What is the RERA registration number of AWHO GURJINDER VIHAR PHASE-IV?
The RERA registration number of AWHO GURJINDER VIHAR PHASE-IV is UPRERAPRJ4197, as recorded on the UP-RERA portal.
What is the RERA status of AWHO GURJINDER VIHAR PHASE-IV?
As reported by UP-RERA, the status of AWHO GURJINDER VIHAR PHASE-IV is "Registered".
Where is AWHO GURJINDER VIHAR PHASE-IV located?
As reported to UP-RERA, AWHO GURJINDER VIHAR PHASE-IV is located at N/A, Gautam Budh Nagar, Uttar Pradesh.
Is AWHO GURJINDER VIHAR PHASE-IV completed?
As reported to UP-RERA, AWHO GURJINDER VIHAR PHASE-IV was completed on 28 Jul 2020.
Is AWHO GURJINDER VIHAR PHASE-IV delayed?
Measured against the latest completion date reported to UP-RERA, AWHO GURJINDER VIHAR PHASE-IV is 31 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.