Canary Phase 2 is a RERA-registered real-estate project in Lucknow (RERA ID UPRERAPRJ8652). Its RERA-registered completion deadline (28 Mar 2024) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ8652 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Apr 2017 |
| Original start | 1 Apr 2017 |
| Project duration | 84 |
| Address | Lucknow, Lucknow |
| RERA registered | 11 Aug 2017 |
| Promised completion | 30 Sept 2022 |
| Revised completion | 28 Mar 2024 |
| Completion certificate filed | — not on record |
| Registration fee | ₹29,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 357 | 28 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 281 | 13 Aug 2015 | 12 Aug 2020 | 30 Sept 2022 |
| 1019 | 25 Jul 2018 | 24 Jul 2023 | 30 Sept 2022 |
| 1019 | 25 Jul 2018 | 24 Jul 2023 | 29 Mar 2023 |
| 1019 | 25 Jul 2018 | 24 Jul 2023 | 28 Mar 2024 |
| Khasra | Area | Type |
|---|---|---|
| 210 | 3000.4 | — |
| 211 | 278.12 | — |
| 212 | 609 | — |
| 213 | 300 | — |
| 215 | 600 | — |
| 210 | 3058 | Khasra |
| 211 | 120 | Khasra |
| 212 | 609 | Khasra |
| 213 | 400 | Khasra |
| 215 | 600 | Khasra |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 23512 | 1 Nov 2014 | — | — |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | — | CA · Arch · Eng | view ↗ |
| 2023-Q4 | — | CA · Arch · Eng | view ↗ |
Yes. Canary Phase 2 is registered with UPRERA under registration number UPRERAPRJ8652, registered on 11 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Canary Phase 2 is 28 months past the completion date filed with UPRERA (28 Mar 2024), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Canary Phase 2 is registered in Lucknow, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗