Estanzo

Timeline Bar

Registered11 Apr 2018
Promised19 Sept 2021
Today3 Aug 2026

Timeline

Promised completion19 Sept 2021
Revised completion19 Sept 2021
Actual completion
Possession delay58 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,08,500
Project cost (in ₹ Lakhs)₹9,700 Lakhs
Project duration99 months
Project categoryResidential
Locality
Original start date
Proposed start date7 Jan 2014

Inventory

Total units1056
Unit TypeUnitsCarpet Area (sqm)
1 BHK28843.587
2 BHK43264.149
3 BHK33685.24–86.52

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8787284276
Emailbccbuildtech@gmail.com
Coordinator7705004129
Address4th Floor Ganj Trade Center,10 Capper Road Lalbagh Lucknow

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1100.0%
2020-Q2100.0%
2020-Q3100.0%
2020-Q4100.0%
2021-Q1100.0%
2021-Q2100.0%
2021-Q3100.0%
2021-Q4100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
33720 Sept 201319 Sept 201819 Sept 202119 Sept 2021
33720 Sept 201319 Sept 201819 Sept 202119 Sept 2021

Land Parcels

Khasra No.AreaPlot Type
511935
5119405
51110340

Approved Unit Plan

Unit plan rows on file60
Total flats (sum of rows)1056
BlocksA, B, C, D, E
Floor types1 BHK, 2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
137149 Nov 2017
1563220 Dec 2017
111925 Jan 2018

Frequently Asked Questions

What is the RERA registration number of BCC GREENS?

The RERA registration number of BCC GREENS is UPRERAPRJ15533, as recorded on the UP-RERA portal.

What is the RERA status of BCC GREENS?

As reported by UP-RERA, the status of BCC GREENS is "Registered".

Where is BCC GREENS located?

As reported to UP-RERA, BCC GREENS is located at Lucknow, Lucknow, Uttar Pradesh.

When will BCC GREENS be completed?

The latest completion date reported to UP-RERA for BCC GREENS is 19 Sept 2021.

Is BCC GREENS delayed?

Measured against the latest completion date reported to UP-RERA, BCC GREENS is 58 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.